Amendment 0002 - Corrected Q&A

View the file

Other files

File Type Posted
Amend_0005_-_P17PS00522_-revised_Bid_Schedule_B.pdf PDF
Amend_0005_-_Q&A.pdf PDF
Amend_0005_-_SF_30_-_P17PS00522.pdf PDF
Amend_0004_-_F1.3_FIRE_TANK_AND_PUMPHOUSE.PDF PDF
Amend_0004_-_SF-30_P17PS00522.pdf PDF
Amend_0004_-_21_12_19_-_GROUND-MOUNTED_FIRE_WATER_STORAGE_TANKS.PDF PDF
Amend_0004_-_Section_L_Solicitation_(Revised).pdf PDF
Amend_0004_-_Herrmann_House_As-Constructed_Plans.pdf PDF
Amend_0004_-_171024_MIIN_CLIN_ADDENDUM_SHEETS_C2.0A_L1A_L2A_A1.5A_A2.3A.pdf PDF
Amend_0004_-_Q&A.pdf PDF
Amend_0004_-_171023_MIIN_PMIS_159776_A71_REVISED.pdf PDF
Q&A_Amend_0003.pdf PDF
033016-GeoDesign_Report_Well.pdf PDF
SF30_Amd_000003.pdf PDF
Amend_0003_Statement_Of_Structural_Tests.pdf PDF
Amend_0003_Site_Visit_Sign_in_Sheet.pdf PDF
Amend_0002_-_Asbestos_Survey.pdf PDF
Sol_P17PS00522_Amd_000002.pdf PDF
Amend_0002_-_Geotechnical_Report.pdf PDF
B08_Solit_Att_01_Specs.pdf PDF
B08_Solit_Att_01_Drawings.pdf PDF
B08_Solit_Att_01_Engineering_Calcs.pdf PDF
Q_&_A_-_1st_Set.pdf PDF
SF30_-_Amend_0001_-_P17PS00522.pdf PDF
B08_Solit_Att_12_SBSubKCalc.xlsx XLSX spreadsheet
B08_Solit_Att_04_Equals.doc DOC document
B08_Solit_Att_05_Exp.docx DOCX document
B08_Solit_Att_01_Specs.pdf PDF
B08_Solit_Att_10_BidBond.pdf PDF
B08_Solit_Att_07_KeyPers.docx DOCX document
B08_Solit_Att_08_PastPerf.doc DOC document
B08_Solit_Att_02_Drawings.pdf PDF
B08_Solit_Att_03_WD.pdf PDF
B08_P17PS00522.pdf PDF
B08_Solit_Att_06_HazMat.doc DOC document
B08_Solit_Att_09_SubRef.doc DOC document
B08_Solit_Att_11_GenRefs.doc DOC document
B01_Synopsis_PreSolitNotice.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q3: Owners typically pay any plan check fees, and if a building permit is required, then we need to know.

CORRECTED Answer: As this is a federal building, city plan check/permit and inspection is not required. However, all work must comply with state and local regulations and requirements, and federal requirements (whichever are greater), per the project documents.

The National Park Service (NPS) will coordinate with the local Fire Department as a curtesy during construction. There will be no contractor coordination required.

Q4: Who is the AHJ (Authority Having Jurisdiction) for both permitting and for inspections?

CORRECTED Answer: The final AHJ is the NPS, as this is federal property, however as the project documents/specifications state, all local and state requirements and regulations for the work must be met.