This is a Technical Specifications document for the Eugene Water & Electric Board (EWEB) detailing improvements to the Hayden Bridge Lower Pond facility in Springfield, Oregon, under Work Order 2100969. The project encompasses extensive infrastructure improvements including installation of approximately 470 feet of 24-inch C900 pipe with removal of 345 feet of existing 18-inch pipe, installation of 1,090 feet of 3-inch HDPE water line, construction of two new manholes (48-inch and 60-inch), installation of six fire hydrants, construction of a concrete overflow structure with level control and associated walkway, demolition of existing overflow structures, construction of 14-foot-wide gravel access road (approximately 350 feet) and 10-foot-wide pond maintenance road (approximately 70 feet), recondition of approximately 1,000 feet of existing perimeter road, excavation of accumulated pond material, construction of sludge collection sumps, removal of approximately 300 feet of cyclone site fencing, and comprehensive erosion control and site restoration. The work must comply with prevailing wage requirements and is subject to weekly progress meetings with mandatory two-week rolling schedules submitted by the contractor. EWEB will conduct inspections and coordinate with a special inspector, and the contractor is responsible for all construction staking, as-built drawings, and final project closeout documentation.

Payment for work is structured on a combination of lump-sum and unit-price basis, with mobilization paid at 75 percent upon achievement of five percent work completion and the remainder upon substantial completion. Most items are bid as lump-sum with progress payments based on percentage of work completed, while excavated material from the lower pond and rock excavation are paid by actual cubic yards removed. The contractor must obtain all necessary permits, provide a comprehensive construction safety plan addressing OSHA requirements, and maintain a valid contractor's license. All materials including ductile iron pipe, PVC, HDPE pipe and fittings, valves, hydrants, and concrete must meet specified AWWA and ASTM standards and be approved through the submittal process before installation. The contract expires June 30, 2027, and includes detailed requirements for hydrostatic testing, erosion and sediment control in compliance with City of Eugene standards, and all testing must be witnessed by EWEB representatives.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EUGENE WATER & ELECTRIC BOARD

Hayden Bridge Lower Pond Improvements

WO 2100969

TECHNICAL SPECIFICATIONS

OCTOBER 2026

EXPIRES 06/30/2027

Docusign Envelope ID: 8879DD70-21BD-84FC-8131-CFA78C46DA73

October 2026 TOC-i Eugene Water & Electric Board WO 2100969 HB Lower Pond Improvements

TABLE OF CONTENTS

TECHNICAL REQUIREMENTS: PLANS, SPECIFICATIONS, AND DETAILS

CONTRACT SPECIFICATIONS

Section Title

01010 SUMMARY OF WORK

01014 WORK COORDINATION SEQUENCE & SCHEDULE

REQUIREMENTS

01060 SAFETY AND HEALTH

01200 MEASUREMENT AND PAYMENT

01250 PROJECT MEETINGS

01300 SUBMITTALS

01400 QUALITY CONTROL

01560 CONSTRUCTION SITE MANAGEMENT

01700 RESTORATION OF IMPROVEMENTS

01710 CONSTRUCTION STAKING

01720 AS BUILT DRAWINGS

01750 CONTRACT CLOSEOUT REQUIREMENTS

02200 EXCAVATION AND BACKFILL

02600 PIPING

02601 HDPE PIPING

02606 VALVES AND HYDRANTS

02675 TESTING

03301 REINFORCED CONCRETE

03400 PRECAST CONCRETE UTILITY STRUCTURES.

STANDARD DETAILS

WC20 THRUST BLOCKS

WC150 VALVE BOXES TYPICAL INSTALLATION

WC210 TYPICAL PRESSURE REDUCING VALVE VAULT

WC220 TYPICAL TRENCH SECTION

RD130 BOLLARDS

October 2026 TOC-ii Eugene Water & Electric Board

DRAWINGS

G1 VICINITY MAP, KEY MAP, AND INDEX OF DRAWINGS

G2 SYMBOLS, ABBREVIATIONS AND NOTES

C1 SITE PLAN

C2 ROAD IMPROVEMENT PLAN

C3 LOWER POND - PLAN

C4 DETAILS – SHEET 1

C5 DETAILS – SHEET 2

S1 OVERFLOW STRUCTURE - GENERAL NOTES

S2 OVERFLOW STRUCTURE PLAN & DETAILS

S3 OVERFLOW STRUCTURE - ELVATION

October 2026 01010-1 Eugene Water & Electric Board

SECTION 01010

SUMMARY OF WORK

PART 1 - GENERAL

1.01 GENERAL

The work covered under this contract will be performed at the Hayden Bridge Filtration Plant in Springfield, Oregon.

1.02 DESCRIPTION OF PROJECT

The work to be performed under this contract includes but is not limited to:

• Installation of approximately 470 feet of 24-inch C900 and demo/removal of approximately 345 feet of existing 18-inch pipe.

• Installation of a 24-inch by 24-inch tee with (1) 24-inch butterfly valves connecting to proposed and existing pipelines.

• Construction of (1) 48-inch manhole and existing manhole repairs.

• Construction of (1) 60-inch manhole.

• Removal/replacement/relocation of existing valves and drain piping.

• Installation of approximately 1090 feet of 3-inch HDPE water line.

• Installation of (6) fire hydrants.

• Construction of (1) concrete overflow structures and level control structure, with associated walkway, railway, etc. Demolish existing overflow structure and pump platform.

• Construction of 14ft wide gravel access road (approx. 350ft), 10 ft wide pond access maintenance road (approx. 70 ft) and road shoulder stabilization as required.

• Recondition existing lower pond perimeter road and access driveway from the Hayden Bridge Road intersection to the Upper settling pond (approx. 1000ft).

• Construction/Demolition of steel cyclone site fence (approx. 300ft).

• Removal of accumulated material from lower settling pond.

• Construction of sludge collection sumps and suction piping.

• Installing erosion control, finish grading, restoration of improvements, and stabilizing disturbed areas.

1.03 WORK COMPLETED BY OWNER

EWEB will complete the following work.

October 2026 01010-2 Eugene Water & Electric Board

• Inspection services.

1.04 SCHEDULE

All work shall be completed by the dates specified in Section 00400.

1.05 PREVAILING WAGES

Prevailing Wages are required for the project. See Specification Section 00830.

1.06 CLEAN-UP

• Keep the work site, staging areas, and Contractor’s facilities clean and free from rubbish and debris.

• Remove materials and equipment from the site when they are no longer necessary.

• Demolished materials shall not be stored on site.

• Clear all equipment, unused materials, and rubbish from the site upon completion of the work and before final acceptance, the work site shall be cleared of equipment, unused materials, and rubbish.

1.08 PERMITS

CONTRACTOR shall obtain:

• Any permits required to complete the work.

END OF SECTION

October 2026 01014-1 Eugene Water & Electric Board

SECTION 01014

WORK COORDINATION, SEQUENCE, AND SCHEDULE REQUIREMENTS

PART 1 – GENERAL

1.01 SECTION INCLUDES

A. Requirements for the coordination, sequencing, and scheduling of the work.

1.02 CONTINUITY OF OPERATIONS

A. GENERAL

Coordinate the construction of the improvements to limit any disruptions in the normal operation of the Hayden Bridge Filtration Plant.

B. ACCESS

Coordinate work to avoid interference with access to the Hayden Bridge Filtration Plant. Contractor shall use dedicated contractor access road whenever feasible. Any work that may affect plan operations shall be coordinated with the Plant operators at least 48 hours in advance. See plan

1.03 WORK SEQUENCE

A. Work sequence requirements are outlined on the drawings

1.04 COORDINATION

A. Coordinate scheduling, submittals, and the work to ensure an efficient and orderly sequence of installation and construction of interdependent elements.

B. Additional Coordination requirements are outlined on the Drawings.

1.05 SCHEDULE

A. Provide a minimum 48 hours notice for EWEB inspections.

B. Provide a minimum of 1 weeks’ notice prior any interruptions to the existing Backwash and Filter to Waste systems.

1.06 SUBMITTALS

A. Submit, a minimum of two weeks prior to any scheduled water disruptions, a detailed construction plan. Include a contingency plan if the work cannot be completed as scheduled.

B. The Contractor shall not proceed with the work until the plan and schedule have been returned to the Contractor with the approval of the Engineer.

C. Submit in accordance with Section 01300.

October 2026 01060-1 Eugene Water & Electric Board

SECTION 01060

SAFETY AND HEALTH

PART 1 – GENERAL

1.01 SECTION INCLUDES

A. Contractor’s responsibilities for safety during all work for this project.

1.02 GENERAL

B. The Contractor assumes full responsibility for safety for all work related to the Contract Documents. By submitting a bid, the Contractor certifies that they are experienced and qualified to anticipate and meet the safety and health requirements of this project.

1.03 SAFETY AND HEALTH REGULATIONS

A. Safety and Health Regulations for Construction, under Section 107 of the Contract Work Hours and Safety Standards Act, as set forth in Title 29, C.F.R.

B. Federal and State Occupational Safety and Health Act, as amended.

1.04 CONSTRUCTION SAFETY PLAN

A. Submit, in accordance with Section 01300, a construction site safety plan, which details the methods and procedures to comply with State, Federal, and local health and safety laws, rules and requirements for the duration of the Contract Time. At a minimum include the following:

1. Procedures for providing workers with an awareness of safety and health hazards expected to be encountered during the course of construction.

2. Safety equipment appropriate to the safety and health hazards expected to be encountered during construction. Include warning devices, barricades, safety equipment in public right-of-way and protected areas, and safety equipment used in multi-level structures.

3. Methods for minimizing employees’ exposure to safety and health hazards expected during construction.

4. Procedures for reporting safety or health hazards.

5. Procedures to correct and follow-up on a recognized safety and health hazard.

6. Procedures for investigation of accidents, injuries, illnesses and unusual events that have occurred at the construction site.

7. Periodic and scheduled inspections of general work areas and specific

October 2026 01060-2 Eugene Water & Electric Board work stations.

8. Training for employees and workers at the job site, including at a minimum:

a. General Safety Rules, including reporting of Unsafe Conditions

b. Hazard Communication & chemical safety

c. Evacuation Routes, Alarms & Procedures

d. Hot Work Program

e. Process Safety Management

f. Personal Protective Equipment

9. Methods of communication of safe working conditions, work practices and required personal protection equipment.

10. Identify the OSHA Certified competent person, defined as one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees and one how has the authority to take prompt corrective action, and who will be onsite during all phases of construction.

B. Assume responsibility for every aspect of Health and Safety on the job site, including the health and safety of Subcontractors, suppliers, and other persons on the job site.

C. Transmit to Owner copies of reports and other documents related to accidents or injuries encountered during construction.

D. To ensure the safety of Contractor and Owner employees, facilities and equipment, the Contractor shall conduct comprehensive pre-work safety review conferences with employees.

E. Provide to the Engineer a listing of all hazardous chemicals with applicable Material Safety Data Sheets that will be used on the job site.

F. Utilize employees trained in safe practices and instruct employees as to the specific potential hazards of this project and protection procedures that are to be used during the course of the project. Contractor shall maintain records as to training and enforcement procedures that assure that safe practices are followed.

G. Contractor shall be responsible for providing all necessary safety equipment.

October 2026 01200-1 Eugene Water & Electric Board

SECTION 01200

MEASUREMENT AND PAYMENT

1.01 SECTION INCLUDES

A. Requirements for measurement and payment for unit price items.

1.02 GENERAL

A. The total bid price shall cover all work required by the Contract Documents and cover all costs in connection with the proper and successful completion of the work. The final price shall include furnishing materials, equipment, supplies, and appurtenances; providing all construction equipment and tools necessary to complete the work; performing all necessary labor and supervision; and profit and overhead.

B. Payment for work bid at a unit price will be made only for actual quantities of accepted work, measured as specified below. The quantities appearing in the bid schedule are approximate and are provided for comparison of bids. EWEB does not warrant that the actual individual items, amount of work, or quantities will correspond to those shown in the bid schedule.

C. Items bid on a “Lump Sum” basis shall result in a complete structure or system in satisfactory working condition in respect to functionality of the installation.

1.03 MEASUREMENT AND PAYMENT

A. The numbers below correspond to the bid item numbers listed in Section 00400.

1. Mobilization and Demobilization

a. This item includes all requirements for mobilization and demobilization.

b. Measurement:

This item will not be measured.

c. Payment:

The amount paid for mobilization in the progress payment will be based on the percent of the original contract amount, as follows:

i. When 5% of the work is completed: 75 percent of the amount for mobilization and demobilization will be paid

October 2026 01200-2 Eugene Water & Electric Board

ii. When all work is substantially complete: the remaining amount will be paid

2. Install 24-inch C900 Drain Line and demo/removal of 18-inch existing pipe

a. This item includes all materials and work required for installing 24-inch ductile iron pipe and demo/removal of 18-inch existing pipe, including all trenching to the depths shown on the drawings, backfilling and all required joint restraint systems for pipe, fitting and appurtenances.

c. Payment:

Payment will be lump sum with progress payments based on percentage of work completed.

3. Install 24-inch Tee with (1) 24-inch butterfly valve connecting to proposed and existing pipelines

a. This item includes all materials and work required for installing 24-inch Tees and 24-inch butterfly valves connecting to proposed and existing pipelines including all trenching to the depths shown on the drawings, backfilling, all required joint restraint systems for pipe, fittings, appurtenances.

c. Payment:

4. Construction of (1) 48-inch manholes and existing manhole repairs.

a. This item includes all materials and work required for manhole

October 2026 01200-3 Eugene Water & Electric Board construction and repairing existing manholes including all trenching and backfill. Contractor to provide everything needed to complete the work.

5. Construction of (1) 60-inch manhole.

a. This item includes all materials and work required for manhole construction including all trenching and backfill. Contractor to provide everything needed to complete the work.

6. Removal/replacement/relocation of existing valves and drain piping and extending pump discharge line around the lower pond.

a. This item includes all materials and work required for Removal/replacement/relocation of existing valves and drain piping and extending pump discharge line around the lower pond.

October 2026 01200-4 Eugene Water & Electric Board

7. Installation of approximately 1090 feet of 3-inch HDPE water line.

a. This item includes all materials and work required for installation of approximately 1090 feet of 3-inch water line.

8. Installation of (6) fire hydrants.

a. This item includes all materials, labor, equipment, and work required to install fire hydrants.

This item will be measured per the number of fire hydrants installed.by

Payment will be based on the number of fire hydrants installed.

9. Construction of (1) concrete overflow structures and level control structure, with associated walkway, railing, etc.

Removal and demolition of existing overflow structure platform and all associated equipment.

a. This item includes all materials, labor, equipment, and work required to construct (1) concrete overflow structures and level control structure; with associated walkway, railing, etc. Demolish existing overflow structure and pump platform.

October 2026 01200-5 Eugene Water & Electric Board

b. Measurement:

This item will not be measured.

c. Payment:

10. Construct 14-foot width gravel access/lower pond road intersection (approx. 350ft length), 10-foot width pond access road (approx. 70ft length) and road shoulder stabilization as required.

a. This item includes all materials, labor, equipment, and work required to construct 14-foot width gravel access/lower pond road intersection (approx. 350ft length), 10-foot width pond access road (approx. 70ft length) and road shoulder stabilization.

c. Payment:

11. Recondition existing lower pond perimeter road and access driveway from the Hayden Bridge Road intersection to the Upper settling pond.

a. This item includes all materials, labor, equipment, and work required to recondition/regrade and compact gravel road surfacing.

c. Payment:

October 2026 01200-6 Eugene Water & Electric Board

12. Remove/Excavate accumulated material from Lower Pond.

a. This item includes all materials, labor, equipment, and work required to excavate and dispose of accumulated material from the Lower Pond.

This item will be measured based on a count of truckloads and truckload capacity.

c. Payment:

Payment will be based on actual cubic yards of material excavated and removed.

13. Construct sludge collection sumps and suction piping

a. This item includes all materials and work required for the sludge collection sump and suction piping construction.

c. Payment:

14. Rock excavation removal.

a. This item includes all materials and work required for rock excavation removal.

This item will be measured by the insitu from pre and post rock excavation survey or field measurements.

October 2026 01200-7 Eugene Water & Electric Board

Payment will be based on actual cubic yards of material excavated and removed.

15. Erosion Control, Grading, Site Restoration and Stabilizing Disturbed areas.

a. This item includes all materials and work required for installing and maintaining Erosion Control, Finish Grading, and Site Restoration.

15. Items Not Listed:

a. Where work is required but does not appear as a separate item in the bid form, the cost for that work shall be included and absorbed in the unit prices listed in the bid schedule.

October 2026 01320-1 Eugene Water & Electric Board WO 2100969 HB Lower Pond Improvement

SECTION 01250

PROJECT MEETINGS

1.01 SECTION INCLUDES

A. Requirements and Contractor’s responsibilities for project meetings during the work.

1.02 PRECONSTRUCTION MEETING

A. Prior to the start of construction, the Owner will schedule a meeting of the Contractor and their respective representatives. The purpose of the meeting will be to clarify construction contract administration procedures, to establish lines of authority and communication and identify duties and responsibilities of the parties.

B. The agenda, prepared by Owner, for the meeting will cover at least the following items, a more detailed agenda will be distributed at the meeting:

1. Organization, personnel and contact information of the Contractor's forces, including Subcontractors and materials suppliers.

2. Owner’s construction management (CM) organization, personnel and contact information.

3. Channels and procedures for communication.

4. Contractor’s construction schedule, including sequence of critical work.

5. Processing of shop drawings and other data that will be submitted to

Owner for review.

6. Processing of change order requests.

7. Procedures for safety, first aid and security.

8. Procedures for quality control, housekeeping and related matters.

C. Minutes of Meeting

1. The Owner will compile minutes of the meeting and distribute copies to all participants.

October 2026 01320-2 Eugene Water & Electric Board

1.03 PROGRESS MEETINGS

A. Unless otherwise arranged, there will be weekly progress meetings at a location determined by the Owner.

1. The purpose of the weekly meetings is to coordinate the efforts of all concerned to result in smooth and coordinated progress towards completion of the overall project.

2. Owner, Contractor, Subcontractors and suppliers’ representatives as may be needed, other Contractors working at the site, the Project Manager, and other interested or affected parties will attend these meetings.

B. Contractor shall bring to each weekly meeting a two-week rolling schedule. The two-week rolling schedule shall include the Contractor’s proposed daily activities and location(s) of work during the coming two-week period. No work shall commence at the beginning of each work week until the updated two-week rolling schedule is submitted.

C. The Contractor will be required to address the following items at the weekly meeting:

1. Work completed last week.

2. Work anticipated next week.

3. Subcontractors on site the prior week.

4. Subcontractors scheduled on site next week.

5. Contract document deficiencies or questions noted during prior week.

6. Changes in the scope of work during the prior week.

7. Corrective measures and procedures planned to regain planned schedule, cost or quality assurance, if necessary.

8. Report of any accidents, and any site safety issues that need to be addressed.

D. Other Agenda items to be discussed.

1. Review and revise as necessary and approve minutes of previous meetings.

2. Status of submittals of equipment and shop drawings.

3. Identify problems that impede planned progress.

4. Other current business.

October 2026 01320-3 Eugene Water & Electric Board

E. Revision of Minutes

1. Unless published minutes are challenged in writing prior to the next regularly scheduled progress meeting, they will be accepted as properly stating the activities and decisions of the meeting.

2. Persons challenging published minutes shall reproduce and distribute copies of the challenge to all indicated recipients of the particular set of minutes.

3. Challenge to minutes shall be settled as priority item of "old business" at the next regularly scheduled meeting.

F. Minutes of Meeting

1. The Owner will compile minutes of each project meeting and will furnish copies to all participants.

October 2026 01300-1 Eugene Water & Electric Board

SECTION 01300

SUBMITTALS

1 PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Submittal requirements to demonstrate compliance with the provisions and intent of the contract documents.

1.02 GENERAL

A. The documentation to be submitted for each item or process incorporated in the work is specified in the individual specifications.

B. Submittal requirements may be waived for those items furnished from the EWEB Warehouse

C. Work cannot proceed until the material submittals have been returned marked approved or conditionally approved.

1.03 SUBMITTAL PREPARATION

A. Verify that all features of all products conform to the specified requirements.

B. Clearly edit submittal documents to indicate only those items, models, or series of equipment that are being submitted for review. Cross out or otherwise delete all extraneous materials.

C. Ensure that there is no conflict with other submittals.

D. Coordinate submittals among subcontractors and suppliers.

E. Coordinate submittals so that work will not be delayed. No extension of time will be allowed because of failure to properly schedule submittals.

F. Verify field conditions that relate to the submittal item.

G. Ensure the submittal documents are clear and legible. Submittal documents determined to be illegible will be returned without review.

1.04 TRANSMITTAL PROCEDURE

A. Transmittal Form

1. Include a transmittal form with each submittal.

2. The transmittal form shall indicate any proposed material, equipment, or method of work that deviates from the contract documents.

3. Sequentially number (starting at 1) each transmittal form. Resubmittals shall be assigned a sequential letter. Submittal 25 B for example, is the second resubmittal of submittal 25.

October 2026 01300-2 Eugene Water & Electric Board

B. Submit one PDF electronic copy of the submittal for review and comment unless the submittal is longer than 50 pages in length or it results in an electronic file larger than 6 megabytes. If either of these conditions exist, submit three hard copies.

1.05 REVIEW PROCEDURE AND EFFECT OF REVIEW

A. General

1. Review is for general compliance with the contract documents and does not extend to means; methods; techniques; sequences or procedures of construction; verifying quantities, dimensions, weights, gages, or fabrication processes; or to safety precautions or programs.

2. Review of a separate item will not indicate approval of the assembly in which the item functions.

B. Engineer will review the submittal within 30 days after receipt. The review shall indicate the following:

1.06 REVIEW COSTS

A. EWEB is responsible for the cost of the initial submittal and the first revised submittal review.

B. Contractor is responsible for the cost to review additional resubmittals. The cost of review includes, without limitation, administrative, design and engineering activities directly related to review of submittals.

Review Comment Effect of Comment

APPROVED The submittal is in compliance with the construction documents. The Contractor may begin work or incorporate the material covered by the submittal.

CONDITIONALLY APPROVED The submittal requires limited corrections. The Contractor may begin implementing the work method or material in accordance with the noted corrections without resubmittal.

NOT ACCEPTABLE -

RESUBMIT

The submittal is insufficient, contains incorrect data, or does not comply with the Contract Documents. The Contractor shall not begin work associated with the submittal item until the submittal has been revised, resubmitted, and returned with the review comment “Approved” or “Conditionally Approved”.

REVIEW NOT REQUIRED The submittal will be returned without a review by an Engineer.

October 2026 01400-1 Eugene Water & Electric Board

SECTION 01400

QUALITY CONTROL

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Requirements for quality control and inspection.

1.02 GENERAL

A. Inspection by the Owner’s Authorized Representative does not relieve the Contractor of obligations to complete the work per the requirements of the Contract Documents.

B. EWEB will contract with a special inspector. Contractor will coordinate the special inspections.

1.03 INSPECTION

A. The Contractor shall provide 24 hours notice before a required inspection.

B. Required inspections:

Item EWEB Special Inspector

City of Eugene

Prepared subgrade prior to placing any bedding material below the pipe or vaults every 100 ft

X

Compacted bedding material below the pipe, valves, and vaults every 100 ft

X X

Compacted pipe zone every 100 ft X X

Compacted trench zone every 100 ft X X

Pipe, valve, and vault installation prior to backfilling X

Existing sewer pipe where the water line crosses below X

Prepared road subgrade X X X Temporary Paving X X X Final Paving X X

C. Materials and workmanship not conforming to EWEB's requirements shall be considered defective and will be rejected. Defective work or material, whether in

October 2026 01400-2 Eugene Water & Electric Board place or not, shall be removed immediately from the site and replaced with materials or workmanship that conforms to EWEB’s requirements at the expense of the contractor.

D. Inspection by EWEB or acceptance of any part of the facilities by EWEB is not a waiver of any provision of the Plans and Specifications.

E. EWEB will inspect joint trench utilities to ensure proper placement. Final acceptance of the installation must be coordinated with each individual utility.

1.04 SAMPLES AND TESTS

A. The source of supply of materials for the Work will be subject to tests and inspection before installation when requested by EWEB. EWEB’s Authorized Representative shall have full authority to require continuing tests and inspection of any source of supply or supplier’s source plants where there is evidence of irregularities in the materials presented or that the materials do not fully comply with the specifications.

B. All tests of materials furnished by the Contractor shall be made in accordance with the specified standards.

October 2026 01560-1 Eugene Water & Electric Board

SECTION 01560

CONSTRUCTION SITE MANAGEMENT

1.01 SECTION INCLUDES

A. Requirements for providing a neat and environmentally acceptable work site.

1.02 SITE MAINTENANCE

A. The Contractor shall keep the work site, staging areas, and Contractor’s facilities clean and free from rubbish and debris. Remove materials and equipment from the site when they are no longer necessary. Do not store equipment removed as part of demolition on site. Upon completion of the work and before final acceptance, clear the work site of equipment, unused materials, and rubbish to present a clean and neat appearance.

B. CLEAN-UP

1. Waste material of any kind will not be permitted to remain on the work site or on adjacent streets. Immediately upon such materials becoming unfit for use in the work, they shall be collected, carried off the site, and properly disposed of by the Contractor.

2. In the event that waste material, refuse, debris, and/or rubbish are not removed from the site by the Contractor, the Owner reserves the right to have the waste material, refuse, debris and/or rubbish removed and disposed of at the expense of the Contractor.

3. Paints, solvents, and other construction materials shall be handled with care to prevent entry of contaminants into storm drains, surface waters, or soils.

C. STREET CLEANING:

1. The Contractor shall prevent dirt and dust from escaping from trucks departing the site, by covering dusty loads, washing truck tires before leaving the site, and other reasonable methods.

2. In the event that the above requirements are violated and the Contractor takes no action after notification of infraction by the Owner, the Owner reserves the right to have the streets in question cleaned by others and the expense of the operation charged to the Contractor.

October 2026 01560-2 Eugene Water & Electric Board

1.03 AIR POLLUTION CONTROL

A. The Contractor shall not discharge smoke, dust, and other contaminants into the atmosphere that violate the air pollution regulations for the area. Internal combustion engines shall not be allowed to idle for prolonged periods of time.

Maintain construction vehicles and equipment in good repair. Exhaust emissions that are determined to be excessive by the Engineer shall be repaired or replaced.

1.04 NOISE CONTROL

A. The Contractor shall comply with all local controls and noise level rules, regulations, and ordinances which apply to any work performed pursuant to the Contract. If the requirements of this Section are more restrictive than those of the local regulations, the requirements of this Section shall govern.

B. Each internal combustion engine, used for any purpose related to this Contract, shall be enclosed and be equipped with a muffler of a type recommended by the manufacturer. No internal combustion engine shall be operated on the project without said muffler and enclosure.

1.05 EROSION AND SEDIMENT CONTROL PLAN

A. Prepare a sediment and erosion control plan in accordance with the City of Eugene Standards and the Drawings. EWEB will coordinate the permit submittal with the City of Eugene. The application requirements are included in Appendix D.

B. Plan and execute construction by methods to control surface drainage from stockpiles, excavations and from borrow and waste disposal areas. Prevent erosion and sedimentation.

C. Minimize the amount of bare soil exposed at one time. Cover all stockpiles during wet weather.

D. Provide temporary sediment controls such as silt fences, check dams, straw bale barriers, sand bag barriers, rock filter beds, sediment traps, sediment basins, drop inlet protection, and sand bag protection in accordance with the City of Eugene standards.

E. Construct fill and waste areas by selective placement to avoid erosive surface silts or clays.

F. Construction site housekeeping practices include but are not limited to: stabilized construction entrances if required, solid waste management, concrete waste disposal, hazardous materials management, spill prevention and control, daily maintenance and clean up.

October 2026 01560-3 Eugene Water & Electric Board

G. The Contractor shall not perform any work including but not limited to clearing and grubbing, excavation or earthwork of any type until written acceptance of the erosion and sediment control plan has been received from the Owner and approved by the City.

October 2026 01700-1 Eugene Water & Electric Board

SECTION 01700

RESTORATION OF IMPROVEMENTS

1.01 SECTION INCLUDES

A. Requirements for restoration of work areas after installation and construction of new facilities.

1.02 PROTECTION OF EXISTING FACILITIES

A. Take precautions to protect the integrity and usefulness of existing facilities.

B. Protect installed Work and provide special protection where required in individual specification sections.

C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

D. Prohibit traffic from landscaped areas.

E. Immediately repair or replace existing equipment, controls, structures, or facilities that are damaged as part of the Work.

F. Restore disturbed areas to preconstruction conditions or better.

a. If necessary, remove existing structures including curbs, gutters, and pipelines, as necessary for the performance of the work.

i. Repair existing structures that are damaged as a result of the Work under this contract

ii. Rebuild or replace the structures in as good a condition as originally found or better.

October 2026 01710-1 Eugene Water & Electric Board

SECTION 01710

CONSTRUCTION STAKING

1.01 CONSTRUCTION STAKING

A. Construction staking shall be provided by the Contractor.

1.02 LAYOUT AND MEASUREMENT TO BE PERFORMED BY CONTRACTOR

A. Contractor is responsible for laying out the work from the dimensions provided on the contract drawings.

B. Contractor is responsible for all measurements required for the execution of the work.

C. Furnish, at the Contractor’s own expense, stakes, equipment, tools, materials, and all labor as required in layout of any parts of the work from the control points provided by the Owner.

D. The Engineer may suspend work at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

October 2026 01720-1 Eugene Water & Electric Board

SECTION 01720

AS-BUILT DRAWINGS

A. Requirements for the preparation and maintenance of the project as-built drawings.

1.02 PROJECT AS-BUILT DRAWINGS

A. Maintain a neatly and accurately marked set of record drawings showing the final locations and layout of all mechanical equipment, piping and conduit; wiring and wire terminations, structures; and other facilities.

B. not used C. Drawings shall be kept current, with all work instructions and change orders;

mechanical, equipment accommodations; and construction adjustments.

D. The Owner reserves the right to inspect the drawings at any time. Progress payments, or portions thereof, may be withheld if drawings are not accurate and current.

E. Deliver to the Engineer, prior to acceptance of work, 1 set of neatly marked record drawings, accurately showing all the information required above.

F. Marking of the contract documents shall be performed using colored pencils as follows:

Additions Red Deletions Green Comments Blue Dimensions Graphite

1.03 SUBMITTAL AND PAYMENT

A. Submit as-built documents in accordance with Section 01300.

B. Final payment will not be made to the Contractor for the as-built documents until they are noted “Approved” by the Owner as part of the Section 01300 submittal review process.

October 2026 01750-1 Eugene Water & Electric Board

SECTION 01750

CONTRACT CLOSEOUT REQUIREMENTS

PART 1 – GENERAL

1.01 SECTION INCLUDES

A. This Section outlines the requirements of events required for Contract Closeout, the period that commences when the work nears substantial completion through final payment.

1.02 CONTRACT CLOSEOUT REQUIREMENTS

A. General

1. The sequence of events and the descriptions listed below represent the suggested order of activities as the Contract proceeds from construction to closeout. Not all work will proceed in the order listed below, and the Contractor may request adjustments for the Owner’s consideration. The following Closeout Sequence of Events is general in nature and does not encompass all work that must be completed.

B. Closeout Sequence of Events

1. Complete the majority of the work including but not limited to all testing, training, and commissioning.

2. Request an inspection after the new facilities are usable and functional.

3. If the Owner finds the work suitable for operation, the Owner will prepare and submit to the Contractor for signature a certificate of substantial completion that at a minimum includes the following:

a. Date of substantial completion (the date of inspection).

b. Responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the work, and insurance.

c. Final completion date.

4. If Owner approves the issuance of a Certificate of Substantial Completion, the Contractor may submit a pay request for all money owed except retainage and other work on approved schedule of values that has not been completed.

5. The Owner will prepare a punch list based on the items discussed during the inspection. The punch list may be modified as work progresses.

6. Owner processes substantial completion pay request, if received.

7. Contractor completes all items on punch list, including submission of all required documents as specified in Section 1.03 by the final completion date.

8. Contractor submits Notice of Final Completion.

October 2026 01750-2 Eugene Water & Electric Board

9. Owner conducts final inspection to verify all punch list items have been addressed and all required documents submitted.

10. If all punch list items have been addressed and as-built drawings received Owner approves Notice of Final Completion. If all punch list items are not addressed, Owner will issue a revised punch list.

11. Contractor returns all Owner locks and keys and submits a final pay request.

12. Owner processes final pay request.

1.03 REQUIRED DOCUMENTATION FOR CONTRACT CLOSEOUT

A. Signed Certificate of Substantial Completion.

B. The following documents shall be submitted following Owner’s acceptance of

Substantial Completion and Contractor’s completion of all Punch List items.

Owner must receive and approve these documents prior to acceptance of the Notice of Final Completion and processing final pay request.

1. Accounts Affidavit as provided in Section 00620. This form must be signed by the Contractor and notarized.

2. Notice of Final Completion. This document submitted and signed by the

Contractor shall state that the project has been completed.

3. An insurance certificate demonstrating that the policy is still in force.

4. Certified Payroll Statements. These statements are required by the Oregon

Bureau of Labor and Industries (BOLI) for projects larger than $50,000.

5. Evidence of Insurance. Submit insurance certificate demonstrating compliance with insurance requirements set forth in the General Conditions and Supplemental Conditions.

6. Written Statement that Insurance Policy is Renewable.

7. Consent of Surety. Provide documentation from Surety stating that there are no unresolved claims and that Surety approves of final payment to Contractor.

8. Certificate of Occupancy (if required by local building official).

9. Spare Parts and Materials. Provide all spare parts and materials listed in the specifications and drawings.

10. Approved Operation and Maintenance Manuals.

11. Record drawings.

12. Warranty Certificates.

PART 2 – NOT USED

PART 3 – NOT USED

October 2026 02200-1 Eugene Water & Electric Board

SECTION 02200

EXCAVATION AND BACKFILL

PART 1 – GENERAL

A. excavation, backfilling, grading, and compaction.

1.02 GENERAL

This section covers the requirements for trench excavation, backfilling, grading, and compaction.

1.03 MATERIALS

A. Material Classifications

Furnish the following materials meeting the requirements of the current edition of the Oregon Standard Specifications:

Class A Backfill - Native or common material that, in the opinion of the Engineer, meets the characteristics required for the specific surface loading or other criteria of the backfill zone.

Class B Backfill - Granular material consisting of gravel or crushed rock. Designated size shall be 1" - 0 or 3/4" - 0.

Class C Backfill – not allowed.

Class D Backfill - Use pit run or bar run material, well graded from coarse to fine. The maximum dimension shall be 3 inches.

Class E Backfill - Use Controlled Low-Strength Material (CLSM) conforming to Section 00442 of the Oregon Standard Specifications for Construction.

B. PIPE ZONE AND BEDDING

Pipe zone and pipe bedding shall be Class B material.

C. VAULT AND STRUCTURE FOUNDATIONS

Unless otherwise specified foundations for vaults and other structures shall be constructed of Class B backfill.

1.04 EXECUTION

A. EXCAVATION:

Construct trench sides as nearly vertical as practicable. Do not slope the sides of trenches between the bottom of the trench and the elevation of the top of the pipe.

October 2026 02200-2 Eugene Water & Electric Board

Minimum trench widths are shown on the standard details. Wider trench widths may be required by EWEB, the jurisdictional authority or the Design Engineer.

Grade bottom to allow for placement of the required bedding material

1. Removal of Surfacings and Obstructions

Cleanly saw cut and remove all pavement and other surfacings per the jurisdictional authority’s requirements.

2. Excavation

Excavate to the line and depths indicated in the plan accounting for the required bedding material.

3. Sheeting, Shoring and Bracing

a. Trench safety is the sole responsibility of the contractor

b. Shoring, sheeting, and bracing shall be installed as necessary to maintain a safe work environment compliant with all Federal and State safety regulations.

c. Increase trench widths as necessary and remove or adjust shoring as backfill progresses to prevent disrupting backfill and creating voids.

d. An OSHA competent person shall be onsite continuously during construction and be responsible for maintaining a safe excavation.

4. Trench Foundation

Remove any soil along trench base that is soft or high in organic or deleterious material.

Overexcavate soft, unsuitable material as necessary to provide a firm stable base. Stabilize trench foundation with compacted Class B backfill material as necessary

5. Vault Foundations

Place material in 6 inch lifts and compacted as required.

6. Control of Water

Keep excavations free from water during construction. Dispose of excess water in accordance with the jurisdictional authority’s requirements.

B. BACKFILL

This section covers the required backfill materials, pipe bedding, and compaction.

October 2026 02200-3 Eugene Water & Electric Board

1. BEDDING AND TRENCH BACKFILL PROCEDURE:

a. Remove all loose material, wood, and debris from the trench prior to backfilling.

b. Provide a minimum of 4-inches of Pipe Bedding material compacted as specified herein.

c. Do not place bedding in freezing weather or where the material in the trench is already frozen or is muddy, except as authorized.

d. Excavate minimally sized bell holes as necessary so that the pipe barrel lies evenly on the compacted pipe bedding.

e. Pipe Zone material shall extend to a minimum of 12 inches above the crown of the pipe.

f. Shovel slice backfill material into the haunch areas of the pipe, continuous along the length of the pipe.

g. Remove any temporary pipe support structures including timbers prior to backfilling.

h. Backfill pipeline trenches to the level of the original ground surface or underside of the pavement base course.

i. Place backfill material in the trench to the full excavated width.

Place backfill material carefully from a low height in order to minimize damage to pipe coatings.

j. Backfill simultaneously and uniformly on both sides of the pipe.

Hand shovel sufficient material to securely anchor the pipe so that no movement will occur when the next section of pipe is being placed or when additional material is placed.

k. Remove water collecting at the low points along the trench by pumping or other approved means in order to avoid softening of adjacent ground.

l. Backfill trenches located within the public right of way within the shortest possible time so streets can be opened to traffic.

m. Maximum lift, before compaction: 12 inches.

n. Provide uniform and continuous support for each section of utility except at bell holes or depressions necessary for making proper joints.

o. Protect the piping and protective coatings from damage.

p. Compact each loose lift as specified below before placing the next lift.

C. COMPACTION:

1. Compact by means of impact, vibration, or a combination of these methods. Take care to ensure no damage to the pipe or pipe coatings occurs during compaction procedures.

2. Only hand-operated motor driven mechanical compacting equipment shall be used over pipelines until the backfill has been compacted to 12-inches over the crown of the pipe.

October 2026 02200-4 Eugene Water & Electric Board

3. Compaction by hydraulic jetting or ponding is not allowed.

4. Moisture Content: When the moisture content of the fill material is below optimum moisture content as determined by the moisture density curves, add water until the moisture content as necessary to obtain the required compaction values. When the moisture content of the fill material is above optimum moisture content, aerate by blading or other approved methods until the moisture content is adequate to reach required compacting.

5. Compaction shall be in accordance with the following:

Table 4: Compaction Requirements

Pipe Size Installation

Subgrade Base Rock

Gravel Road Surfacing

Vault Foundation

Pipe Zone

Trench Backfill

95%

Pipe Bedding 85%

6. INSPECTION AND QUALITY ASSURANCE

All water facilities shall be inspected by EWEB prior to backfilling. EWEB’s inspector may require the Contractor to take samples and perform moisture content, gradation, compaction, and density tests during placement of backfill materials to check compliance with these requirements.

Test results may be required prior to proceeding with any paving. Design Engineer, when required, shall submit test results from an independent testing firm in accordance with the following:

TABLE 5: TESTING PROCEDURES

Test Standard Procedure

Moisture content ASTM D3017

Density in-place ASTM D1556 or ASTM D2922

Moisture-density relationships ASTM D698 (Standard Proctor)

October 2026 02600-1 Eugene Water & Electric Board

SECTION 02600

PIPING

PART 1 – GENERAL

1.01 SECTION INCLUDES

A. Requirements for furnishing and installing piping materials, thrust restraint devices, connections to existing facilities, and abandonment of existing facilities.

1.02 QUALITY ASSURANCE

A. References

This specification references the latest edition of the following:

1. AWWA C110 “Ductile Iron and Gray Iron Fittings, 3 inch through 48 inch for Water and Other Liquids”

2. AWWA C111 “Rubber-Gasket Joints for Ductile Iron Pressure Pipe and Fittings”

3. AWWA C151 “Ductile Iron Pipe, Centrifugally Cast, for Water or Other Liquids”

4. AWWA C153 “Ductile Iron Compact Fittings for Water Service”

5. AWWA C600 “Installation of Ductile Iron Water Mains and Their Appurtenances”

6. AWWA C605 “Underground Installation of PVC and Molecularly oriented PVCO pressure pipe and fittings”

7. AWWA C905-97 Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 14 in. Through 48 in. (350 mm through 1,200 mm), for Water Transmission and Distribution

8. AWWA C906 “Standard for Polyethylene (PE) Pressure Pipe and fittings 4 In. (100 mm) Through 63 In. (1,600 mm), for Water Distribution and Transmission”

9. ASTM D2774 “Standard Practice for Underground Installation of Thermoplastic Pressure Piping”

1.03 SUBMITTALS

A. Prepare and submit in accordance with Section 01300.

October 2026 02600-2 Eugene Water & Electric Board

B. Submit manufacturer’s data for all pipe material, fittings, appurtenances, and coatings.

PART 2 – PRODUCTS

2.01 GENERAL

Submit proposed manufacturer information for approval.

2.02 DUCTILE IRON PIPE AND APPURTENANCES

A. Ductile Iron Pipe:

a. Pipe Provided by EWEB

B. Fittings:

1. Same material and class as the pipe to which they are joined.

2. Manufactured in accordance with AWWA C110/ANSI A21.10 or AWWA

C153/ANSI 21.53.

C. Joints:

1. Type as indicated on the drawings.

2. Push On Joints:

a. In accordance with AWWA C111/ANSI A21.11 and AWWA C151.

b. Tyton type.

3. Mechanical Joints:

a. In accordance with AWWA C111/ANSI A21.11.

4. Flanged joints: in accordance with AWWA C115 /ANSI 21.15.

5. Restrained Joints:

a. Rated for a minimum water working pressure of 250 psi.

b. Mechanical Joints with Joint Restraint:

i. Mechanical joint with restraint provided by a follower gland with individually actuated wedges or mechanical joint with a gasket and follower gland that increases the resistance to pull-out as pressure or external forces increase.

October 2026 02600-3 Eugene Water & Electric Board

c. Push-on Joint with Joint Restraint:

i. Comply with AWWA C111/ANSI A21.11.

Single gasket with individual stainless steel locking segments vulcanized into the gasket.

D. Gaskets:

1. Conform to AWWA C111/ANSI 21.11.

2. Suitable for flanged or mechanical joints.

3. Flanged gaskets: Full face, 1/8-inch thick red rubber.

E. Lining:

1. Cement mortar in conformance with AWWA C151.

F. External Coating:

1. Pipe: Asphaltic coating in accordance with AWWA C151.

2. Fittings: Asphaltic in accordance with AWWA C110/ANSI A21.10.

G. Lubricant: non-toxic, NSF 61 approved.

H. Polyethylene Encasement:

1. Not required

I. Locator wire:

1. Single strand 12 gauge copper wire with blue insulation.

2. Splice kit:

a. Moisture resistant.

b. Fully encapsulated

c. Connector style: direct bury.

d. Maximum voltage rating: 600 volts.

J. Bolts

1. Flange bolts: 304 stainless steel.

2. All other bolts: Corrosion resistant high-strength low alloy steel.

October 2026 02600-4 Eugene Water & Electric Board

2.03 PVC PIPE AND APPURTENANCES

A. GENERAL:

This section includes materials, installation, and testing of PVC pressure pipe conforming to AWWA C905. Size range is 14- to 48-inch nominal pipe size.

B. SUBMITTALS

1. Submit submittal packages in accordance with Standard Specification Section 01300.

2. Provide affidavit of compliance with AWWA C905.

3. Submit copies of the following manufacturer required tests conducted on the project pipe:

a. Quick-burst strength of pipe and couplings.

b. Flattening resistance of pipe.

c. Record of additional tests after test sample failure.

4. G. Submit restrained joint system installation instructions. Include bolt torque limitations and assembly tolerances.

C. PVC PIPE MATERIAL

1. GENERAL

Provide PVC pipe conforming to AWWA C905 with material cell classification 12454-B per ASTM D 1784. Provide standard pipe having integral bell and spigot with elastomeric gasket and cast iron equivalent outside diameter. Provide pipe in standard 20-foot laying lengths. Provide Class 200 pressure rating with restrained joints.

D. RESTRAINED JOINTS

1. Provide restrained joints using restraining systems that incorporate a series of machined serrations on the inside diameter of a restraint ring to provide positive restraint. Restraining systems shall meet or exceed the requirements of UNI-B-13-94 or ASTM F 1674 and the following:

2. Restraint devices for PVC bell-and-spigot joints shall consist of a split restraint ring installed on the spigot, connected to a solid backup ring seated behind the bell.

3. Restraint devices for connection to ductile iron mechanical joints shall consist of a split restraint ring installed on the PVC pipe behind the ductile iron

October 2026 02600-5 Eugene Water & Electric Board fitting follower gland and gasket and shall retain the full deflection capability of the joint.

4. The split restraint ring shall be machined to match the cast iron equivalent outside diameter of the pipe, provide full 360-degree support around the barrel of the pipe, and shall incorporate a series of machined serrations for gripping the outside surface of the pipe. The serrations shall be uniform and extend the full circumference of the clamp. The ring shall also incorporate a positive means of avoiding applying excessive clamping force to the pipe.

5. Materials used in the restraint device shall be ductile iron conforming to ASTM A 536, Grade 65-45-12.

6. T-bolts, studs, and connecting hardware shall be high strength, low alloy material in…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .