Plan Preparation Package Manual – Charles County, Maryland
This document is a comprehensive plan preparation and submission manual issued by the Charles County Department of Planning and Growth Management, Codes, Permits & Inspection Services Division (CPIS) in June 2012. The manual establishes standardized format requirements and minimum criteria for the submission of construction plans, reports, and related documents for subdivision, commercial, industrial, institutional, and county capital improvement projects. The manual applies to all development services permits (DS Permits) submitted to Charles County and covers multiple construction disciplines including grading, roads, stormwater management, storm drainage, water and sewer systems, and floodplain studies. The guidelines are mandatory for permit approval, with the county reserving the right to reject incomplete submissions, unclear plans, or documents not properly sealed and signed by licensed design professionals. All applicants must review and comply with applicable county ordinances, the Charles County Road Ordinance, Grading Ordinance, Stormwater Management Ordinance, Storm Drainage Ordinance, Floodplain Management Ordinance, Water and Sewer Ordinance, the Standard Detail Manual, and the Standards and Specifications for Construction Manual before plan submission.
The manual specifies detailed technical requirements for plan sheets, including drafting practices, minimum lettering sizes, graphical scales, symbol usage, and required information for each discipline. Major construction projects must submit separate plan sheets organized in a prescribed sequence, with all drawings measuring 36 inches by 24 inches (with specified margins), while minor construction projects may combine information on standard-sized sheets. Review and inspection fees, along with bond amounts calculated as 110 percent of estimated construction costs, are required based on the county's current fee schedule and unit prices. All drawings must be signed and sealed by licensed professionals (Professional Engineers, Professional Land Surveyors, or Registered Landscape Architects as appropriate to discipline), include a Charles County approval block and PGM number, and contain specific information tailored to each construction category. The document provides extensive appendices including sample forms, standard symbols, certification requirements, easement agreements, stormwater management procedures, and asset summary report instructions to facilitate compliance with county standards and expedite the review and approval process.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Charles County, Maryland
Original Issue Date - July 1989
As-Builts Dedication Floodplains
Grading Roads Storm Drainage
Stormwater Management Water and Sewer
Plan Preparation Package Development Services Permits
Codes, Permits & Inspection Services Division
June 2012
Visit Charles County’s Website at www.charlescountymd.gov http://www.charlescountymd.gov/
MISSION STATEMENT
The mission of Charles County Government is to provide our citizens the highest quality service possible in a timely, efficient, and a courteous manner. To achieve this goal, government must be operated in an open and accessible atmosphere, be based on comprehensive long and short term planning, and have an appropriate managerial organization tempered by fiscal responsibility.
OUR VISION
Charles County is a place where all people thrive and businesses grow and prosper;
where the preservation of our heritage and environment is paramount;
where government services to its citizens are provided at the highest level of excellence;
and where the quality of life is the best in the nation.
INTRODUCTION
This package is designed to assist developers and engineers through the permitting process and in the preparation of plans for submissions to Charles County. Well-prepared applications, reports and plans will require minimal revisions, thereby expediting the review and approval process.
These guidelines are the minimum requirements for submission of plans to Charles County. They have been extracted from the Charles County Road Ordinance, Grading Ordinance, Stormwater Management Ordinance, Storm Drainage Ordinance, Floodplain Management Ordinance, the Water and Sewer Ordinance, the Standard Detail Manual (Detail Manual) and the Charles County Standards and Specifications for Construction Manual (Specification Manual) and the department’s policy and procedures. These guidelines are not intended to replace the County ordinances or manuals. This document has been incorporated by reference in various Charles County ordinances thus making all requirements found in this document regulatory. Charles County requires that all developers and engineers obtain and thoroughly review all ordinances, codes, manuals and any other materials required for design and construction of projects within Charles County.
All of the referenced material can be found on the County’s website at www.charlescountymd.gov.
Close adherence to these guidelines along with a working knowledge of the County ordinances, design manuals, construction manuals and procedures will produce uniform, clear, and concise plans that are easily reviewed and easily read and interpreted by field personnel. Plans not meeting the minimum standards established in this document may be rejected.
The Codes, Permits & Inspection Services Division (CPIS) works closely with developers and engineers during all phases of development, from plan review through inspection and project close out to assure our mutual goal of quality development of Charles County.
Any person applying for a Development Services Permit (DS Permit) and/or doing related work must purchase a Charles County Standard Detail Manual and a Standard and Specifications for Construction Manual.
http://www.charlescountymd.gov/
TABLE OF CONTENTS
CHARLES COUNTY, DEPARTMENT OF PLANNING AND GROWTH MANAGEMENT
PLAN PREPARATION PACKAGE
SECTION I
PLAN SUBMISSION
A. PURPOSE
B. GENERAL REQUIREMENTS
SECTION II
PLAN PREPARATION GUIDELINES AND REQUIREMENTS FOR SUBDIVISION,
COMMERCIAL, INDUSTRIAL, INSTITUTIONAL AND COUNTY CAPITAL PROJECTS
A. PURPOSE
B. GENERAL PLAN PREPARATION REQUIREMENTS FOR PROJECTS
C. DRAFTING PRACTICES
D. INFORMATION TO BE SHOWN ON PLANS
E. GRADING
1. Review and Inspection Fees
2. Bond Amount
3. Cost Estimate
4. General Requirements
5. Area of Special Geotechnical Consideration
6. Minimum Grading Design and Plan Information Requirements
F. ROADS
1. Review and Inspection Fees
2. Bond Amount
3. Cost Estimate
4. Roadway Plan & Profile Sheets
5. Roadway Profile View
6. Cul-de-sacs Plan and Profile
7. Entrances
8. Sign Schedule
9. Notes
10. Street Tree Planting List
11. Maintenance of Traffic Control Plan
12. School bus turnaround
G. STORMWATER MANAGEMENT
1. Review and Inspection Fees
2. Bond Amount
3. Cost Estimate
4. Municipal NPDES Permit
5. SWM Administrative Waivers
6. Right to Discharge
7. Adequate Conveyance
8. Location of Nonstructural, ESD or Micro Scale SWM Practices
9. I&M Agreements for Single Family Lots
10. Inventory Sheets for Micro-Scale or ESD practices on Single Family Lots
11. Bonding for Open SWM Channels
12. Large Land Disturbance Activities
13. Step 1 - Concept Stormwater Management Plans
14. Step 2 - Site Stormwater Management Plans
15. Step 3 - Final Stormwater Management Plans
16. Stormwater Management Computations
17. Drainage Area Maps
18. Stormwater Management Report
H. STORM DRAINAGE
1. Review and Inspection Fees
2. Bond Amount
3. Cost Estimate
4. Bonding of Open Conveyance Systems
5. Approved Software Packages
6. Plans
7. Plan View of Stormwater Conveyance Systems
8. Storm Drain & Ditch Profiles
9. Details
10. Computations
11. Storm Drain Design and Calculations Methods
12. Hydraulic Gradient Calculations
13. Culvert Analysis
14. Spread
I. DRAINAGE AREA MAPS (STORMWATER CONVEYANCE SYSTEMS)
J. WATER AND SEWER
1. Review and Inspection Fees
2. Bond Amount
3. Cost Estimates
4. General Requirements
5. Ancillary Permits
6. Requirements Specific to Water Plan View
7. Requirements Specific to Water Profile
8. Requirements Specific to Sewer Plan View
9. Requirements Specific to Sewer Profile
10. Requirements Specific to Water and Wastewater Pumping Stations, Well Houses and Water
Tower Design
K. FLOODPLAIN STUDIES
1. Calculated Floodplain Studies
2. Floodplain Limits and Elevations
3. Approximate Floodplain Development
4. Floodplain Studies
5. Water Surface Elevations
6. Electronic Documents
7. Runoff Data
L. SHA ENTRANCE PERMITS
M. PLANNING AND ZONING
N. DEDICATION/CONVEYANCE DOCUMENTS
1. Easement Agreements
2. Deeds and Conveyances
3. Deed of Partial Release
4. Preliminary Title Report
5. Dedication Agreement
6. Document Exhibit
7. Easement Widths
O. BONDS
P. ORDINANCES
Q. REVIEWS
R. AS-BUILT PLAN REQUIREMENTS
1. Submittal and Approval 2 General Requirements for As-Built Plans
3. Minimum Requirements for Roads
4. Minimum Requirements for Water and Sanitary Sewer
5. Minimum Requirements for Stormwater Management, Drainage and Grading
S. BRIDGE INSPECTION REPORT AND CERTIFICATION
T. VOIDING DEVELOPMENT SERVICES PERMIT APPLICATIONS
APPENDICES
1. Development Services Permit Application
2. Standard Symbols
3. SWM Summary Sheet
4. Initial Submission Check List
5. Approval/Revision Blocks
6. Telephone Numbers for Key Personnel
7. PGM Number/Title Block Placement 8 Maryland Office of Planning Land-Use Codes
9. State Watershed Designations
10. Certifications
11. Area of Special Geotechnical Consideration
12. Asset Summary Reports
A. Instructions B. Drainage C. Pump Station D. Roads E. Sewer F. Stormwater Management G. Water Storage Facilities H. Water I. Miscellaneous
13. Easements and Agreements A. SWM Inspection & Maintenance Agreement B. Private Slope, Drainage & SWM Easement C. Public Slope, Drainage and SWM Easement
D. Private SWM Natural Area Conservation Easement E. Public Pedestrian Travel Way Easement F. Private Pedestrian Travel Way Easement G. Public Sight Distance Easement
14. 3-Step SWM Plan Review Procedures
15. ESD Screening
16. MDE Codes
17. As-Built Table Sheets
18. Road Inventory Sheet
19. SWM NOCC and Inventory Forms
Charles County, Maryland
FORMAT GUIDELINES AND MINIMUM REQUIREMENTS FOR THE PREPARATION
AND SUBMISSION OF CONSTRUCTION PLANS FOR ROADS, GRADING, WATER AND
SEWER, STORM DRAIN AND STORMWATER MANAGEMENT
I. PLAN SUBMISSION
A. PURPOSE
1. The purpose of these guidelines is to establish standard format and minimum requirements for the submission of site, subdivision, development and Capital Improvement Project (CIP) documents to the Department of Planning and Growth Management (PGM), Codes, Permits & Inspection Services Division (CPIS) for review.
2. The primary objective is to expedite the review process by eliminating the review time spent on incomplete submissions. Submission packages and plans shall be prepared in conformance with Section II of these guidelines and all applicable County Ordinances, Detail Manual, MSHA Drainage Manual (Drainage Manual), 2000 Maryland Stormwater Design Manual and any Supplements, Volumes I & II (SWM Design Manual) and the Standard Specifications for Construction Manual.
3. Submission packages may be administratively evaluated and only those which adhere to the following minimum requirements will be accepted by CPIS for review. The County reserves the right to not accept those which do not meet these requirements.
B. GENERAL REQUIREMENTS
1. The documents listed on the Initial Submission Checklist (Appendix 4) are required for an initial submission of the development plans to PGM/CPIS for review. The initial submission package and all subsequent submissions will be submitted at the PGM Permits Counter, County Government Building, La Plata, Maryland.
Review fees (see Charles County Fee Schedule) are required at the time of the initial submission of the project. All checks for fees must be made payable to "Charles County Commissioners.”
Adjustments to the review fees, inspection fees and any other fees required as part of the project have to be paid prior to permit issuance.
II. PLAN PREPARATION GUIDELINES AND REQUIREMENTS FOR
SUBDIVISION, COMMERCIAL, INDUSTRIAL, INSTITUTIONAL AND
COUNTY CAPITAL PROJECTS
A. PURPOSE:
1. The purpose of these guidelines is to establish a standard format with minimum requirements for the preparation of constructions plans, reports, letters, forms, materials, and any other documents necessary in obtaining a DS Permit.
2. The primary objective of the guidelines is to produce clear, consistent, and precise plans and materials that can be easily interpreted and implemented by Charles County or Charles County
June 2012 2 contract personnel.
3. Close adherence to these guidelines and applicable County ordinances will assist developers and design professionals during their plan development stage and help expedite the review and approval process by the County.
4. The County reserves the rights to reject any DS Permit application package or any re-submittal for the following reasons:
a. Incomplete plan assembly packages,
b. Unclear or cluttered plans,
c. Plans, letters or documents which are not sealed or signed by the design professional, or
d. Other reasons the County determines warrants a rejection
B. GENERAL PLAN PREPARATION REQUIREMENTS FOR PROJECTS:
1. The following format guidelines are intended as general guidelines for the development and submission of plans for major & minor construction projects. However, other methods and alternatives that produce the desired results may be considered with approval from the County prior to the submission of permit information. Minor construction projects with limited disturbance and construction may submit an abbreviated DS Permit as noted. Minor projects may include individual lot grading, driveway entrances, grease traps, limited shore erosion project, bulkheads, or other limited disturbance projects. Also, any proposed variations or deviations from these guidelines shall be requested in writing to the Chief of CPIS prior to plan submission. Each separate category should be ghosted on the plans for other categories if the information would be necessary for understanding the project.
2. All plan sheets for Major Construction Projects shall be separate and organized in the following order:
a. Title Sheet
b. Grading/Storm Drainage/Floodplain
c. Storm Drain/Culvert Details, Profiles and Notes
d. Detailed Stormwater Management (separate from grading) Plan (also ghosted on other categories)
e. Stormwater Management Details and Notes
f. Stormwater Management Individual Lot Plan, Notes and Details
g. Stormwater Management Landscaping Plan
h. Roadway and Public Storm Drainage Plan
i. Roadway Profiles and Notes
j. Maintenance of Traffic (MOT) Plan
k. Typical Road Sections and Road Details
l. Water and Sewer Composite Plan
m. Water and Sewer Plan
n. Water and Sewer Profile
o. Typical Water and Sewer Sections, Notes and Details
p. Conceptual Grading Plans for Individual Lot Development
q. Forest Conservation Plan (separate from all other disciplines)
r. Sediment and Erosion Control Sheets (separate from all other categories)
s. Demolition, existing conditions and/or any other plan.
Note: Some information may be combined on one sheet (i.e. storm drain profiles and typical storm drainage information, or conceptual grading and individual lot swm) if approved by CPIS in advance. The County reserves the right to require information to be provided on separate sheets.
3. All plan sheets for Minor Construction Projects shall be formatted and organized in the following order:
a. Plan size shall be of sufficient size as to be easily read and understood but should be on standard size sheets such as 8.5”x11”, 8.5”x14”, 11”x17” or 24”x36”.
b. The plans shall contain all of the information required on a major construction plan as appropriate and as necessary to include and not be limited to title blocks, owner information, project information, approval blocks, existing contours, proposed contours, north arrows, existing proposed construction details, etc.
c. Grading, drainage, stormwater management, roads, water and sewer and other categories can be contained on the same sheet provided that the information is accurate and easy to read.
d. Sediment and erosion control shall be on separate sheets.
4. All drawings in a set of major construction plans shall be 36 inches wide by 24 inches high.
a. Drawings for major construction plans shall have a 1" margin along the top, bottom and right edges and a minimum 1-¼" left margin
b. Sheets shall be stapled with five staples ½" to ¾" from the left side beginning 2" below the top and 5" increments thereafter with the final approved paper sets having a blue or black binding strip.
5. The North Arrow shall be shown on each drawing. All vicinity maps and location plans shall be oriented so that North is towards the top of the sheet.
6. Stationing on plan and profile sheets shall increase from left to right across the drawing. Sheets shall be placed in plan set in order of increasing station.
7. All plans shall be oriented so that North is towards the top or right of the sheet. The North Arrow shall be shown on each sheet.
8. Any of the plan formatting requirements of Items 6 and 7 may be waived or modified by CPIS upon advanced written request if better continuity of the plan and profile sheets can be obtained.
However, there shall be consistency in stationing and north arrow orientation for all sheets throughout the plan assembly.
C. DRAFTING PRACTICES:
1. Good drafting practices shall be exercised in the preparation of all drawings. Plans need to be clear and not give a cluttered appearance. Line weights and line brightness shall be established for the maximum clarity. Unclear or cluttered plans may be rejected.
2. The minimum size of lettering for all notes and descriptions shall be 1/8" in size (lower case only) or font size eighteen (18). All other lettering shall be proportionately larger depending on the importance of the item referred. Street names and similar designations shall be boldly lettered to stand out.
3. Standard symbols to be used in preparation of the drawings shall be as shown on Appendix 2.
Additional symbols may be used provided such is included in the symbol list.
4. Any abbreviation or acronym used shall be defined in a list provided on the title sheet.
5. A graphical scale shall be provided on all drawings. Scales to be used on the drawings shall be as follows:
a. Vicinity, Location - See Section II, Paragraphs D.1.a. & b. and Paragraph I-1.
June 2012 4
b. Drainage Area Maps (DAM) – Shall be separate for drainage and stormwater management and shall be contained in the appropriate report. DAM shall be of sufficient scale as determined by the County to be clear with a minimum scale of 1”=200’. Offsite DAM or DAM used for floodplain studies shall be of appropriate scale to be readable as determined by the County Engineer.
c. Typical Sections - As appropriate to show necessary details clearly. An exaggerated horizontal or vertical scale may be used in developing the section and a notation of "Not to scale" indicated on the plans.
d. Typical Details - As appropriate to show details clearly. 1"=20' minimum and multiples thereof for larger scales. Water and Sewer Details may be referenced to a Standard Charles County Detail by including a table with reference numbers and names on the Cover Sheet.
e. Roadway and Water & Sewer plans - 1"=50' minimum. 1"=20' may be used for special paving plans, intersections and cul-de-sac details.
f. Grading Plan - 1"=50' minimum.
g. Roadway, Water, Sewer and Storm Drain Profiles - 1"=50' horizontal and 1"=5' vertical.
Enlargements of these scales will be permitted for special detailing. All profiles will be represented on a horizontal and vertical grid line graph profile.
6. All drawings must be signed and sealed by (a licensed professional registered in the state of Maryland) the following (unless specifically allowed otherwise by State Law):
a. Grading: Professional Engineer or Professional Land Surveyor, or Registered Landscape
Architect.
b. Roadway: Professional Engineer or Professional Land Surveyor
c. Water & Sewer: Professional Engineer
d. Stormwater Management & Floodplains: Professional Engineer, Professional Land Surveyor
(see note below)
e. Storm Drainage: Professional Engineer or Professional Land Surveyor
f. Landscape Plans: Registered Landscape Architect
7. All drawings shall contain the following:
a. A PGM# will be assigned to each project. This will be incorporated on the plans in the lower right hand and upper right hand corners (see Appendix 7) of all drawings with a #4 pen or similar sized font. The PGM # shall be bold and be formatted as follows, PGM# VCYY-XXXX (category – VSC, VSS, VC, VR, VI, etc.) year-number (ex. PGM# VR03-0171). For construction revisions to issued permits the PGM# shall be formatted as follows, PGM# VCYY-R-XXXX (category (VC, VR, VI, etc.) year- revision number -number (ex. PGM# VR03- 2-171). The project name shall also be placed before the PGM# in the upper right hand corner.
b. A Charles County Approval Block will be provided on the lower right side of each sheet (except for sediment and erosion control sheets) immediately above the title block. A sample approval block is provided as Appendix 5.
c. A revision block will be incorporated on each sheet for revisions made to plans after the issuance of the DS Permit. See Appendix 5 for an example. Revisions will begin after the County has approved the construction drawings and the DS Permit has been issued. The revisions shall be clearly marked adjacent to each revision with a revision number.
d. A title block shall be on each drawing and at a minimum shall contain the following:
1. project name
2. section number
3. phase number
4. date
5. scale
6. sheet number
7. sheet title
D. INFORMATION TO BE SHOWN ON DRAWINGS:
1. Title Sheets
a. Vicinity Map - Scale: 1"-2000' minimum. Vicinity map is to show major roads or streets, major streams, towns large institutions, north arrow, etc. and the site location.
b. Location Plan - Scale: 1"-200' preferred, 1"-400' minimum. Location plans shall show overall subdivision layout, section limits, adjacent subdivisions, street names, control bench mark location(s) and north arrow. The section to be constructed shall be clearly delineated.
c. Title Information - subdivision name or project name, section number, election district, County and State.
d. Owner's Certificate, name, physical address and phone number.
e. Engineer’s and/or Surveyor's Certificate, name, physical address, signature and seal.
f. Sheet index to drawings.
g. Legend of specific graphic special symbols applicable to the project which differ from the
County's Standard Symbols. The Standard Symbols should be used to the fullest possible extent.
h. List of abbreviations and acronyms applicable to the project.
i. General Notes or notes applicable to the category.
j. Special Provisions shall include notes that are specific to this project, separate from “General
Notes,” such as applicable preliminary plan requirements, timing of offsite improvements, etc.
k. Horizontal control references shall be the 1991 Maryland State Plane coordinate system.
Vertical control references shall be North American Datum (NAD) 1983.
l. Charles County Planning Commission Preliminary Plan & Final Approval Number or Site Plan
Number as applicable and the date of approval to be located in the upper left corner of the title block.
m. Charles Soil Conservation District Approval Number with approval and expiration dates to be located as required by the Charles Soil Conservation District.
n. Applicable Grant Number.
o. Tax map and parcel number.
p. A table containing the following applicable information:
1. Preliminary Plan number and approval date;
2. Charles Soil Conservation Plan number, approval date and expiration date;
3. Zoning Site Development Plan number and approval date;
4. Stormwater Management Administrative Waiver number and approval date;
5. Concept Stormwater Management Plan number and approval date; and
6. Site Stormwater Management Plan number and approval date
q. Any other information or note that the County determines is applicable for a particular project.
2. General Notes shall be as follows:
a. All work shall be in accordance with the latest Charles County Department of Planning and
Growth Management Specifications Manual, the latest Charles County Detail Manual and in accordance with all County ordinances.
b. Contractor is responsible for contacting "Miss Utility" at 1-800-257-7777, 48 hours prior to any excavation work.
c. The developer is responsible to hold a “Preconstruction” meeting to include the contractor, Charles County Inspection personnel, public utilities, and any local, state or federal agencies as required prior to the start of construction.
d. The contractor is responsible for contacting the Charles County Department of Planning and
June 2012 6
Growth Management/Codes, Permits & Inspection Services Division 48 hours prior to the start of all construction in accordance to all permits issued @ 301-645-0700.
e. Maximum slopes shall be not greater than three (3) feet horizontal to one (1) foot vertical outside the road right-of-way. Slopes within the road right-of-way shall be not greater than two
(2) feet horizontal to one (1) foot vertical, or as specified in the County Road Ordinance and in the Charles County Detail Manual.
f. Certified compaction tests are required for all trench/fill work in accordance with the latest edition of the Specifications Manual and Grading Ordinance. Final reports and certifications shall be provided prior to pre-final inspections.
g. Certified compaction tests and geotechnical reports shall be submitted on a bi-weekly basis throughout the course of construction as required by the Specifications Manual.
h. A progress set of as-built plans shall be submitted prior to “Substantial Inspections” for water and sewer construction for the purpose of obtaining an approval for substantial inspection
i. As-built plans shall be submitted prior to pre final inspections for all disciplines.
j. For all structures categorized as a “bridge” according to the definition contained in Section
GP.1 of the Charles County Standards and Specifications for Construction Manual, bridge inspection report and certification requirements shall be met prior to the road pre final inspection.
k. With approval from the Department of Planning & Growth Management all erosion and sediment control structures must be removed prior to the release of bonds.
l. Street lighting is not permitted in the road right-of-way outside of the Urban Road Standards District.
E. GRADING:
To be complete and in accordance with the Charles County Grading Ordinance and the Specifications Manual. Plans shall be clear and easy to read and should not include overlapping information which would make it difficult to review.
1. Review and Inspection Fee: The fee for the review and inspection of a DS Permit for grading operations shall be:
a. As established in the latest Charles County Fee Schedule (Fee Schedule) based on the latest Charles County Unit Prices for Fee Establishment and Security Amounts (Unit Prices).
b. The fees shall be payable to the Commissioners of Charles County. The Review Fee shall be submitted with the initial submission and the Inspection Fee shall be submitted at the time of the issuance of the DS Permit. If the final Review Fee is less than the amount previously paid, a credit of the overpayment will be given toward the required Inspection Fee.
2. Bond Amount: The amount of the bond for grading operations shall be computed as follows:
a. As established in the latest edition of the Unit Prices.
3. Cost Estimate - A construction cost estimate for grading outside of the road right-of-way is required. Cost estimates shall be based on the latest Unit Prices and included under the Stormwater Management Bond.
4. General Requirements for an Overall Residential Conceptual Grading Plan
a. Overall conceptual grading plans for subdivision projects shall be provided on separate sheets for all subdivisions of lots of 2 acres or less and/or all subdivisions where grading single family lots impact adjacent lots. This plan shall be provided on separate sheets. The following information shall be provided on the conceptual grading plans:
1. building restriction lines
2. projected house locations
3. easement locations and dimensions (labeled)
4. existing and proposed contours (2' contour interval minimum) with elevations
(note that grades need to comply with all applicable building codes as well as the Grading Ordinance)
5. conceptual entrance and driveway culvert locations and sizes
6. the lowest finished floor elevation, the basement floor elevation (if applicable) and the garage floor elevation (if applicable)
7. environmentally sensitive areas such as Wetlands, RPZs, Critical Areas, Floodplains
(with elevations), Forest Conservation, etc.
8. Soil series and high groundwater information
9. Geotechnical information necessary if located in the “Area of Special Geotechnical
Consideration”
10. Stormwater information for lots with individual lot swm design as outlined in the SWM
Design Manual
11. Other site information of particular interest which may affect the building or activities on the site.
It shall be the responsibility of the applicant of the DS Permit to assure that each individual subdivision lot may be properly graded during the Building Permit process without grading on adjacent lots or without obtaining offsite permission from offsite property owners. A note shall be added to the plans stating the following:
Building permits shall include a site plan showing that each individual lot be graded in substantial compliance with the overall conceptual lot grading plan or as approved by the Department of Planning and Growth Management.
5. Area of Special Geotechnical Consideration
a. A geotechnical report will be required for new construction in the portion of the County designated as the “Area of Special Geotechnical Consideration”. The geotechnical report shall be prepared by a professional engineer licensed in the state of Maryland. The geotechnical report shall identify all unstable soil conditions and make recommendations for construction requirements where the unstable soil conditions exist. Unstable soil conditions shall include but not be limited to, high shrink/swell or other unstable soil conditions as determined by the geotechnical engineer. These recommendations shall become a part of the construction permit requirements.
The geotechnical construction recommendations shall include all necessary requirements for roads, grading, drainage, stormwater management, water & sewer, buildings, foundations, landscaping, utilities, and any other construction as determined by the county. A generalized map is attached in Appendix 11.
6. Minimum Grading Plan Information Requirements
a. Show property boundaries with bearings and distances
b. Show benchmark locations with elevations
c. Provide a timing schedule with anticipated start date, major construction milestone dates and completion date
d. Show the location of all proposed buildings, structures, utilities, sewers, storm drains, stormwater management facilities, roads, parking areas, curb & gutters, landscape areas, streams, channels, ditches, wetlands, buffers, floodplains, backwaters, easements, resource protection zones, tree lines, limits of disturbance, or any other environmental feature or structures located within the limits of where the work is to be completed
e. Gain authorization and provide written copy for off-site grading rights for all work proposed outside of the property boundaries. Any work requiring a recorded document shall have such document reviewed, approved and recorded prior to the issuance of the DS permit.
f. Show the location of all existing buildings, structures, utilities, sewers, storm drains, stormwater management facilities, roads, parking areas, curb & gutters, landscape areas, streams, channels, ditches, wetlands, buffers, floodplains, backwaters, easements, resource
June 2012 8 protection zones, tree lines, limits of disturbance or any other environmental feature or structures located within a minimum of one hundred feet (100') from where the work is to be completed or from the property line. Information beyond one hundred feet (100') may be required by the County if deemed necessary
g. Existing topography (contours and elevations) shall be shown for the entire site extending at a minimum of one hundred feet (100') beyond the property line (farther if deemed necessary by the County). Contour interval shall be two feet (2') with elevations established on all contour lines
h. Proposed topography (contours and elevations) shall be shown for the entire site extending at a minimum of one hundred feet (100') beyond the property line (farther if deemed necessary by the County). Contour interval shall be two feet (2') with elevations established on all contour lines
i. Show an estimate of quantity of fill involved
j. Show the locations of any soil boring or soil test
k. If controlled fill is specified, provide soil classification and maximum dry density and moisture content of all controlled fill
l. All proposed improvements to include roads, water and sewer systems, storm drain pipes and structures, culverts, stormwater management devices shall be ghosted
m. All proposed easements with dimensions and labels
n. Geotechnical recommendations
o. With approval from the Codes, Permits & Inspections Services Division all erosion and sediment control devices must be removed prior to the release of the bonds
F. ROADS: To be in accordance with the Charles County Road Ordinance.
1. Review and Inspection Fees: The fees for review and inspection of a DS Permit for road improvements shall be as follows:
a. As established in the latest Fee Schedule based on the latest Unit Prices.
b. The fees shall be payable to the Commissioners of Charles County. The Review Fee shall be submitted with the initial submission and the Inspection Fee shall be submitted at the time of the issuance of the DS Permit. If the final Review Fee is less than the amount previously paid, a credit of the overpayment will be given toward the required Inspection Fee.
2. Bond Amount: The bond amount for road, common access driveways and entrance improvements shall be as follows:
a. 110% of the estimated cost of construction for construction within the right-of-way & common access driveways if applicable. The minimum bond amount for Commercial, Industrial, and multi-family entrances shall be $5000.
3. Cost Estimate - A construction cost estimate for road and/or entrance improvements within the road right-of-way as well as construction of common access driveways is required. Cost estimates shall be based on the latest Unit Prices.
4. Roadway Plan & Profile Sheets
a. Plan view and relative profile views, i.e. same station break points, shall appear on separate plan sheets.
b. Plans shall be drafted to scales which meet Section II, Paragraph C-4.
c. Roadway Plan View - The plan view shall not show grading or unnecessary information. The plan shall contain the following information:
1. Dimensions - Pavement, shoulders, hiker/biker paths, sidewalks, and right-of-way widths shall be noted at a minimum rate of one per page per roadway shown.
2. Road Names - The road name shall be provided and placed outside of the road right-of-way limits. Names shall be bold and placed so as not to cause confusion with other information on the sheet. These names shall be as approved previously by the 911 Addressing Office with the preliminary subdivision plans.
3. Classification and Design speed - Shall be noted per each roadway design and placed below, adjacent to roadway name.
4. Stationing - Shall meet provisions of Section II paragraph B - 6&7, and shall be comparable to the stationing of the profile view.
(a) Stationing for roadway extensions shall be continued from the previous project, section, or phase.
(b) Stationing for equivalency points of roadway intersections shall be labeled.
(c) Provide stationing for significant features such as center of cul-de-sacs, end of pavement, and barricade placement.
5. Horizontal Alignment Data – All data relative to the horizontal alignment shall be provided as follows:
(a) Point of Intersection (P.I.)
(b) Point of Curvature (P.C.)
(c) Point of Tangency (P.T.)
(d) Intersection Angle ( DELTA)
(e) Radius (R)
(f) Tangent Distance (T)
(g) Tangent Bearing (B)
(h) Length of Curve (L)
(i) Long Chord Length (L.C.)
(j) Middle Ordinate (M)
(k) Degree of Curve (D)
(l) Superelevation Data (superelevation rate, runoff, etc.) where provided.
6. Property Lines - Property line boundaries shall be shown for each lot and parcel, or subdivision of each, which lies adjacent to the roadway.
7. Storm Drains and Drainage Road (Cross) Culverts - Storm drain systems and road culverts shall be shown and labeled with a description of the structures. Pipes shall be screened to include the type and size.
(a) Easements shall be shown, labeled and dimensioned where necessary according to
County regulations and Section II, Paragraph M.2.of this package.
8. Cross Section - Representative cross-sections will be provided for each roadway and/or roadway pavement widening in the remaining space available on the plan sheet or on separate sheets. These sections shall consist of not only the necessary widths of roadway, design, and dedication; but also the depths of the pavement section and description of material to be used, shoulders, roadside ditches, curb and gutter size and type, sidewalk width, landscaping width easements, and any other information as required by the County. Provide applicable street names for each detail.
9. Location of Signs
10. Fillet or curb radii with P.C. and P.T. for all streets shall be shown.
11. Label size of existing curb. Label any needed curb transitions.
12. Direction of flow arrows, at curb returns and critical drainage points.
13. Location of pedestrian ramps with detail reference.
14. Pavement markings for acceleration and deceleration lanes, paved shoulders, pedestrian/hiker-biker facilities, parking spaces and where require by section 6.2 of the Road Ordinance, in accordance with current MUTCD standards. This can be shown on a
June 2012 10 separate sheet from the road plans. Note angle of hatching paint color and type, line width, and spacing with details as necessary. Label existing markings.
15. Sight distance shall be shown for all intersections and entrances and around small radius turns. Show easements 2’ outside the line of sight where it extends outside the right-of-way.
16. Show under-drains (or assessment by geotechnical engineer that they are not needed)
17. Show USPS cluster box units (CBUs) if within the road right-of-way (Ordinance 6.6.B)
18. Label any existing utility poles, signs, mailboxes or other privately owned structures that must be relocated
19. Provide guardrail where warranted with appropriate end treatment labeled. Provide details.
5. Roadway Profile View - The profile view shall contain the following information:
a. Utility Placement - All utility or storm drain systems crossing the roadway shall be shown on this view. Adequate cover protection must be shown and depths labeled.
b. Stationing - Shall meet the provisions in Section II paragraphs B-6&7 and shall be continued from the previous project, section, or phase when applicable for roadway extensions.
c. Vertical Alignment Data - All data relative to the vertical alignment shall be provided as follows:
1. Point of Vertical Intersection (P.V.I.)
2. Point of Vertical Curvature (P.V.C.)
3. Point of Vertical Tangency (P.V.T.)
4. Grades of Tangents (in percent, with upgrades in direction of increasing stationing being positive and downgrades negative).
5. Length of Vertical Curve (V.C.L.)
6. Design Speed - as noted in plan view Section II, Paragraph F.4.c.(3)
7. Algebraic difference in grade (A)
8. Vertical offset from P.V.I. to middle of curve, in feet (E).
9. Profile rate of change (K).
d. Elevations shall be noted for existing conditions at proposed roadway centerline and right-of-way lines left and right of centerline. In addition, the proposed profile conditions for centerline and right-of-way lines must be shown.
e. Sight distance shall be shown for all intersections, horizontal curves, when the line of sight is outside of the right-of-way and all entrances.
6. Cul-de-sacs Plan and Profile
a. Shall meet all requirements stated in Section II, Paragraphs F-4&5 respectively.
b. Shall show all necessary design features such as: all radii for roadway, cul-de-sac islands, shoulder, and right-of-way.
c. Cross slope of cul-de-sac bulb shall be shown in plan view.
d. Linear profile around cul-de-sac bulb at curb line for closed sections only.
e. Show center point elevation and stationing.
7. Entrances
a. Commercial-Industrial-Apartment Entrances - shall be shown in detail with respect to typical design standards. Detail shall be noted such as:
1. Entrance width - measured at straight line tangents.
2. Radius of entrance fillets.
3. Pavement section detail - All materials to be used for construction shall be noted, including descriptions, type, and thicknesses.
4. Entrance profile - this shall be drafted to show adequate cover over drainage structures and utilities.
5. Entrance landing grade or slope.
b. Subdivision Entrances - shall be shown in relation to Section II, Paragraphs F-4&5.
c. Label entrance aprons to be paved. For commercial/industrial/apartment entrances, specify that the apron is to be constructed per Standard Detail R/2.30 to R/2.32.
8. Sign Schedule table indicating quantity, type, size, material, and MUTCD reference number for all signs.
9. Transportation Notes – the following notes shall be placed on the title sheet or first road plan sheet as applicable:
a. In accordance with Section 5.6.C of the Road Ordinance, an evaluation of the proposed roadway pavement section based upon existing subsurface and sub-grade soil conditions and worst case scenario for traffic volumes (EAL’s) is required to be submitted by a licensed Geotechnical Engineer prior to placement of the sub-base materials. The subgrade must have a minimum CBR value of 7.
b. All signs shall be mounted on galvanized channel posts.
c. Signs shall be installed prior to substantial completion acceptance.
d. Existing pavement shall be sawcut at the white edge line prior to road widening.
e. Apply tack coat and bituminous joint sealer at all vertical joints between existing pavement and proposed asphalt widening.
f. The contractor shall remove and restripe any pavement markings that are damaged during construction.
10. Street Tree Planting List indicating name, quantity, and caliper. Street trees shall be shown and labeled (can be shown on a separate landscaping plan). Specify appropriate tree planting standard details. Provide a note stating, “A certificate of compliance from a landscape Architect, registered in the State of Maryland, shall be submitted to the County Highway Engineer by the owner/developer of the project prior to bond release. The certification shall state that the type and location of all planted street trees are in compliance with the Road Ordinance, Standard Detail Manual, and/or approved construction plan.”
11. Maintenance of Traffic Control Plan shall be shown as per MUTCD and the MSHA standards.
The following note shall be placed on the MOT plan: “Standard hours for work within the public road right-of-way are from 9 am to 3 pm on weekdays, excluding holiday periods”
The following special provisions apply to road closures of more than 15 minutes duration:
a. Road closures shall be approved by the County Highway Engineer during project design. The
Engineer may require specific signage, times of operation, or other restrictions to be specified on the plan.
b. Road closures shall not be permitted during holiday seasons.
c. Variable Message Sign (VMS) shall be placed in each direction 2 weeks prior to street closures and remain in place as directed by the County Highway Engineer. The VMS messages shall be shown on the plan.
d. Road closures shall be advertised in the local newspaper by the contractor twice per week during the two weeks prior to closure.
12. School bus turnaround with “NO PARKING” signs in accordance with the Road Ordinance.
G. STORMWATER MANAGEMENT: Where applicable, new projects requiring a DS Permit must follow the Charles County 3-Step SWM Plan Review Process. Procedures for submission of Concept Stormwater Management Plans (Step 1) and Site Stormwater Management Plans (step 2) can be found in Appendix 14 Projects which have received a SWM Administrative Waiver do not follow the 3-Step Plan Review Process.
June 2012 12
All stormwater management designs shall be in accordance with the Charles County Stormwater Management Ordinance and the 2000 Maryland Stormwater Design Manual (and any supplements).
1. Review and Inspection Fees: The review fees are based on the County’s “Fees and Charges” schedule is required. This review fee shall be submitted with the initial submission of plan and the inspection fee shall be submitted prior to the issuance of a DS Permit. The fees are to be made payable to the Commissioners of Charles County. If the final review fee is less than the initial amount previously paid, a credit of the overpayment will be given toward the required inspection fee. Fees schedules are posted yearly on the County’s web site.
2. Bond Amount: The bond amount for stormwater management shall be 110% of the total estimated construction cost estimate. The construction cost estimate is based on unit prices established in the latest Unit Prices.
3. Cost Estimate: The construction cost estimate shall be based on the Unit Prices. Stormwater management construction cost estimates shall be separate from all other categories. Public facilities shall be broken out separate from the private facilities within the cost estimate.
4. Municipal National Pollutant Discharge Elimination System (NPDES) - Charles County is required to have an acceptable stormwater management program to remain in good standing in the Charles County’s Municipal National Pollutant Discharge Elimination System (NPDES) and may impose any stormwater management requirement from time to time to assure the County’s standing.
5. SWM Administrative Waivers - Project which received preliminary stormwater management plan approval prior to May 4, 2010 may request a SWM Administrative Waiver. Projects which receive a SWM Administrative Waiver may use the 2001 SWM Ordinance and the 2000 Maryland Stormwater Design Manual (without the supplement) as the basis for the design. SWM Administrative Waivers have sunset dates which would require a project submitted to receive final swm and sediment and erosion control approval by May 4, 2013 and final completion acceptance of the swm facilities and the associated sediment and erosion control facilities by May 4, 2017.
Project receiving a SWM Administrative Waiver must submit a copy of the approval letter with the plan submission.
6. Right-to-Discharge - If the project includes the increase of discharge from any point from a project the project developer may gain a Right-to-Discharge from the adjacent property owner after it has been determined that there is an adequate outfall. The Right-to-Discharge must be obtained prior to DS Permit approval and must be recorded in the Land Records of Charles County and must be shown on the plans.
7. Adequate Conveyance - Each project must adequately convey offsite runoff entering into the project via an adequate conveyance system. The development of the project cannot impede or backwater runoff onto the adjacent upstream properties beyond the pre-existing limits without gaining the rights through acceptable recorded documents. All documents must be recorded prior to DS Permit approval.
8. Location of Nonstructural, ESD or Micro Scale SWM Practices used in urban residential projects (excluding apartment complexes) shall be off the lots unless approved by the County in advance. These practices may be used in rural residential projects if it would be impracticable to place in an open space area. If an on-lot ESD practice or micro-scale bmp (excluding nonstructural practices for rooftop or non-rooftop disconnections) is provided to address a single residential lot then a SWM Inspection & Maintenance Agreement (Appendix 13) must be recorded prior to the issuance of the associated building permit.
9. I&M Agreements for Single Family Lots - The County may ask for recorded SWM I&M agreements for single family lots.
10. Inventory Sheets for Micro-Scale or ESD practices on Single Family Lots - The County may ask for inventory sheets for micro-scale or Nonstructural/ESD practices utilized on single family lots.
11. Bonding for Open SWM Channels - If a swm practice such as an open ditch serves a dual purpose (swm and drainage) the bonding for practice shall be included in the swm bond only.
12. Large Land Disturbance Activities such as mining projects are not exempt from having to address stormwater management. Stormwater management for these projects shall meet the swm requirements by designing swm using the target for ESD implementation to be “woods in good condition”. Once the mining is completed and if portions of the site will be returned to agricultural land management practices (cultivation of crops for sale) then the stormwater management plans may be revised to eliminate any stormwater management practice for those portions of the site returning to crop cultivation. The stormwater management for those portions of the site not returned to crop cultivation such as access roads must remain and be protected by permanent easements and or agreements.
13. Step 1 - Concept Stormwater Management Plans: Procedures for submission of the Concept
SWM Plan are provided in Appendix 14. The information required on a Step 1 SWM Plan is outlined in the Stormwater Management Ordinance and the 2000 Maryland Stormwater Design Manual (including supplements). Key elements are listed here:
a. Plans sheets shall be formatted according to final plan standards noted above. In addition to the standard applicable information the title sheet shall contain the wording “Concept SWM Plan” in the project title.
b. Drawings at a scale not to exceed 1”=50’ showing site location, existing natural features, water and other sensitive resources, topography, and natural drainage patterns;
c. The anticipated location of all proposed impervious surfaces, buildings, roadways, parking, sidewalks, utilities, and other site improvements;
d. The location of the proposed limit of disturbance, erodible soils, steep slopes, and areas to be protected during construction;
e. Preliminary estimates of Stormwater Management requirements, the selection and location of ESD practices to be used, and the location of all points of discharge from the site;
f. A SWM report with the following information:
g. Cover page with the following information:
1. Project title information to include the Wording “Concept SWM Plan”
2. Assigned PGM #
3. Project location information (ex: tax map, grid and parcel)
4. Design firm information
5. Seal and signature of the responsible design professional
6. Any State required certification
h. A narrative that supports the concept and describes how the design will achieve:
1. Natural resource protection and enhancement,
2. Maintenance of natural flow patterns,
3. Reduction of impervious areas through better site design, alternative surfaces, and nonstructural practices,
4. Integration of erosion and sediment controls into the stormwater strategy, and implementation of ESD planning techniques and practices to the MEP.
i. Plans sheets shall be formatted according to final plan standards noted above. In addition to the standard applicable information the title sheet shall contain the wording “Concept SWM Plan” in the project title.
J. Any other information required by the County Engineer.
June 2012 14
k. After the approval of the concept plan and within two weeks from the date of the approval letter the engineer will submit one hard copy check plan and electronic copies of the plans and the report on one compact disc (CD). The County may reject future submittals until the electronic copies of the approved plans and reports are provided. Failure to provide electronic copies of the approved plans and report may result in a voiding of the project in which case the review fees will be forfeited and the project will have to start the review process from step 1.
14. Step 2 - Site Stormwater Management Plans: Procedures for submission of the Site SWM
Plan are provided in Appendix 14. The information required on a Step 2 Stormwater Management…