This document is a Past Performance Questionnaire for GSA Request for Proposal (RFP) 47PF0025R0019 for Masonry Restoration and Cornice Repointing. The questionnaire is designed to collect detailed performance feedback from a previous project reference, with a submission deadline of April 16, 2025, to be sent directly to the GSA Contracting Officer, Rhonda Booker.
The questionnaire comprehensively evaluates the contractor's performance across multiple dimensions, including quality, budget, schedule, management and staffing, administration, and overall performance. It requires the reference to provide ratings on a 5-point scale and optional narrative explanations for various aspects such as contract conformance, budget management, schedule adherence, subcontractor management, communication effectiveness, client sensitivity, and administrative responsiveness. The form is structured to capture nuanced insights into the contractor's past performance, which will likely be used in evaluating future contract awards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF 1442_Revised.pdf | ||
| Amendment 0003.pdf | ||
| Price Breakdown_Revised.pdf | ||
| Staging.pdf | ||
| Clarification Responses.pdf | ||
| Pre-Bid Agenda.pdf | ||
| ESL Masonry Sign In Sheet.pdf | ||
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| WD IL20250007_031425.pdf | ||
| Form SF1442.pdf | ||
| Form_GSA527.pdf | ||
| Specifications.pdf | ||
| Drawings.pdf | ||
| RFP 47PF0025R0019.pdf | ||
| Form_SF24.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAST PERFORMANCE QUESTIONNAIRE
RFP 47PF0025R0019
Masonry Restoration and Cornice Repointing
Please complete and submit this reference directly to the GSA Contracting Officer, Rhonda Booker, at rhonda.booker@gsa.gov, no later than April 16, 2025
Section 1 – To be completed by the Contractor
Contractor’s Name:
Address:
Telephone Number:
Point of Contact (POC):
Role of the POC:
Project Title or Brief Description of the Work:
Dates of Performance:
Section 2 – To be completed by the Reference
Please complete the following questionnaire on behalf of the contractor listed in Section 1. Only the project listed in Section 1 shall be considered for this evaluation. For each question below, select the rating that best describes the Contractor’s performance. Please provide a narrative explanation where appropriate; any narrative comments are greatly appreciated. The completed questionnaire should be emailed directly to the Contracting Office to ensure the confidentially of your responses. Your responses will be reviewed solely for the purposes of a past performance evaluation and only the selection committee will see your response.
Name of Respondent:
Title/Company Name:
Role of Respondent on the Project being Referenced:
Telephone:
Email:
If you have additional comments to provide, please add them at the end of the attached questionnaire.
Thank you, in advance, for your time and providing GSA with this valuable feedback.
QUALITY
1. Overall, how well did the quality of the work conform to the contract requirements?
Excellent - 5 4 3 2 1 - Poor
BUDGET
2. Overall, how was the contractor’s performance with regards to budget?
3. Was the project completed within the original contract budget? Yes No If not, please provide the reason for actual cost differences. (e.g. owner driven changes, differing site conditions, errors and omissions, etc…)
4. Was change order work pricing determined fair and responsible? Yes No
If there were issues with change order pricing, please explain.
SCHEDULE
5. Overall, how was the contractor’s performance with regards to schedule?
6. Did the contractor complete the project within the original contract schedule? Yes No If not, what were the reasons for changes to the schedule?
MANAGEMENT & STAFFING
7. Did the Contractor staff the job adequately? (PM, Superintendent, etc.) Yes No
8. Were key personnel adequately qualified for their positions? Yes No
9. How well did the prime contractor manage his subcontractors? (e.g. Coordinating trades, updating subs on changes to the SOW, prompt payment, performance issues, etc…)
10. How effective was the Contractor at communicating with key project stakeholders?
11. How well did the Contractor demonstrate sensitivity to client/tenant concerns? (e. g. Coordination issues, site cleanliness, noise, etc…)
ADMINISTRATION
12. How responsive and responsible was the contractor in administrative areas? (e.g. Documenting progress, responding to RFI’s, processing payments, tracking changes, etc.)