Construction Services: Construct Law Enforcement Facility, Hains Point, Washington D. C. NPS PMIS # NCRO-201541 Federal contract opportunity
Solicitation number
P16PS01045
Issued by
Department of the Interior National Park Service National Office

About this file

Contains signed form SF-30 Amendment of Solicitation/Modification of Contract and government responses to questions provided at the presolicitation meeting held on July 21 2016.

View the file

Other files for this federal contract opportunity

Other files attached to Construction Services: Construct Law Enforcement Facility, Hains Point, Washington D. C. NPS PMIS # NCRO-201541, newest first.
File Type Posted
P16PS01045-000007_Amendment_complete.pdf PDF
DVB_Gen_Decision_No_DC2_Bldg_08-05-2016.pdf PDF
DVB_Gen_Decision_No_DC1_HC_08-05-2016.pdf PDF
P16PS01045-000006_Amendment_signed.pdf PDF
P16PS01045-000006_Q A_w-attach.pdf PDF
P16PS01045-000005_Amendment_complete.pdf PDF
P16PS01045-000004_Amendment_Complete.pdf PDF
P16PS01045-000002_Att2a__DVB_Gen_Decision_No_DC1_HC_07-22-2016.pdf PDF
P16PS01045-000002_Att2b_DVB_Gen_Decision_No_DC2_Bldg_07-22-2016.pdf PDF
P16PS01045-000002_Att1a_Preproposal_Slide_Show_NCRO_201541.pdf PDF
P16PS01045-000002_Att1b_NCRO_201541_attendees_sign_in_7.21.16.pdf PDF
P16PS01045-000002_Amendment.pdf PDF
B02_P16PS01045-000001_Amendment.pdf PDF
101_P16PS01045_Experience form 6.8.16.docx DOCX document
104_P16PS01045_Past Performance Questionnaire_6.8.16.docx DOCX document
201_SF 24 Bid Bond.pdf PDF
02_P16PS01045_SF-1442_Constr_Clauses-Provisions.pdf PDF
100_P16PS01045_SoliCover Sheet-Tech Proposal.pdf PDF
202_P16PS01045_SF 1442_Solicitation_07-14-2016.pdf PDF
Att_3b_DVB_Gen_Decision_No_DC2_Bldg_07-08-2016.pdf PDF
204_P16PS01045_Reps Certs.pdf PDF
Att_2b_NCRO_201541_100__Final_Drawings_Sheets_041to100_of_215_no_Sheet_055.pdf PDF
Att_2c_NCRO_201541_100__Final_Drawings_Sheets_101to160_of_215.pdf PDF
205_P16PS01045_Subcontracting Plan_6.8.16.doc DOC document
Att_3a_DVB_Gen_Decision_No_DC1_HC_07-08-2016.pdf PDF
00_P16PS01045__NCRO 201541 Proposal Submission Pkg.pdf PDF
Att_2a_NCRO_201541_100__Final_Drawings_Sheets_001to040_of_215_no_Sheet_027or039.pdf PDF
102_Subcontractor Form.doc DOC document
206_P16PS01045_GeneralReferences.docx DOCX document
Att_2d_NCRO_201541_100__Final_Drawings_Sheets_161to215_of_215.pdf PDF
203_Contract Price Schedule.XLS XLS spreadsheet
Att_1b_NCRO_201541_100__Final_Specifications_Volume_2.pdf PDF
200_P16PS01045_Sol Cover Sheet-Bus Proposal.pdf PDF
103_P16PS01045_Key Personnel Form.docx DOCX document
203_P16PS01045_Contract Price Schedule.pdf PDF
Att_1a_NCRO_201541_100__Final_Specifications_Volume_1.pdf PDF
208_P16PS01045_ProposedEquals.docx DOCX document
207_P16PS01045_HazmatForm.docx DOCX document
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NCRO-201541 – NPS Solicitation P16PS01045 Amendment No. 3 – 07/26/2016

QUESTIONS AND ANSWERS - #1 through #4

Please find the following government responses to Questions #01 through #04, which were submitted at the preproposal conference held on July 21, 2016:

1. What are you looking for in key subcontractors? Is there a difference between major subcontractors and key subcontractors?

There is no difference. We are looking for any subcontractors who will be constructing key components in this project to submit past performance and demonstrate their capabilities and technical skills.

2. Are there restrictions for distribution of the specifications and drawings to subcontractors?

No. The prime contractor can provide these documents to their subcontractors or the subcontractors can contact Al O’Mara, contracting officer, or Alan Stormont, contract specialist, for the access code to open downloaded files from FBO.

3. If we missed the preproposal site visit, can we have a tour of the site?

The site is open to the public and you may visit on your own. There will not be any further tours.

None of the contractors were permitted inside of the NCR annex buildings; therefore, it is an outside view of the buildings, adjacent parking, existing vegetation, etc.

4. Please clarify what has already been completed regarding permitting for the stormwater and sediment control? Slide 30 on the preproposal presentation.

The civil engineer has submitted the stormwater and sediment control to DOEE, and the final submission is under review. The fees have been paid for this submission. The contractor will need to pick up on any further construction related permits required.