Amended_Performance_Work_Statement_-_FCCO_Trailer_Relocation_9_pages_0001.pdf

PDF 3 MB Posted

Attached to
FCCO CONSTRUCTION TRAILER RELOCATION SERVICE
Solicitation number
140R4026Q0100
Issued by

About this file

Performance Work Statement Summary: FCCO Construction Trailer Relocation

This is a Performance Work Statement for the relocation of a double-wide office trailer owned by the Bureau of Reclamation's Four Corners Construction Office (FCCO) in support of the Navajo-Gallup Water Supply Project in northwest New Mexico. The trailer, measuring 24 feet wide by 60 feet long (capable of being moved in two 12-foot sections), must be relocated from its current location near Yah-Ta-Hey Junction in McKinley County, New Mexico (GPS coordinates 35.629609, -108.779830) to the San Juan Lateral River Intake Pumping Plant site at 3895 US-64, Fruitland, New Mexico in San Juan County. The contractor is responsible for determining and obtaining all required transportation permits and compliance with New Mexico Department of Transportation and local county regulations, as well as determining the safe feasibility of moving the trailer and obtaining necessary certifications. The contractor must furnish all required axles and tires, determine the transportation route and schedule, and disconnect plumbing, sewer, and skirting at the current location.

The contractor must provide proof of insurance and a Job Hazard Analysis approved by Reclamation before commencing work, and is liable for all damage to the trailer, Government equipment, and non-Federal infrastructure resulting from the move. At the destination, the contractor shall level and place the trailer on blocks, re-attach skirting, and relocate stairs, with Reclamation responsible for power installation. The relocation schedule must be approved by Reclamation and carefully coordinated with Ames Federal Contracting Group, LLC (the on-site contractor) with a minimum of five business days' notice. Quality assurance includes on-site inspection during preparation, monitoring of transportation, and final inspection of placement and installation to ensure the trailer is properly supported and secured.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FCCO Construction Trailer Relocation

Amended in RED 06 July 2026

PWS Page 1 of 8

1. INTRODUCTION: The Bureau of Reclamation, Upper Colorado Basin Region, Four

Corners Construction Office (FCCO), is responsible for the construction of the Navajo- Gallup Water Supply Project located in northwest New Mexico. The project includes the completed Cutter Lateral and the under-construction San Juan Lateral. The San Juan Lateral begins at the San Juan Lateral River Intake Pumping Plant, diverts water to the Frank Chee Willetto Reservoir, then delivers it to a treatment plant south of the river. From there, pumping plants convey the water to Navajo communities along Hwy-491, extending past Yah-Ta-Hey Junction and into the City of Gallup. The southern sections of the project have been completed, while construction continues upstream in the vicinity of the San Juan River. Since the southern sections have been completed, FCCO has a need to have mobile structural moving/relocation services to move their office trailer.

2. SCOPE: The FCCO owns a double-wide office trailer currently located near Yah-Ta-Hey Junction, Mckinley County, New Mexico, that needs to be relocated to a property in Fruitland, New Mexico, west of Farmington, New Mexico, located in San Juan County.

A. Contractor Requirements

i. Contractor shall determine and obtain all required transportation permits, clearances required along the route, and must comply with all New Mexico DOT and local county rules and laws.

ii. Contractor shall determine if trailer can be moved safely and shall ensure any required certifications are obtained.

iii. Contractor shall determine and furnish axles and tires required for the move.

iv. Contractor shall determine the transportation route and schedule.

v. Contractor relocation schedule (including preparation, pick-up, delivery, and installation times) must be approved by Reclamation before onsite work can begin.

vi. Contractor shall be liable for any damage caused to the trailer, tires, axles, skirts or other Government owned equipment.

vii. Contractor shall be responsible for any damage caused to non-Federal infrastructure or property resulting from moving the trailer.

viii. Contractor shall comply with the Reclamation Safety and Health Standards.

ix. Contractor shall provide a Job Hazard Analysis (JHA) that must be approved by

Reclamation before any work can begin.

x. Contractor shall provide proof of insurance to Reclamation before beginning any work.

xi. Contractor shall determine if furniture and equipment stored inside the trailer is secure enough for transportation and shall advise Reclamation accordingly.

PWS Page 2 of 8

B. Current Location

i. Trailer Specifications: 24 ft wide (can be moved in two 12-ft wide sections) x 60 ft long. No tires or axles will be provided. See attached pictures.

ii. Location: The trailer is located at GPS coordinates: 35.629609, -108.779830.

The exit gate is 17.5 ft wide. The contractor shall need to coordinate access with Reclamation. See attached aerial images lot and trailer to be relocated.

iii. Disconnection:

1. Plumbing and sewer shall need to be disconnected by the contractor.

2. Skirting shall be removed by the contractor.

3. Stairs are not connected but shall be relocated with the trailer.

4. There is no external HVAC equipment.

5. Reclamation will ensure power is disconnected in advance of removal.

iv. Some furniture and equipment shall, if possible, remain inside the building during transportation.

C. Destination and Installation

i. Destination: The trailer needs to be delivered to and re-established at the San Juan Lateral River Intake Pumping Plant site located at 3895 US-64, Fruitland, NM 87416. See attached site plan.

ii. Relocation Schedule:

1. Ames Federal Contracting Group, LLC is the contractor on-site and delivery and installation of the office trailer shall be carefully coordinated with Ames for safety, security, and work management.

2. Coordination with Ames shall be completed through Reclamation.

3. Contractor shall give Reclamation no less than 5 business days’ notice to coordinate with Ames.

4. Delivery and installation schedule shall be approved in advance

iii. Installation:

1. The Contractor shall level and place trailer on blocks as appropriate.

2. The Contractor shall contract shall re-attach skirts and place stairs from original site.

3. No water or sewer shall be attached.

4. Reclamation will be responsible for installing power.

3. SECURITY:

A. The Project Manager, Contracting Officer’s Representative (COR) or Contracting

Officer’s Technical Representative (COTR) will assist with the Contractor’s entry into secure areas and inform the Contractor of security procedures. The Contractor https://maps.app.goo.gl/Ctb3MFaou5ihUvpa8

PWS Page 3 of 8 shall comply with all security procedures.

B. Reclamation reserves the right to perform security checks on Contractor employees.

4. QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)

Task Performance

Indicator Inspection Minimum

Acceptable Quality Level

Preparation The trailer shall be properly prepared for transportation, including securing any necessary items inside the trailer to make it safe for transportation.

On-site inspection prior to transportation will take place.

Trailer sides will be prepared for safe transportation with no risk of causing problems on the road.

Transportation The trailer shall be moved safely from the origin to the destination without incident.

Reclamation will monitor transportation of the trailer.

Trailer will be transported to the destination without causing safety issues.

Installation The trailer shall be installed at the destination on blocks and have skirting re-installed.

Reclamation will complete a final inspection of the placement and installation of the trailer.

Trailer will be supported correctly and properly.

PWS Page 4 of 8

CURRENT LOCATION

PWS Page 5 of 8

PWS Page 6 of 8

CURRENT LOCATION

Current location

Trailer to relocate

PWS Page 7 of 8

DESTINATION

PWS Page 8 of 8

APPROXIMATE DESTINATION SITE LAYOUT

7-1371 (7-74) s-u at Radamallon

LICENSE PLATE RECORD

eompi.a lhls term in duplicate and forward to the appropriate Regional Property � each •- •-- ,_ llcenM ..,,... 1g , .... e ,_ ..... ,se p .. tas ■181'9qU...0, wti,_, ■ny ctw,ge ,s made on prevk>Ut ,-.. HI omen� or when plalea are deltmyad ExplaJn tr.insact10n and refer lo pertinent doarnents ln the ce ad on opposite side. The duplk:ate copy W1ll be relumed to Iha onglnatlng offlc:e as confirmation of 8 reque&t for llcens:e plata or change I &Jg spa l provld(See FRMR 11•S-3a 3) nu nmen

TO:

FROM:

SUBJECT: Identification of Government-owned Vehicles

Check (X) appllcablo block and complete.

[KJ Applicatlons hereby made for one set of Departmental license plates for permanent assignment to the vehicle described on the reverse side hereof

D License Plate 1- has been transferred with the vehicle described, to the following proJect or office

D License Plate 1- has been voided due to loss or destruction of plate or plates bearing that number.

Officer Date

Administrative Officer 9/5/2013

Plate Number Prolect or Office Make Body Tvoe or Bed Year l-54836T Animas-La Plata United Modular Office Trailer 2002

Project Serial No. Bureau Order No. Vehicle ldent or Serial No. Tons-Caoacitv-Yards GSA Purchase Contract No.

FA#:0127965 06PG4N0046 UM258501246002

Remarks

2002 used Model Model - RS2464 (24x64 with hitch - 24 x 60 box) Features -Wood exterior, vinyl siding gypsum interior walls, I-grid ceiling, (2) handicapped restrooms, shingled roof, carpet and tile entry walls, all electric heat and air, alarm ready

This plate replaces 1470446

ACKNOWLEDGEMENT

This license plate number has been recorded In the name of the project office indicated, and assigned to the vehicle described; or otherwise disposed of as follows:

Sianature (Acknowledging Officer) Title Date

�ir....,....a Property Management Specialist 09/05/2013