CHESAPEAKE AND OHIO CANAL
Georgetown, Washington, D.C.
REHABILITATE LIFT LOCK #3 AND #4
CHOH
PMIS NO. 150696/150699
VOLUME 1 OF 3
PROJECT SPECIFICATIONS
Construction Documents
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
June 20, 2016
REHABILITATE LIFT LOCK #3 AND 4
CHOH-150696/150699 TOC-1
TABLE OF CONTENTS
VOLUME 1 OF 3 – REHABILITATE LIFT LOCK #3 AND #4
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work ................................................................ 01 11 00-1 to 01 11 00-4
01 26 01 Contract Modification Procedures ........................................ 01 26 01-1 to 01 26 01-6
01 27 00 Definition of Contract Line Items ........................................ 01 27 00-1 to 01 27 00-6
01 31 00 Project Management & Coordination................................. 01 31 00-1 to 01 31 00-10
01 32 16 Construction Schedule .......................................................... 01 32 16-1 to 01 32 16-9
01 32 33 Photo Documentation for Historic Preservation Projects .... 01 32 33-1 to 01 32 33-2
01 33 23 Submittal Procedures ............................................................ 01 33 23-1 to 01 33 23-8
01 35 13.22 Archeological Protection ............................................01 35 13.22-1 to 01 35 13.22-3
01 35 23 Safety Requirements ............................................................. 01 35 23-1 to 01 35 23-3
01 35 91 Historic Preservation Treatment Procedures ........................ 01 35 91-1 to 01 35 91-7
01 40 00 Quality Requirements ........................................................... 01 40 00-1 to 01 40 00-8
01 42 00 References ........................................................................... 01 42 00-1 to 01 42 00-19
01 50 00 Temporary Facilities and Controls ....................................... 01 50 00-1 to 01 50 00-6
01 57 19.12 Noise & Acoustic Management..................................01 57 19.12-1 to 01 57 19.12-2
01 57 23 Temporary Storm Water Pollution Prevention .................... 01 57 23-1 to 01 57 23-7
01 67 00 Product Requirements ........................................................... 01 67 00-1 to 01 67 00-9
01 73 29 Cutting and Patching ............................................................. 01 73 29-1 to 01 73 29-3
01 73 40 Execution ............................................................................... 01 73 40-1 to 01 73 40-6
01 74 19 Construction Waste Management and Disposal .................. 01 74 19-1 to 01 74 19-7
01 77 00 Closeout Procedures.............................................................. 01 77 00-1 to 01 77 00-4
Geotechnical Engineering Report - C&O Canal Lock #3 Renovations
Soils Management Plan
Work Plan
Sediment and Canal Surface Water Sampling Results Letter
VOLUME 2 OF 3 – CHOH 150696 - REHABILITATE LIFT LOCK #3
DIVISION 02 - EXISTING CONDITIONS
02 41 19 Selective Structure Demolition ............................................. 02 41 19-1 to 02 41 19-6
02 61 50 Management and Disposal of Excavated Non-Hazardous
Contaminated Soil and Wastewater ..................................... 02 61 50-1 to 02 61 50-9
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete ....................................................... 03 30 00-1 to 03 30 00-14
CHOH – 150696/150699 TOC-2
DIVISION 04 – MASONRY
04 03 05 Repointing of Existing Stone Masonry ................................ 04 03 05-1 to 04 03 05-3
04 03 07 Stone Masonry ...................................................................... 04 03 07-1 to 04 03 07-8
04 10 00 Mortar .................................................................................... 04 10 00-1 to 04 10 00-3
DIVISION 6 – WOOD, PLASTICS AND COMPOSITES
06 10 63 Exterior Rough Carpentry ..................................................... 06 10 63-1 to 06 10 63-3
06 19 00 Timber Miter Gates ............................................................... 06 19 00-1 to 06 19 00-4
DIVISION 9 – FINISHES
09 96 00 Painting .................................................................................. 09 96 00-1 to 09 96 00-7
DIVISION 31 - EARTHWORK
31 00 00 Earthwork and Grading ....................................................... 31 00 00-1 to 31 00 00-15
31 10 00 Site Clearing .......................................................................... 31 10 00-1 to 31 10 00-4
31 23 19 Dewatering ............................................................................ 31 23 19-1 to 31 23 19-3
31 23 23 Excavatable Flowable Fill .................................................... 31 23 23-1 to 31 23 23-5
31 50 00 Excavation Bracing ............................................................... 31 50 00-1 to 31 50 00-5
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 14 00 Unit Paving ............................................................................ 32 14 00-1 to 31 14 00-3
32 91 13 Soil Preparation .................................................................... 32 91 13-1 to 32 91 13-3
32 92 00 Turf and Grasses ................................................................... 32 92 00-1 to 32 92 00-8
32 93 00 Planting ................................................................................ 32 93 00-1 to 32 93 00-10
DIVISION 33 - UTILITIES
33 11 00 Water Distribution Systems .................................................. 33 11 00-1 to 33 11 00-6
33 45 00 Subsurface Drainage System ................................................ 33 45 00-1 to 33 45 00-4
VOLUME 3 OF 3 - CHOH 150699 - REHABILITATE LIFT LOCK #4
DIVISION 02 - EXISTING CONDITIONS
02 41 19 Selective Structure Demolition ............................................. 02 41 19-1 to 02 41 19-6
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete ....................................................... 03 30 00-1 to 03 30 00-14
DIVISION 04 – MASONRY
04 03 05 Repointing of Existing Stone Masonry ................................ 04 03 05-1 to 04 03 05-3
04 03 07 Stone Masonry ...................................................................... 04 03 07-1 to 04 03 07-8
04 10 00 Mortar .................................................................................... 04 10 00-1 to 04 10 00-3
CHOH – 150696/150699 TOC-3
DIVISION 6 – WOOD, PLASTICS AND COMPOSITES
06 19 00 Timber Miter Gates ............................................................... 06 19 00-1 to 06 19 00-4
DIVISION 9 – FINISHES
09 96 00 Painting .................................................................................. 09 96 00-1 to 09 96 00-7
DIVISION 31 - EARTHWORK
31 20 10 Erosion and Sediment Control ............................................. 31 20 10-1 to 31 20 10-5
31 23 23 Excavatable Flowable Fill .................................................... 31 23 23-1 to 31 23 23-5
CHOH – 150696/150699 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Contractor use of premises.
3. Public Use of Site
4. Work Restrictions.
5. Special Construction Requirements.
6. Soils Investigation Report.
7. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Chesapeake and Ohio National Historic Park, Georgetown Washington, D.C. Lock #3 and Lock 4 located between 30th Street, NW and 31st Street NW.
B. The Work consists of the following:
1. Rehabilitate Lift Lock #3
a. The Work includes all required labor, material and equipment for the cataloging existing canal stone and location, disassembly of the lock walls down to the foundation; building a new foundation; rebuilding the lock using original and supplemental stone; construction of new lock gates; and restoration of the surrounding plaza paving and landscaping.
2. Rehabilitate Lift Lock #4
a. The Work includes rehabilitation of the existing stone lock walls including but not limited to repair and replacement of mortar joints, reconstruction of a portion of the stone wall, dutchman repair of existing stones.
1) Bid Option A: Replacement of the existing upper and lower canal gates for
Lock #4.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to limits of disturbance indicated on the construction drawings.
CHOH – 150696/150699 01 11 00 - 2
B. Storage of Materials: Confine storage of materials to within the limits of disturbance indicated on the construction drawings. No soil shall be stored on site. All Excavated soil shall be hauled off site immediately.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.4 PUBLIC USE OF SITE
A. The area within the limits of construction will be closed to the public during construction.
Contractor to coordinate rerouting of pedestrians around construction site. Maintain access to existing buildings adjacent to area of work.
B. Existing streets, 30th Street NW and Thomas Jefferson Street NW, are open to traffic for the duration of construction. Contractor is responsible for any permits required for temporary shut of streets if required.
1.5 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
CHOH – 150696/150699 01 11 00 - 3
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer (CO). Submit requests 72 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 7 p.m., Monday through Friday, except when otherwise indicated.
1. Early Morning Hours: As allowed by jurisdiction. Contractor is responsible for obtaining required variances or permits.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than 7 days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: 11 pm to 6 am, alternate hours as coordinated with the CO.
D. Nonsmoking Site: Smoking is not permitted within Project Site or within 25 feet of entrances.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.8 SOILS INVESTIGATION REPORT
A. A soils investigation report entitled Geotechnical Engineering Report - C&O Canal Lock #3 Renovations Georgetown, Washington, DC (May 17, 2016) has been prepared by GeoCapital Engineering, LLC.
CHOH – 150696/150699 01 11 00 - 4
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.9 SOILS MANAGEMENT PLAN
A. Contaminated Soil Management Plan, C&O Canal Lock #3 Renovations, Georgetown, Washington, DC (GeoCapitol Engineering LLC, March 18, 2016).
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.10 WORK PLAN
A. Work Plan, C&O Canal Lock #3 Renovations, Georgetown, Washington, DC (GeoCapitol Engineering LLC, April 11, 2016).
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
1.11 SEDIMENT AND CANAL SURFACE WATER SAMPLING RESULTS
A. Sediment and Canal Surface Water Sampling Results Letter, C&O Canal Lock #3 Renovations, Georgetown, Washington, DC (GeoCapitol Engineering LLC, March 16, 2016).
B. A copy of the report is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
CHOH – 150696/150699 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
CHOH – 150696/150699 01 26 01 - 2
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
CHOH – 150696/150699 01 26 01 - 3
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct
CHOH – 150696/150699 01 26 01 - 4
received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
CHOH – 150696/150699 01 26 01 - 5
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead 10% Profit 10%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
CHOH – 150696/150699 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
CHOH – 150696/150699 01 27 00 - 1
050611 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS – CHOH-150696 - REHABILITATE LIFT LOCK #3
A. Contract Line Item No. 1 – Remove Trees
1. This item consists of furnishing all material and work necessary for the removal of existing trees indicated in the contract documents.
2. Measurement for payment will be the actual number of trees removed.
3. Payment will be made at the contract unit price (EA).
B. Contract Line Item No. 2 – Remove Hardscape (Benches, posts, etc)
1. This item consists of furnishing all material and work necessary for removal of existing site features including, benches, bollards, monuments and posts.
2. No measurement will be made on lump sum items.
3. Payment will made at the contract lump sum price (LS).
C. Contract Line Item No. 3 – Remove Existing Brick Pavers
1. This item consists of furnishing all material and work necessary for the removal of existing brick paved walkways.
2. Measurement for payment will be the actual number of area of brick pavers removed.
3. Payment will be made at the contract unit price (SY).
D. Contract Line Item No. 4 – Excavation
1. This item consists of furnishing all material and work necessary for the excavation and installation of suitable fill of the site as required to complete the work identified in the contract documents. All work associated with removal of groundwater is incidental to this item.
2. Measurement for payment will be the actual volume of materials removed.
3. Payment will be made at the contract unit price (CY).
E. Contract Line Item No. 5 – Contaminated Soil Replacement
1. This item consists of furnishing all material and work necessary for the replacement of contaminated soils as identified in the contract documents.
CHOH – 150696/150699 01 27 00 - 2
2. Measurement for payment will be the actual volume of materials removed and replaced.
3. Payment will be made at the contract unit price (CY).
F. Contract Line Item No. 6 – Temporary Excavation Bracing
1. This item consists of furnishing all material and work necessary for the installation and removal of temporary excavation bracing during construction.
2. No measurement will be made on lump sum items.
3. Payment will made at the contract lump sum price (LS).
G. Contract Line Item No. 7 – Replace Upper Lock Gate Complete
1. This item consists of removing the existing upper gates and miter sill and castings and hardware, and furnishing and installing new timber miter sill and lock gate and all castings and hardware, and testing the gate operation.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract lump sum price (LS).
H. Contract Line Item No. 8 – Replace Lower Lock Gate Complete
1. This item consists of removing the existing lower gates and miter sill and castings and hardware, and furnishing and installing new timber miter sill and lock gate and all castings and hardware, and testing the gate operation.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract lump sum price (LS).
I. Contract Line Item No. 9 – Remove Lock Wall Masonry
1. This item consists of all work necessary to document, dismantle, and store lock wall masonry that is to be reused and dispose of stones that will not be reused.
2. Measurement for payment will be the actual number of cubic yards of Masonry dismantled.
3. Payment will be made at the contract unit price (CY).
J. Contract Line Item No. 10 – Temporary Bracing of Jet Grout Columns
1. This item consists of all work necessary to brace the Jet Grout columns at the bridge that are exposed during the wall dismantling.
2. No measurement will be made on Lump Sum items.
3. Payment will be made at the contract lump sum price (LS).
K. Contract Line Item No. 11 – Monitoring of Existing Structures.
1. This work includes all work necessary to monitor the 30th Street Bridge and the Foundry
Building during construction.
2. No measurement will be made on Lump Sum items.
3. Payment will made at the contract Lump Sum price (LS).
L. Contract Line Item No. 12 – Remove Lock Timber Foundation
1. This item consists of all work necessary to remove and dispose of the lock timber foundation including timber beams and planking.
2. Measurement for payment will be the actual number of square feet of timber foundation removed.
3. Payment will be made at the contract unit price (SF).
M. Contract Line Item No. 13 – Lock Concrete Foundation
CHOH – 150696/150699 01 27 00 - 3
1. This item consists of all work associated with placing the new lock concrete foundation, concrete footings under reconstructed walls, and the concrete slab on grade at the base of the upper gate. Lean concrete under footings and repair of concrete patches on existing stone masonry retaining walls are incidental to this item.
2. Measurement for payment will be the actual cubic yards of concrete placed.
3. Payment will be made at the contract unit price (CY).
N. Contract Line Item No. 14 – New Ashlar Stone
1. This item consists of furnishing new ashlar stone for the reconstruction of the lock face stones.
2. Measurement for payment will be the actual cubic yards of new ashlar stone placed in the wall. There will be no payment made for stone material delivered to the site but not used in the wall construction.
3. Payment will be made at the contract unit price (CY).
O. Contract Line Item No. 15 – New Rubble Stone
1. This item consists of furnishing new rubble stone for the reconstruction of the lock face stones.
2. Measurement for payment will be the actual cubic yards of new rubble stone placed in the wall. There will be no payment made for stone material delivered to the site but not used in the wall construction.
3. Payment will be made at the contract unit price (CY).
P. Contract Line Item No. 16 – Dutchman Repair of Ashlar Stone
1. This item consists of all work associated with installing a Dutchman repair of an existing
Ashlar stone that are designated by the CO.
2. Measurement will be made per repair.
3. Payment will be made at the contract unit price per item (EA).
Q. Contract Line Item No. 17 – Stone Restoration Mortar Repair
1. This item consists of all work necessary repair damaged ashlar stones designated for repair by the CO.
2. Measurement will be made for payment for each repair.
3. Payment will be made at the contract unit price for each (CF).
R. Contract Line Item No. 18 – Reconstruct Lock Wall Masonry Backing
1. This item consists of reconstructing the lock wall rubble stone backing using the original backing stones and where necessary new rubble stones. All work associated with installing rubble stone masonry on top of the lock wall under the gutter is incidental to this item.
2. Measurement will be made for the actual cubic yards of Rubble Stone Backing placed in the wall
3. Payment will be made at contract unit price per cubic yard (CY).
S. Contract Line Item No. 19 – Reconstruct Lock Wall Ashlar Face Stone
1. This item consists all work necessary to reconstruct the lock wall ashlar face stones.
2. Measurement for payment will be the actual cubic yards of stone installed in the wall.
3. Payment will be made at the contract unit price (CY).
T. Contract Line Item No. 20 – Lock Repointing
CHOH – 150696/150699 01 27 00 - 4
1. This item consists of repointing deteriorated mortar joints on the face of the lock walls.
2. Measurement for payment will be the actual number of lineal feet of joint.
3. Payment will be made at the contract unit price (LF).
U. Contract Line Item No. 21 – Lock Foundation Repair
1. This item consists of installing dry pack non shrink grout between remaining foundation timbers at the east end of the lock.
2. Measurement for payment will be the actual number of cubic feet of non-shrink grout installed.
3. Payment will be made at the contract unit price (CF).
V. Contract Line Item No. 22 – Gutter
1. This item consists of installing concrete pavers to form a gutter underneath the four edges of the bridge and crushed stone between the pavers.
2. No measurement for payment will be for Lump Sum Items
3. Payment will made at the contract Lump Sum price (LS).
W. .Contract Line Item No. 23 – Brick Pavers
1. This item consists of furnishing all material and work necessary for the installation and of new brick pavers, below grade utilities, and CCTV inspection of existing storm sewer line as indicated in the contract documents.
2. Measurement for payment will be the actual number of square yards of pavers installed.
3. Payment will be made at the contract unit price (SY).
X. Contract Line Item No. 24 - Tree Boxes
1. This item consists of furnishing all material and work necessary for the installation of new tree boxes.
2. Measurement for payment will be the actual number of tree boxes installed.
3. Payment will be made at the contract unit price (EA).
Y. Contract Line Item No. 25 – Trees
1. This item consists of furnishing all material and work necessary for the installation of new trees.
2. Measurement for payment will be the actual number of trees installed.
3. Payment will be made at the contract unit price (EA).
Z. Contract Line Item No. 26 – Repair and Install Hardscape
1. This item consists of furnishing all material and work necessary for the repair and reinstallation existing site features including, lights, benches, bollards, monuments and posts.
2. No measurement will be made on lump sum items.
3. Payment will made at the contract lump sum price (LS).
3.2 LIST OF CONTRACT LINE ITEMS - CHOH-150699 – REHABILITATE LIFT LOCK #4
A. Contract Line Item No. 27 - Staging Area
1. This item consists of all labor, equipment and material required for the installation of the project staging area, and removal of the staging area and restoration to original conditions.
2. Measurement for payment will be on lump sum items.
CHOH – 150696/150699 01 27 00 - 5
3. Payment will be made at the contract unit price (LS).
B. Contract Line Item No. 28 – Partial Repair of Southwest Corner of Canal Wall
1. This item consists of all work associated with documenting and removing damaged stone masonry, removing tree roots and rebuilding the upper corner of the canal wall.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract unit price per item (LS).
C. Contract Line Item No. 29 – Dutchman Repair of Ashlar Stone
1. This item consists of all work associated with installing a Dutchman repair of an existing
Ashlar stone that are designated by the CO.
2. Measurement will be made per cubic foot of repair.
3. Payment will be made at the contract unit price per cubic foot (CF).
D. Contract Line Item No. 30 – Stone Restoration Mortar Repair
1. This item consists of all work necessary repair damaged ashlar stones designated for repair by the CO.
2. Measurement will be made for payment for each cubic foot of repair.
3. Payment will be made at the contract unit price per cubic foot (CF).
E. Contract Line Item No. 31 – Repointing Rubble Stone
1. This item consists of repointing deteriorated rubble stone masonry mortar joints on the face of the lock walls.
2. Measurement for payment will be the actual number of lineal feet of joint.
3. Payment will be made at the contract unit price (LF).
F. Contract Line Item No. 32 – Repointing Ashlar Stone
1. This item consists of repointing deteriorated ashlar stone mortar joints on the face of the lock walls.
2. Measurement for payment will be the actual number of lineal feet of joint.
3. Payment will be made at the contract unit price (LF).
G. Contract Line Item No. 33 – Breast Wall Backside Parge Repair
1. This item consist of all work associated with installing parging on the back side of the breast wall including temporary excavation and backfill.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract unit price per item (LS).
H. Contract Line Item No. 34 –Fill Culverts with Flowable Fill
1. This item consists of all work associated with filling the culverts with excavatable flowable fill including plugging the culverts and coring the opening.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract unit price per item (CF).
I. Contract Line Item No. 35 – Lock Foundation Undermining Repair
1. This item consists of all work associated with installing dry pack non shrink grout between the natural rock surface and the underside of the lock walls.
2. Measurement for payment will be the actual number of cubic feet of non-shrink grout installed.
3. Payment will be made at the contract unit price (CF).
CHOH – 150696/150699 01 27 00 - 6
J. Contract Line Item No. 36 – Repair Lock Wall Concrete Patches
1. This item consists of all work associated with sounding existing concrete patches and repairing loose concrete with new concrete patching material up to 6” thick.
2. Measurement for payment will be the actual number of square feet of concrete repair installed.
3. Payment will be made at the contract unit price (CF).
K. Contract Line Item No. 37 – Gutters
1. This item consists of all work involved in installing concrete pavers to form a gutter underneath the four edges of the bridge including building up a short rubble stone wall under the paver and installing crushed stone between the pavers under the bridge.
2. No measurement for payment will be for Lump Sum Items
3. Payment will made at the contract Lump Sum price (LS).
L. Contract Line Item No. 38 –Option A - Replace Upper Lock Gate Complete
1. This item consists of removing the existing upper gates and miter sill and castings and hardware, and furnishing and installing new timber miter sill and lock gate and all castings and hardware, and testing the gate operation.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract lump sum price (LS).
M. Contract Line Item No. 39 – Option A - Replace Lower Lock Gate Complete
1. This item consists of removing the existing lower gates and miter sill and castings and hardware, and furnishing and installing new timber miter sill and lock gate and all castings and hardware, and testing the gate operation.
2. No measurement will be made on lump sum items.
3. Payment will be made at the contract lump sum price (LS).
END OF SECTION 01 27 00
CHOH - 150696 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination.
3. Submittals
4. Coordination Drawings.
5. Requests for Information (RFIs).
6. NPS/DSC SharePoint Project Website.
7. Project meetings.
8. Environmental Coordination.
9. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 DEFINITIONS
A. Agency with Jurisdiction B. Construction Permits – Contractor Provided C. Government Furnished Permits
1.3 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
http://www.nps.gov/dscw/definitionsdc_a.htm#awj http://www.nps.gov/dscw/definitionsdc_c.htm#cpcp http://www.nps.gov/dscw/definitionsdc_g.htm#gfperm
CHOH - 150696 01 31 00 - 2
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.4 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).
CHOH - 150696 01 31 00 - 3
3. Number of Copies: Submit six opaque copies of each submittal. Contracting Officer will return two.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those Section
B. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Traffic Management Plan
9. Temporary Staging Area Layout Plan
10. Waste Management Plan.
11. Quality Control Plan.
12. Erosion and Sediment Control Plan
13. Historic Preservation Treatment Plan.
14. List of Required Construction Permits. Refer to paragraph 1.9 and include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
C. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued.
1.5 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
CHOH - 150696 01 31 00 - 4
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Existing site condition.
6. Drawing number and detail references, as appropriate.
7. Field dimensions and conditions, as appropriate.
8. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
9. Contractor's signature.
10. Requested date for response.
11. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of…