FCCO CONSTRUCTION TRAILER RELOCATION SERVICE
Solicitation number
140R4026Q0100
Issued by

About this file

This is a Performance Work Statement (PWS) for the relocation of a double-wide office trailer owned by the Bureau of Reclamation's Four Corners Construction Office (FCCO) in New Mexico.

The contractor must relocate a 24-foot-wide by 60-foot-long double-wide office trailer from its current location near Yah-Ta-Hey Junction in McKinley County, New Mexico (GPS coordinates 35.629609, -108.779830) to the San Juan Lateral River Intake Pumping Plant site at 3895 US-64, Fruitland, New Mexico, located in San Juan County. Key contractor responsibilities include: obtaining all required transportation permits and clearances from New Mexico DOT and local authorities; determining the transportation route and schedule subject to Reclamation approval; disconnecting plumbing and sewer lines and removing skirting at the origin site; securing furniture and equipment inside the trailer for safe transport; providing a Job Hazard Analysis and proof of insurance prior to work commencement; and completing installation at the destination, including leveling the trailer on blocks and reinstalling skirting and stairs. The contractor bears liability for damage to the trailer, Government equipment, and non-Federal infrastructure or property. At the destination, the contractor must coordinate delivery and installation with Ames Federal Contracting Group, LLC (the on-site contractor) with no less than five business days' notice to Reclamation. Installation excludes water and sewer connections, which Reclamation will handle separately. The Quality Assurance Surveillance Plan specifies three performance areas: preparation (on-site inspection prior to transportation), transportation (Reclamation monitoring for safe delivery without safety issues), and installation (final inspection confirming proper placement and support on blocks).

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FCCO Construction Trailer Relocation

10 June 2026

PWS Page 1 of 8

1. INTRODUCTION: The Bureau of Reclamation, Upper Colorado Basin Region, Four

Corners Construction Office (FCCO), is responsible for the construction of the Navajo- Gallup Water Supply Project located in northwest New Mexico. The project includes the completed Cutter Lateral and the under-construction San Juan Lateral. The San Juan Lateral begins at the San Juan Lateral River Intake Pumping Plant, diverts water to the Frank Chee Willetto Reservoir, then delivers it to a treatment plant south of the river. From there, pumping plants convey the water to Navajo communities along Hwy-491, extending past Yah-Ta-Hey Junction and into the City of Gallup. The southern sections of the project have been completed, while construction continues upstream in the vicinity of the San Juan River. Since the southern sections have been completed, FCCO has a need to have mobile structural moving/relocation services to move their office trailer.

2. SCOPE: The FCCO owns a double-wide office trailer currently located near Yah-Ta-Hey Junction, Mckinley County, New Mexico, that needs to be relocated to a property in Fruitland, New Mexico, west of Farmington, New Mexico, located in San Juan County.

A. Contractor Requirements

i. Contractor shall determine and obtain all required transportation permits, clearances required along the route, and must comply with all New Mexico DOT and local county rules and laws.

ii. Contractor shall determine the transportation route and schedule.

iii. Contractor relocation schedule (including preparation, pick-up, delivery, and installation times) must be approved by Reclamation before onsite work can begin.

iv. Contractor shall be liable for any damage caused to the trailer, tires, axles, skirts or other Government owned equipment.

v. Contractor shall be responsible for any damage caused to non-Federal infrastructure or property resulting from moving the trailer.

vi. Contractor shall comply with the Reclamation Safety and Health Standards.

vii. Contractor shall provide a Job Hazard Analysis (JHA) that must be approved by Reclamation before any work can begin.

viii. Contractor shall provide proof of insurance to Reclamation before beginning any work.

ix. Contractor shall determine if furniture and equipment stored inside the trailer is secure enough for transportation and shall advise Reclamation accordingly.

B. Current Location

i. Trailer Specifications: 24 ft wide (Two 12-ft wide sections) x 60 ft long.

Each side has axles with 8 tires with 2 spares available. See attached

PWS Page 2 of 8 pictures.

ii. Location: The trailer is located at GPS coordinates: 35.629609, -108.779830.

The exit gate is 17.5 ft wide. The contractor shall need to coordinate access with Reclamation. See attached aerial images lot and trailer to be relocated.

iii. Disconnection:

1. Plumbing and sewer shall need to be disconnected by the contractor.

2. Skirting shall be removed by the contractor.

3. Stairs are not connected but shall be relocated with the trailer.

4. There is no external HVAC equipment.

5. Reclamation will ensure power is disconnected in advance of removal.

iv. Some furniture and equipment shall, if possible, remain inside the building during transportation.

C. Destination and Installation

i. Destination: The trailer needs to be delivered to and re-established at the San Juan Lateral River Intake Pumping Plant site located at 3895 US-64, Fruitland, NM 87416. See attached site plan.

ii. Relocation Schedule:

1. Ames Federal Contracting Group, LLC is the contractor on-site and delivery and installation of the office trailer shall be carefully coordinated with Ames for safety, security, and work management.

2. Coordination with Ames shall be completed through Reclamation.

3. Contractor shall give Reclamation no less than 5 business days’ notice to coordinate with Ames.

4. Delivery and installation schedule shall be approved in advance

iii. Installation:

1. The Contractor shall level and place trailer on blocks as appropriate.

2. The Contractor shall contract shall re-attach skirts and place stairs from original site.

3. No water or sewer shall be attached.

4. Reclamation will be responsible for installing power.

3. SECURITY:

A. The Project Manager, Contracting Officer’s Representative (COR) or Contracting

Officer’s Technical Representative (COTR) will assist with the Contractor’s entry into secure areas and inform the Contractor of security procedures. The Contractor shall comply with all security procedures.

B. Reclamation reserves the right to perform security checks on Contractor employees.

https://maps.app.goo.gl/Ctb3MFaou5ihUvpa8

PWS Page 3 of 8

4. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

Task Performance Indicator

Inspection Minimum Acceptable Quality Level

Preparation The trailer shall be properly prepared for transportation, including securing any necessary items inside the trailer to make it safe for transportation.

On-site inspection prior to transportation will take place.

Trailer sides will be prepared for safe transportation with no risk of causing problems on the road.

Transportation The trailer shall be moved safely from the origin to the destination without incident.

Reclamation will monitor transportation of the trailer.

Trailer will be transported to the destination without causing safety issues.

Installation The trailer shall be installed at the destination on blocks and have skirting re-installed.

Reclamation will complete a final inspection of the placement and installation of the trailer.

Trailer will be supported correctly and properly.

PWS Page 4 of 8

CURRENT LOCATION

PWS Page 5 of 8

PWS Page 6 of 8

CURRENT LOCATION

Current location

Trailer to relocate

PWS Page 7 of 8

DESTINATION

PWS Page 8 of 8

APPROXIMATE DESTINATION SITE LAYOUT