PPQ For VISN 8 AE IDIQ.docx

DOCX document 21 KB Posted

Attached to
C1DA--VISN 8 Architect Engineering MATOC Federal contract opportunity
Solicitation number
36C24822R0003
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

View the file

Other files for this federal contract opportunity

Other files attached to C1DA--VISN 8 Architect Engineering MATOC, newest first.
File Type Posted
36C24822R0003_5.docx DOCX document
4th set of Questions and Answers MATOC 6-28.pdf PDF
36C24822R0003_4.docx DOCX document
Modification to Previous Pre-Sol Notice - Q and A 6-24.pdf PDF
36C24822R0003_3.docx DOCX document
Modification to Pre-Sol Notice - Q and A 6-21-22.pdf PDF
36C24822R0003_2.docx DOCX document
Modification to Pre-Sol Notice - Q and A.pdf PDF
Position Definitions (26 pages).pdf PDF
VISN 08 Gographic Areas Graphic.pdf PDF
36C24822R0003.docx DOCX document
S02_RFP_Attachment_AE MATOC Labor Categories current 12-28-21.xlsx XLSX spreadsheet
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AE Synopsis 36C24822R0003, VISN 8 AE MATOC Design and Engineering Services

PAST PERFORMANCE QUESTIONNAIRE

Rating Abbreviations: (O) – Outstanding, (G) - Good, (S) - Satisfactory, (M) - Marginal, and (U) - Unsatisfactory

CONTRACT INFORMATION (Contractor to complete Blocks 1-4)

1. Contractor Information
Firm Name:CAGE Code:
Address:DUNs Number:

Phone Number: Email Address:

Point of Contact: Contact Phone Number:

2. Work Performed as: |_| Prime Contractor |_| Sub Contractor |_| Joint Venture |_| Other Percent of project work performed:

If subcontractor, who was the prime (Name/Phone #):

3. Contract Information Contract Number: Delivery/Task Order Number (if applicable):

Contract Type: |_| Firm Fixed Price |_| Cost Reimbursement |_| Other (Please specify):

Contract Title: Contract Location:

Award Date (mm/dd/yy):

Contract Completion Date (mm/dd/yy):

Actual Completion Date (mm/dd/yy):

Explain Differences:

Original Contract Price (Award Amount):

Final Contract Price (to include all modifications, if applicable):

Explain Differences:

4. Project Description:

Complexity of Work |_| High |_| Med |_| Routine How is this project relevant to project of submission? (Please provide details such as similar equipment, requirements, conditions, etc.)

CLIENT INFORMATION (Client to complete Blocks 5-8)

5. Client Information Name: Title:

Phone Number: Email Address:

6. Describe the client’s role in the project:

7. Date Questionnaire was completed (mm/dd/yy):

8. Client’s Signature:

1. QUALITY:
Circle One For Each Element
a) Quality of technical data/report preparation efforts
O G S M U

a.1. Comments:

b) Ability to meet quality standards specified for technical performance
O G S M U

b.1. Comments:

c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
O G S M U

c.1. Comments:

d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
O G S M U

d.1. Comments:

e) Does the Contractor provide design documents and specifications that are accurate?
O G S M U

e.1. Comments:

2. SCHEDULE/TIMELINESS OF PERFORMANCE:
Circle One For Each Element
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
O G S M U

2.a.1 Comments:

b) Rate the contractor’s use of available resources to accomplish tasks identified in the contract
O G S M U

2.b.1. Comments:

3. CUSTOMER SATISFACTION:
Circle One For Each Element
a) To what extent were the end users satisfied with the project?
O G S M U

3. a.1. Comments:

b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)
O G S M U

3.b.1. Comments:

c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
O G S M U

3.c.1. Comments:

d) Overall customer satisfaction
O G S M U

3.d.1 Comments:

4. MANAGEMENT/ PERSONNEL/LABOR
Circle One For Each Element
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
O G S M U

4.a.1. Comments:

b) Ability to hire, apply, and retain a qualified workforce to this effort
O G S M U

4.b.1 Comments:

c) Government Property Control
O G S M U

4.c.1. Comments:

d) Knowledge/expertise demonstrated by contractor personnel
O G S M U

4.d.1. Comments:

e) Utilization of Small Business concerns
O G S M U

4.e.1. Comments:

f) Ability to simultaneously manage multiple projects with multiple disciplines
O G S M U

4.f.1. Comments:

g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
O G S M U

4.g.1. Comments:

h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
O G S M U

4.h.1. Comments:

5. COST/FINANCIAL MANAGEMENT
Circle One For Each Element
a) Ability to meet the terms and conditions within the contractually agreed price(s)?
O G S M U

5.a.1. Comments:

b) Contractor proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client
O G S M U

5.b.1. Comments:

c) If this is/was a Government cost type contract, please rate the Contractor’s timeliness and accuracy in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
O G S M U

5.c.1. Comments:

d) Is the Contractor’s accounting system adequate for management and tracking of costs? If no, please explain in Remarks section.
Yes No

5.d.1. Comments:

e) If this is/was a Government contract, has/was this contract been partially or completely terminated for default or convenience or are there any pending terminations? Indicate if show cause or cure notices were issued, or any default action in comment section below.
Yes No

5.e.1. Comments:

f) Have there been any indications that the contractor has had any financial problems? If yes, please explain below.
Yes No

5.f.1 Comments:

6. SAFETY/SECURITY
Circle One For Each Element
a) To what extent was the contractor able to maintain an environment of safety, adhere to its approved safety plan, and respond to safety issues? (Includes: following the users rules, regulations, and requirements regarding housekeeping, safety, correction of noted deficiencies, etc.)
O G S M U

6.a.1 Comments:

b) Contractor complied with all security requirements for the project and personnel security requirements.
O G S M U

6.b.1. Comments:

7. GENERAL
Circle One For Each Element
a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
O G S M U

7.a.1. Comments:

b) Compliance with contractual terms/provisions (explain if specific issues)
O G S M U

7.b.1. Comments:

c) Would you hire or work with this firm again? (If no, please explain below)
Yes No

7.c.1. Comments:

d) In summary, provide an overall rating for the work performed by this contractor.
O G S M U

7.d.1. Comments:

Please provide responses to the questions above (if applicable) and/or additional remarks. Furthermore, please provide a brief narrative addressing specific strengths, weaknesses, deficiencies, or other comments which may assist our office in evaluating performance risk (please attach additional pages if necessary):

____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________STRENGHTS:_______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________WEAKNESSES:________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ DEFICIENCIES:_____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________ COMMENTS:________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Past Performance Information provided by: __________________________________________________ (Printed Name) Signature: ________________________________________ Date: ____________________________ Organization: _____________________________________ Phone:____________________________