GATE_201049B_Project_Scope.pdf

PDF 1 MB Posted

Attached to
GATE - Repair Park Telecommunications Federal contract opportunity
Solicitation number
p15ps00589
Issued by
Department of the Interior National Park Service National Office

About this file

Project Scope

View the file

Other files for this federal contract opportunity

Other files attached to GATE - Repair Park Telecommunications, newest first.
File Type Posted
SF-30_Amend_3.pdf PDF
QandA_Amend_3.pdf PDF
Amend_0002_SF-30_P15PS00589.pdf PDF
Amendment_0002_Pre-proposal_mtg_notes.pdf PDF
Amendment_0002_Description_of_Changes.pdf PDF
1_-_Amendment_000001_P15PS00589 _SF-30.pdf PDF
2_-_Amendment_000001_P15PS00589 _Attachment_1 _revised_1040.docx DOCX document
3_-_Amendment_000001_P15PS00589 _Preproposal_Site_Visit_Attendees.pdf PDF
5_-_Wage_Determination _NY3.txt TXT text file
2_-_SF-1442.pdf PDF
GATE_201049B_Drawings_Sheets_1-25.pdf PDF
7_-_Contract_Price_Schedule_-_Blank.xlsx XLSX spreadsheet
3_-_Clauses_ _Provisions.docx DOCX document
4_-_Proposal_Submission_Package.docx DOCX document
GATE_201049B_Reference_Drawings.pdf PDF
1_-_RFP_Cover_Letter.doc DOC document
GATE_201049B_Drawings_Sheets_26-28.pdf PDF
GATE_201049B_Drawings_Sheets_35-39.pdf PDF
GATE_201049B_Drawings_Sheets_32-34.pdf PDF
5_-_Wage_Determination _NJ58.txt TXT text file
6_-_Map _Preproposal_Site_Visit_Location.pdf PDF
GATE_201049B_Drawings_Sheets_29-31.pdf PDF
Presolicitation_Notice _Revised_6-29-15.doc DOC document
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GATEWAY NATIONAL RECREATION AREA

SANDY HOOK, NJ

SOLICITATION 1443N

REPAIR PARK TELECOMMUNICATIONS DAMAGED BY

HURRICANE SANDY

GATE-201049B

FINAL PROJECT SCOPE

NATIONAL PARK SERVICE

DENVER SERVICE CENTER

June 12, 2015

This page intentionally left blank

Table of Contents

1.0 PROJECT INTRODUCTION

1.1 SCOPE

1.2 NPS/DSC SHAREPOINT PROJECT WEBSITE

1.3 LOCATION

1.4 BACKGROUND

1.5 DESCRIPTION

1.6 SCHEDULE

1.7 INFORMATION

1.8 DATA AND MATERIALS TO BE PROVIDED BY THE NPS

2.0 PROJECT REQUIREMENTS

2.1 GENERAL REQUIREMENTS

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

2.1.2 DEFINITION OF CONTRACT LINE ITEMS

2.1.3 PROGRESS PAYMENTS

2.1.4 PROJECT MEETINGS

2.1.5 PROJECT SCHEDULE

2.2 DESIGN REQUIREMENTS

2.2.1 DB CONSTRUCTION DOCUMENTS

2.2.2 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS FOR

DESIGN

2.3 CONSTRUCTION REQUIREMENTS

2.3.1 ENVIRONMENTAL AND SUSTAINABILITY REQUIREMENTS

2.3.2 SCHEDULE OF VALUES

2.3.3 CONSTRUCTION SUPPORT

2.3.4 SUBMITTALS DURING CONSTRUCTION

2.3.5 CONSTRUCTION COORDINATION

2.3.6 DIGITAL IMAGES

2.3.7 QUALITY CONTROL

2.3.8 WORKING HOUR RESTRICTIONS

2.3.9 TEMPORARY SERVICES

2.3.10 ACCESS

2.3.11 PRESERVATION OF ADJACENT FEATURES

2.3.12 EXISTING UTILITIES

2.3.13 HAULING RESTRICTIONS

2.3.14 ACCIDENT PREVENTION

2.3.15 TEMPORARY CONTROLS

2.3.16 FIELD ENGINEERING

2.3.17 PROJECT CLOSE-OUT

2.3.18 SUBSTANTIAL COMPLETION AND FINAL INSPECTION

2.4 FORMS

2.5 SUBMITTAL LIST

3.0 PERFORMANCE REQUIREMENTS

3.1 DESIGN IMPERATIVES

3.2 SUSTAINABILITY

3.4 FACILITY PERFORMANCE

3.5 ELEMENTS AND PRODUCTS

4.0 TECHNICAL REQUIREMENTS

G10 – SITE PREPARATION

G40 – SITE ELECTRICAL UTILITIES

Z10 – GENERAL PERFORMANCE TECHNICAL SPECIFICATION

Z20 – ARCHEOLOGICAL PROTECTION

Z30 – STORM WATER POLLUTION PREVENTION

5.0 ATTACHMENTS

DRAWINGS AND GOVERNMENT-FURNISHED DRAWINGS (REFERENCE ONLY)

1.0 PROJECT INTRODUCTION

Park Alpha and PMIS Number: GATE-201049B

Project Title: Repair Park Telecommunications Damaged By Hurricane Sandy

Project Drawing Number: 646/120197

1.1 Scope

In accordance with the terms and conditions of the Contract, the Contractor shall perform the work of this Request for Proposal (RFP) for the National Park Service (NPS) as described below.

The project consists of the design and construction of a new telecommunication conduit ductbanks, infrastructure, and new fiber optic cabling from the existing Sandy Hook Unit demarcation location in the historic Building 26 at Fort Hancock to 39 facilities throughout Fort Hancock and the Sandy Hook Unit. The project also consists of the design and construction of new fiber optic cabling from the Fee Building (Building 606) to the Verizon Demarc Room in the Bath House at Jacob Riis Park and from the Verizon Demarc Manhole to various facilities throughout Great Kills Park. Two facilities are connected at Jacob Riis Park, and five facilities are connected at Great Kills Park.

This project will be the second of two telecommunication projects at Sandy Hook. The first project involved connecting the Verizon microwave tower building located on the Coast Guard property to the existing Sandy Hook Unit demarcation location in the historic Building 26 at Fort Hancock.

Work includes 4” and/or 1-1/4” conduits in single conduit and ductbank configurations, direct buried and/or directionally bored, with inner ducts in 4” conduits; trench/ backfill and bedding, and ground restoration; single mode, outdoor, loose tube dry filled fiber optic cables that conform to ITU-T G.652.D; fiber optic cable terminations; and new networking racks, telecommunications infrastructure, and termination equipment. Conduit sizes may be 4” and/or 1-1/4” and may be direct buried and/or directionally bored throughout Sandy Hook Unit to allow the Contractor flexibility of installation based on the chosen means and methods.

The work of this RFP shall be performed in accordance with the Denver Service Center (DSC) Workflows website, http://www.nps.gov/dscw.htm.

Listed on the DB homepage are links to the design phases which describe the required workflow process from Predesign through Construction Documents. Each design phase webpage contains hypertext links to definitions, forms, templates, samples and guidelines.

http://www.nps.gov/dscw.htm

In addition, there is an “Information” section (http://www.nps.gov/dscw/information.htm) which provides design requirements and criteria that shall be used for completing the work of this contract. The “Information” section provides links to the following:

• Definitions (http://www.nps.gov/dscw/definitions.htm): A list of terms relevant to design and construction in national parks.

• Design Deliverables – Content and Format Requirements (DB)

(http://www.nps.gov/dscw/del_designbuild.htm):

o Design phase submission requirements for:

Technical content Submission format (hard-copy and electronic)

• Design Standards (http://www.nps.gov/dscw/dstandards.htm): Design Standards arranged by discipline and/or specialty.

• Forms/Templates/Samples/Guidelines (http://www.nps.gov/dscw/publicforms.htm): A listing of forms/templates/samples/guidelines used for a typical project.

• Laws/Regulations/Policies/Guidance (http://www.nps.gov/dscw/laws-policies.htm): A listing of sources for retrieving laws/regulations/policies/guidance applicable to NPS projects.

In case of conflict between this RFP and the DSC DB Workflows website, http://www.nps.gov/dscw/designbuild.htm, this RFP will take precedence over and will be used in lieu of such conflicting portions.

The Contractor remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website, http://www.nps.gov/dscw/designbuild.htm, have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO) requesting direction.

1.2 NPS/DSC SharePoint Project Website

Use the NPS/DSC SharePoint Project website for purposes of hosting and managing project communication and documentation until Final Completion. The NPS/DSC SharePoint Project website will be used for the following functions:

• Project directory

• Project correspondence

• Meeting agendas and minutes

• Contract modifications documentation and logs

• RFI form and processing

• Task and issue management

• Photo documentation

• Baseline schedule, schedule updates and calendar management

• Submittal form and processing

• Drawing and specification document hosting, viewing, and updating

• Online document collaboration http://www.nps.gov/dscw/information.htm http://www.nps.gov/dscw/definitions.htm http://www.nps.gov/dscw/del_designbuild.htm http://www.nps.gov/dscw/dstandards.htm http://www.nps.gov/dscw/publicforms.htm http://www.nps.gov/dscw/laws-policies.htm http://www.nps.gov/dscw/designbuild.htm http://www.nps.gov/dscw/designbuild.htm

• Reminder and tracking functions

• Archiving functions

• Notification of submittal and RFI statuses and current responsible party

Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the project website. For login procedures and other SharePoint information, refer to the DSC Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.

All users will be required to have Internet Explorer version 7 or later and Adobe Acrobat Pro version 9 or later

1.3 Location

This project contains three work sites. These work sites are located in the Sandy Hook Unit at Gateway National Recreation Area in the State of New Jersey, at Great Kills Park at Gateway National Recreation Area in the State of New York, and at Jacob Riis Park at Gateway National Recreation Area in the State of New York.

1.4 Background

This is a utility restoration project to repair Hurricane Sandy damage to telecommunications infrastructure located within Sandy Hook Unit, Great Kills Park, and Jacob Riis Park. The existing system was damaged and has deteriorated to the point where major replacement of the equipment is required. This includes both the conduit infrastructure and cable at portions of Sandy Hook Unit and cable only at Great Kills Park, Jacob Riis Park, and portions of Sandy Hook Unit. The project will also improve connectivity capabilities throughout the Sandy Hook Unit.

1.5 Description

The telecommunications infrastructure shall consist of new conduit and handholes. New loose tube dry filled fiber optic cables shall be provided and terminated at each building within the scope of the project. New conduit infrastructure and fiber optic cables will be required throughout the Sandy Hook Unit, while new fiber optic cables will be installed in existing conduit at Great Kills Park and Jacob Riis Park.

1.6 Schedule

The work in this RFP shall be completed in accordance with the following schedule:

100% Draft DB Construction Documents:

100% Draft DB Construction Documents submitted no later than 30 calendar days after award.

http://www.nps.gov/dscw/precon_spproj.htm

NPS Review completed no later than 15 calendar days after submission of 100% Draft DB Construction Documents.

100% Complete DB Construction Documents:

100% Complete DB Construction Documents and written responses to the NPS 100% Draft DB Construction Documents Review Comments submitted no later than 14 calendar days after receipt of NPS 100% Draft DB Construction Documents review comments.

NPS Review completed no later than 7 calendar days after receipt of 100% Complete DB Construction Documents.

Complete Stamped and Signed DB Construction Documents:

Complete Stamped and Signed DB Construction Documents and written responses to the NPS 100% Complete DB Construction Document review comments submitted no later than 14 calendar days after receipt of NPS 100% Complete DB Construction Document review comments.

Construction:

Construction completed no later than 450 calendar days after award of the contract.

Construction shall not begin until the Contracting Officer has issued the DB Start Work Notice.

As-Constructed Drawings:

As-Constructed Drawings completed no later than 21 calendar days after Substantial Completion.

All DB Construction Documents and As-Constructed Drawings shall be submitted to the NPS Project Manager.

1.7 Information

NPS Points of Contact:

Contractual:

Contracting Officer (CO): Tom Locke, 303-969-2059, Tom_Locke@nps.gov.

Contract Specialist (CS): Joy Ewalt, 303-969-2394, Joy_Ewalt@nps.gov.

Technical:

Project Manager (PM) and Alternate Contracting Officer’s Representative (ACOR): Rick S. Rampi, 303-969-2554, Rick_Rampi@nps.gov.

mailto:Tom_Locke@nps.gov mailto:Joy_Ewalt@nps.gov mailto:Rick_Rampi@nps.gov

Project Specialist (PS) and Contracting Officer’s Representative (COR): Ken Fischer, 303- 969-2453, Kenneth_Fischer@nps.gov.

Address:

National Park Service – Denver Service Center 12795 West Alameda Parkway P.O. Box 25287 Denver, CO 80225

1.8 Data and Materials to be provided by the NPS (Government-Furnished)

The following data and materials will be provided to the Contractor and are included in Section 5 of this RFP:

• Project Drawings

• Existing Drawings, where available (Government-Furnished Information Only)

• Existing Site Map and Underground Utilities, where available (Government-Furnished

Information Only)

• NPS Project Sustainability Checklist (will be provided in electronic format for editing purposes) mailto:Kenneth_Fischer@nps.gov

This page intentionally left blank

2.0 PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 SCOPE OF WORK AND PROJECT SUMMARY/REQUIREMENTS

The project contains work at three locations. The project will consist of the design and construction of a new telecommunications ductbank, fiber optic cables, and associated infrastructure to support new fiber optic cabling throughout the Sandy Hook Unit. The project will also include design and construction of fiber optic cables and associated connecting and termination infrastructure in existing ductbank at Jacob Riis Park and Great Kills Park. Refer to Part 4 for further detailed information.

Coordination:

The Contractor shall be responsible for coordinating the entire project scope including but not limited to site routing, building penetrations, final termination requirements, and locations. Termination enclosures and networking racks shall be designed to be mounted above the appropriate FEMA flood levels. Due to the historical nature and extensive natural resources located in the project area, the Contractor shall make routing revisions as necessary based upon field conditions and coordinate the exact routing and construction schedule with the National Park Service during design.

Unexploded Ordnances:

In the event unexploded ordnances are uncovered at Sandy Hook Unit, the Contractor shall immediately stop work and call 732-872-5900. Unexploded ordnance (UXO) survey shall be performed in areas outside of Fort Hancock (see drawings E.204 through E.213/E.304 through E.313). NPS shall provide a UXO monitor for excavation areas within Fort Hancock (see drawings E.201 through E.203/E.301 through E.303).

Permitting:

The Contractor shall be responsible for any permits required for the construction of the new telecommunications ductbank, fiber optic cables, and associated infrastructure.

Site Survey and Existing Site Utilities:

The Contractor shall be responsible for surveying the extent of the project site work. The survey information provided in this RFP may be out of date and may not reflect actual field conditions. It shall be the responsibility of the Contractor to verify utility information through surveys during design. In no event shall the Government be responsible for damages or time extensions due to lack of site information. The E300 series drawings are identical to the E200 series drawings except for the addition of an aerial image to show as much of the existing conditions as available in lieu of a complete topographic survey.

Roadway Repairs:

The approved conduit/ductbank routing includes routing under existing roadways. The Contractor shall be responsible for determining the best means and methods of installation. The Contractor shall be responsible to repairing the roads to the original or better condition.

Ductbanks and Configurations:

In general, provide new telecommunications ductbanks routing approximately as shown on the drawings. At Sandy Hook Unit, ductbanks shall consist of nonmetallic conduits installed a minimum of 36” from finished grade to the top of the uppermost conduit.

Each ductbank at Sandy Hook Unit shall have a minimum of (2) 4 inch conduits or (6) 1¼ inch conduits. Ductbank configurations and installation methods may consist of (2) 4 inch conduits installed via trenching, (2) 4 inch conduits installed via directional boring, and/or (6) 1¼ inch conduits installed via directional boring throughout Sandy Hook Unit.

One 4 inch conduit or three 1¼ inch conduits shall be dedicated exclusively to NPS IT.

One 4 inch conduit or three 1¼ inch conduits shall be dedicated to third party service providers. Provide three (3) 1 ¼ inch, corrugated plastic innerducts in all 4 inch conduits.

In a few cases, a single conduit is required to service buildings and is dedicated exclusively to NPS IT. For locations and quantities of conduits for each ductbank section, see drawings G.002 and E.201 through E.213.

No new ductbanks are anticipated at Great Kills Park and Jacob Riis Park; all new fiber optic cables and copper cables will be routed through existing infrastructure.

Handholes:

New handholes are required at approximate locations indicated on the RFP drawings.

Handhole shall be a minimum of 4 feet by 4 feet by 4 feet deep. All handholes and lids shall be at a minimum H-20 rated.

Building Penetrations:

As part of this contract, the Contractor shall penetrate the existing building foundation walls with the conduit quantity as indicated on the drawings. Buildings penetrated at Sandy Hook Unit are shown on the drawings. Building penetrations shall be made a minimum of 36 inches underground unless otherwise noted on the drawings.

Building penetrations at Sandy Hook Unit are made within the following Contract Line Items:

Building Penetrated Contract Line Item Number Base Bid / Option 1 4 Base Bid 18 4 Base Bid 20 4 Base Bid 22 4 Base Bid 26 4 Base Bid 28 4 Base Bid 29 4 Base Bid 30 4 Base Bid 32 4 Base Bid 34 4 Base Bid 35 4 Base Bid 41 4 Base Bid 47 4 Base Bid 51 4 Base Bid 53 4 Base Bid 58 4 Base Bid 64 4 Base Bid 66 4 Base Bid 67 4 Base Bid 71 4 Base Bid 72 4 Base Bid 73 4 Base Bid 75 4 Base Bid 84 4 Base Bid 102 4 Base Bid 311 4 Base Bid 335 4 Base Bid 338 4 Base Bid 340 4 Base Bid 341 4 Base Bid 436 4 Base Bid

438 4 Base Bid 17 Option G

Beach Center B Pavilion 15 Option E Beach Center C Pavilion 14 Option D Beach Center D Pavilion 13 Option C Beach Center E Pavilion 12 Option B Fee Collection Building 4 Base Bid Gunnison Beach Center Pavilion 11 Option A Lifeguard Station 4 Base Bid Water Boost Station 4 Base Bid

No new building penetrations are anticipated at Great Kills Park and Jacob Riis Park; all new fiber optic cables and copper cables will be routed through existing infrastructure.

Fiber Optic Cabling and Terminations:

Provide single mode, outdoor, loose tube dry filled fiber optic cables that conform to ITU-T G.652.D as shown on the drawings unless otherwise noted on the drawings.

Terminate the fiber on newly provided enclosures/networking racks. Provide necessary mounting apparatus. Termination enclosures and networking racks shall be designed to be located and installed above the required FEMA flood levels.

Limits of Construction and Disturbance:

The Contractor shall be limited to a ductbank routing variance within the limits of the SHPO approved area of disturbance. If a larger variance from the ductbank routing shown on the plans is desired, the Contractor shall coordinate with NPS prior to any construction.

The project will include, but not be limited to, the following:

• Review the RFP document and drawing package.

• Review site data.

• Provide survey.

• Upon award, determine and provide design schedule of work.

• Submit list of required permits.

• Design site, site utilities, building, and foundation system.

• Submit DB Construction Documents for review and approval, as required.

• Provide schedule of construction work.

• Secure work area and provide for continued access to the facility.

• Construct project

• Create and provide operations and maintenance manual.

• Provide as-constructed drawings.

2.1.2 Definition of Contract Line Items

The intent of this section is to explain, in general, what is included in each contract line item, limits or cut-off points where one item ends and another begins. If no item exists for a portion of the work, include the costs in a related line item.

CONTRACT LINE ITEM NO. 1 – DESIGN:

This item consists of performing all upfront work to design and final layout of Contract Line Items 2 through 23. The design shall include the final recommendations for the installation of new direct buried ductbanks; installation of new handholes; penetration of existing buildings, existing manholes, existing handholes, and new handholes; installation of new fiber optic cables; and all supporting work required to create a complete design.

CONTRACT LINE ITEM NO. 2 – FURNISH AND INSTALL TELECOMMUNICATIONS

INFRASTRUCTURE AT JACOB RIIS PARK:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables and copper cables between the Fee Building (Building 606) and Bath House; installation of conduit between the Verizon Demarc and the NPS termination within the Bath House; installation of termination enclosures as noted on the drawings in the Fee Building (Building 606) and Bath House; the termination of all new fiber optic cables and copper cables; all connectors; all supports; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings. Copper cables shall have the quantity of pairs/conductors as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 3 – FURNISH AND INSTALL TELECOMMUNICATIONS

INFRASTRUCTURE AT GREAT KILLS PARK:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between the Ranger Station and the Verizon Demarc Manhole M.H.1, USPP, Education Center, Beach Center, and Marina;

installation of termination enclosures as noted on the drawings in the Ranger Station, Verizon Demarc Manhole M.H.1, USPP, Education Center, Beach Center, and Marina; the termination of all new fiber optic cables; all connectors; all supports; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 4 – FURNISH AND INSTALL DUCTBANK AT SANDY

HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the construction of the ductbanks throughout the area of work not specifically covered in another Contract Line Item; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; all handholes; and all required building, manhole, and handhole penetrations. The ductbanks configurations are as shown on the drawings.

CONTRACT LINE ITEM NO. 5 – FURNISH AND INSTALL FIBER OPTIC CABLE

BETWEEN BUILDING 26 AND VARIOUS BUILDINGS AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 26 and Buildings 102, 51, 34, 32, 35, 1, 47, 73, 75, 71, 72, 41, 29, 30, 64, 53, 66, 84, 28, 58, 311, Water Boost Station, 67, 20, and 341 using the ductbanks installed in Contract Line Item No. 4;

installation of termination enclosures as noted on the drawings in Buildings 102, 51, 34, 32, 35, 1, 47, 73, 75, 71, 72, 41, 29, 30, 64, 53, 66, 84, 28, 58, 311, Water Boost Station, 67, 20, and 341; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 6 – FURNISH AND INSTALL FIBER OPTIC CABLE

BETWEEN BUILDING 341 AND BUILDINGS 436, 438, AND LIFEGUARD STATION

AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 341 and Buildings 436, 438, and Lifeguard Station using the ductbanks installed in Contract Line Item No. 4; installation of termination enclosures as noted on the drawings in Buildings 341, 436, 438, and Lifeguard Station; the termination of all new fiber optic cables; all connectors;

all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 7 – FURNISH AND INSTALL FIBER OPTIC CABLE

BETWEEN BUILDING 341 AND BUILDINGS 338 AND 340 AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 341 and Buildings 338 and 340 using the ductbanks installed in Contract Line Item No. 4; installation of termination enclosures as noted on the drawings in Buildings 341, 338, and 340; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 8 – FURNISH AND INSTALL FIBER OPTIC CABLE

BETWEEN BUILDING 26 AND BUILDING 438 AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 26 and Building 438 using the ductbanks installed in Contract Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 9 – FURNISH AND INSTALL FIBER OPTIC CABLE

BETWEEN BUILDING 438 AND THE FEE COLLECTION BUILDING AT SANDY

HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 438 and the Fee Collection Building using the ductbanks installed in Contract Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack as shown on the drawings.

CONTRACT LINE ITEM NO. 10 – UNEXPLODED ORDNANCE SURVEY AND

MONITORING AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the survey and monitoring for unexploded ordnances (UXO) for the ductbanks installed in all other Contract Line Items. The survey and monitoring for unexploded ordnances shall be performed in compliance with all relevant United States Army Corps of Engineers (USACE) and Department of Defense (DOD) requirements regarding personnel, equipment and procedures along the ductbank and conduit routing proposed by the Contractor.

CONTRACT LINE ITEM NO. 11 – OPTION A: FURNISH AND INSTALL DUCTBANK

AND FIBER OPTIC CABLE TO GUNNISON BEACH CENTER PAVILION AT SANDY

HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the construction of the ductbank between Gunnison Beach Center Pavilion and EMH-41; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; all required building and handhole penetrations;

fiber optic cables between Building 341 and Gunnison Beach Center using the ductbanks installed in Contract Line Item No. 4 and 11; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 12 – OPTION B: FURNISH AND INSTALL DUCTBANK

AND FIBER OPTIC CABLE TO BEACH CENTER E COMFORT STATION AT SANDY

HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the construction of the ductbank between Beach Center E Pavilion and PIT-02; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; all handholes; all required building and handhole penetrations; fiber optic cables between Building 341 and Beach Center E using the ductbanks installed in Contract Line Item No. 4 and 12; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 13 – OPTION C: FURNISH AND INSTALL DUCTBANK

AND FIBER OPTIC CABLE TO BEACH CENTER D PAVILION AT SANDY HOOK

UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the construction of the ductbank between Beach Center D Pavilion and EHH-53; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; all required building and handhole penetrations; fiber optic cables between Building 341 and Beach Center D using the ductbanks installed in Contract Line Item No. 4 and 13; the termination of all new fiber optic cables; all connectors;

all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 14 – OPTION D: FURNISH AND INSTALL DUCTBANK

AND FIBER OPTIC CABLE TO BEACH CENTER C PAVILION AT SANDY HOOK

UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the construction of the ductbank between Beach Center C Pavilion and PIT-07; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; all required building and manhole penetrations; fiber optic cables between Building 341 and Beach Center C using the ductbanks installed in Contract Line Item No. 4 and 14; the termination of all new fiber optic cables; all connectors;

all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 15 – OPTION E: FURNISH AND INSTALL DUCTBANK

AND FIBER OPTIC CABLE TO BEACH CENTER B PAVILION AT SANDY HOOK

UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the removal of any existing cables in the existing conduit from Beach Center B Pavilion to the nearby utility pole; cleaning of the existing conduit; installation of the pull lie in the existing conduit; installation of the conduit between the existing conduit and EHH-61; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; all required handhole penetrations; fiber optic cables between Building 341 and Beach Center B using the ductbanks installed in Contract Line Item No. 4 and 15; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 16 – OPTION F: CUT DOWN EXISTING PIT WALLS

AND INSTALL NEW TOP WITH LIFTING MANHOLE LID AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the removal of the top portion of the existing concrete pits; construction of new concrete walls and top for the existing concrete pits; installation of spring-assist, H-20 rated manhole lids; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; and all supports.

CONTRACT LINE ITEM NO. 17 – OPTION G: FURNISH AND INSTALL DUCTBANK

SOUTH OF BUILDING 438 AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the construction of the ductbank south of Building 438 to near the Sandy Hook Unit property line; restoration of any disrupted surface, including but not limited to concrete, asphalt, and soil; all connectors; all supports; and all required building penetrations.

Contractor shall coordinate with New Jersey State regulators and utility providers for location of final handhole near the Sandy Hook Unit property line.

CONTRACT LINE ITEM NO. 18 – OPTION H: FURNISH AND INSTALL

REDUNDANT FIBER OPTIC CABLE FROM BUILDING 102 AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 26 and Building 102 using the ductbanks installed in Contract Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 19 – OPTION J: FURNISH AND INSTALL REDUNDANT

FIBER OPTIC CABLE FOR BUILDINGS 34, 32, 35, 67, 1, AND WATER BOOST

STATION AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 26 and Buildings 34, 32, 35, 67, 1, and Water Boost Station using the ductbanks installed in Contract Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 20 – OPTION K: FURNISH AND INSTALL

REDUNDANT FIBER OPTIC CABLE FOR BUILDINGS 47, 75, 73, 72, 71, 41, 66, 84,64,

29, 30, AND 28 AT SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 26 and Buildings 47, 75, 73, 72, 71, 41, 66, 84, 64, 29, 30, and 28 using the ductbanks installed in Contract

Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 21 – OPTION L: FURNISH AND INSTALL REDUNDANT

FIBER OPTIC CABLE FOR BUILDINGS 53, 58, 20, 338, AND 340 AT SANDY HOOK

UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of the fiber optic cables between Building 26 and Buildings 53, 58, 20, 338, and 340 using the ductbanks installed in Contract Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

CONTRACT LINE ITEM NO. 22 – OPTION M: FURNISH AND INSTALL

REDUNDANT FIBER OPTIC CABLE FOR BEACH CENTERS AT SANDY HOOK

UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of fiber optic cables between Building 438 and Beach Centers B, C, D, and E and between Building 26 and Gunnison Beach Center using the ductbanks installed in Contract Line Item No. 4, 11, 12, 13, 14, and 15; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to facilitate redundant connectivity at Gunnison Beach Center and Beach Centers B, C, D, and E as shown on the drawings.

CONTRACT LINE ITEM NO. 23 – OPTION N: FURNISH AND INSTALL FIBER OPTIC

CABLE FOR SOUTH FEED TO BUILDINGS 436 AND LIFEGUARD STATION AT

SANDY HOOK UNIT:

This item consists of providing all equipment, labor, materials, supplies, and project administration for the installation of fiber optic cables between Building 438 and Buildings 436 and Lifeguard Station using the ductbanks installed in Contract Line Item No. 4; the termination of all new fiber optic cables; all connectors; all cable; and all splices. Fiber optic cables shall be single mode, outdoor, loose tube dry filled fiber optic cable in conformance with ITU-T G.652.D, with the quantity of fibers as determined by the connectivity requirements, installed from enclosure/networking rack to enclosure/networking rack to create a redundant loop as shown on the drawings.

2.1.3 Progress Payments

Design Phase - Progress payments during the design phase of the work will be based on submission, review, and acceptance of design deliverables.

Construction Phase - Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the % complete shall be initiated by the Contractor under the direction of a representative of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance. The Contractor shall make the computations for payment based on the governments verification of work completed and in place for any periods for which progress payments are requested.

The Contractor shall furnish the originals of all field notes and all other records relating to the basis for payment, to the Contracting Officer, who shall use them as necessary to determine the final amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.

2.1.4 Project Meetings

Design Meeting

After the award of the contract and acceptance of the Performance and Payment bonds, the CO will arrange a design meeting with the Contractor. This meeting shall occur at Fort Wadsworth, Staten Island, NY. The meeting agenda shall include the following as a minimum:

• Review and emphasize the Park needs and design objectives.

• Environmental and sustainability requirements

• Schedule of Values

• Design schedule (provide minimum of two color hard copies).

• Modifications during design

• Submittals during design

• Areas available for use by the DBC

• Access requirements of the Park

• Natural and Cultural Resource Protection

• Payments to the DBC

• Permits

Preconstruction Meeting

The following Part 2 Project Requirement deliverables shall be submitted a minimum of one week prior to the Preconstruction Meeting.

• Letter designating your Project Superintendent

• Project Schedule with construction portion fully developed

• Accident Prevention Program

• A list of subcontractors for this project (must be same as in your proposal)

• Written statements from subcontractors certifying compliance with applicable labor standard clauses

• Evidence of liability insurance coverage and workmen’s compensation for the contractor and all subcontractors

• Waste Management Plan

• Quality Control Plan

• Storm Water Pollution Prevention Plan (SWPPP) or Under-an-Acre Pollution Prevention

Plan (UPPP) Submittal process

• List of required permits

After 100% Complete DB Construction Documents are approved (or completed portions of CDs necessary for fast tracking the project), and prior to the start of construction, the CO will arrange an on-site Preconstruction meeting with the DBC. The meeting agenda will include the following as a minimum:

• Correspondence procedures

• Jobsite safety

• Roles and responsibilities

• Lines of Authority

• Progress Payments

• Submittal process

• Resolution to comments provided by NPS on the Part 2 Project Requirements

• NPS/DSC SharePoint Project website

• Construction schedule (Provide a minimum of two color hard copies and electronic copy in software it was created in.)

• Labor standards

• Payroll reports

• Modifications

• Accident reporting

• Park Rules and Regulations

• Medical emergency processes, availability, emergency numbers, and contacts.

• Park permits, burning construction waste, rules of the road, alcohol use, housekeeping, firearms, pets, natural and cultural resource concerns.

• Bridge, access road and site constraints.

• Visitation and public relations.

• Environmental and sustainability requirements for the Project, required tracking for sustainability (related submittals), use of the NPS Project Sustainability Checklist.

• Archeological Resources Protection Requirements

• Saturdays, Sundays, holidays and night work.

• Traffic control

• Unexploded ordnance

Progress Meetings

The Contractor shall participate in weekly telephone conference calls with the Contracting Officer, and other project team members to update them on the following meeting agenda items during both design and construction phases:

• Approval of minutes of previous meetings

• Submittal status

• Review of off-site fabrication and delivery

• Requests for Information (RFI’s) and issues

• Modifications

• Work in progress and projected

• Schedule update (provide updated CPM schedule)

• Status of Project Record Drawings and O&M Manuals

• Other business relating to work

2.1.5 Project Schedule

General: The Contractor shall upload the project schedule to the NPS/DSC SharePoint Project website and provide two (2) color copies after award and before the design meeting. The schedule shall include a detailed design phase with design deliverable submission dates, review periods as well as a summary construction schedule with important milestones included for both phases.

Fully develop the construction portion of the schedule and submit to the Contracting Officer on the NPS/DSC SharePoint Project website before the Preconstruction meeting or any construction begins. The project schedule shall be updated on a monthly basis throughout the entire contract period and until project substantial completion. The status date of each schedule update shall be 10 days before the progress payment request date.

Construction work cannot begin until government approval is obtained for either:

• The entire set of 100% Complete DB Construction documents.

• For fast track construction, the 100% Complete DB Construction documents affecting the work to be constructed.

Purpose: The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the DBC.

The project schedule will assist the Contractor and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the DBC's monthly progress payment requests.

Software: The software shall be the latest version of Microsoft Project, Primavera Project Planner, SureTrak, or approved equal.

Schedule Development: The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be the same date as the established completion date of the contract.

The Contractor shall use the Critical Path Method (CPM) with limited use of lead or lag durations between schedule activities. The Contractor's project schedule shall consist of procurement activities (including mobilization, submittal, and the fabrication and delivery of key and long-lead procurement items) and construction activities.

The Contractor's project schedule shall consist of, but not be limited to, the following for each activity:

• Identify each and every activity number with numerical designations (maximum 5-digit).

Numbering of activities shall be in increments of 10.

• Concise description of the work represented by the activity (maximum 48 characters).

Avoid the use of non-standard abbreviations. The work related to each activity shall be limited to one work trade.

• Activity duration in whole working days with a maximum duration of 15 work days each, unless otherwise approved by the Contracting Officer, except for non-construction activities including mobilization, shop drawing and sample submittals, fabrication of materials, delivery of materials and equipment, and concrete curing.

In developing the project schedule, the Contractor shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.

The project schedule, as developed, shall show the sequence and interdependence of activities required for complete performance of the work. The Contractor shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan.

Proposed durations assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.

Resource loading of each activity shall list all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown. Include permit requirements and constraints. Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the contract time.

Project Schedule Updates

Monthly updates: The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract.

If, in the judgment of the Contracting Officer, the Contractor fails or refuses to provide a schedule of values and a complete schedule update or revision as specified hereinafter, the Contractor shall be deemed to have not provided the required information upon which the progress payment may be made, and shall be subject to retainage of a portion of the payment.

Narrative: The report shall include a brief description of the actual progress made during the update period; actual and potential delaying activities; any impediments to progress; issues related to inclement weather; progress toward established milestones and project float. The report shall include a brief description of the work anticipated to be performed in the next month.

Any minor revisions to the schedule should be identified so they can be evaluated and accepted or rejected.

As the Work progresses, indicate Actual Completion percentage for each activity.

If the schedule update shows a late finish date after the contract completion date, at a minimum, include the following in the narrative with your submission:

• Any known delays.

• Actions that will be taken to get back on schedule.

• Pending modifications.

• Impediments or constraints affecting progress.

Progress Payments: The monthly updating of the currently accepted Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the Contractor fails to provide schedule updates or revisions, then a portion of the monthly payment may be retained until such corrections have been made.

Time Impact Analysis for Contract Modifications, Changes, Delays, and Contractor Requests Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the project schedule, the Contractor shall submit to the Contracting Officer a written time impact analysis illustrating the influence of each modification, change, delay, or Contractor request on the contract time.

Time Extensions: Activity delays shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the project schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

Float: Float is not for the exclusive use or benefit of either the National Park Service or the DBC. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by…