P03 Liquidated Damages Pittsburgh 36C24426R0049 646-21-101 UD SPS AHU RO Upgrade signed.pdf

PDF 216 KB Posted

Attached to
Z1DA--646-21-101 UD SPS AHU & RO Upgrade (VA-26-00036217)
Solicitation number
36C24426R0049
Issued by

About this file

This is a Liquidation Damages Formulation Memo for solicitation number 36C24426R0049, UD SPS AHU & RO Upgrade, establishing financial penalties for contractor schedule delays on a construction project.

The memo details liquidated damages calculations based on government personnel costs incurred due to contract administration delays. For VISN 4 Contracting, Engineering, and Legal reviews, daily damages total $338.14, comprising costs for a GS-14/5 Contracting Officer Supervisor ($68.83 for 1 hour), a GS-13/5 Contracting Officer and GS-011/1 Contract Specialist ($58.25 and $144.25 respectively), and a GS-14/4 Legal Officer ($66.81 for 1 hour). Facility Engineering (COR/COTR) damages total $267.78 per day, comprised of a GS-13/5 Construction Manager ($116.50 for 2 hours) and a GS-12/6 Project Engineer ($151.28 for 3 hours). All wage rates are based on the General Schedule Locality Pay Table for Pittsburgh-New Castle-Weirton, PA-OH-WV, effective January 1, 2024. The grand total liquidated damages amount is $605.92 per calendar day of inexcusable delay until work completion or acceptance. The formulation follows Federal Acquisition Regulation 36.206 and is designated as compensatory in nature only, with the government retaining the right to pursue actual damages separate from these assessments. The memo was signed by Elijah McIntosh, Contracting Officer, on March 5, 2026.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Liquidation Damages Formulation Memo

Solicitation Number: 36C24426R0049

UD SPS AHU & RO Upgrade

All Civilian wage rates are based upon the General Schedule Locality Pay Table (Pittsburgh-New Castle-

Weirton, PA-OH-WV) effective January 1, 2024 for Contracting and Project Engineer and FMS Manager.

1. Estimated liquidated damages for VISN 4 Contracting, Engineering, and Legal reviews per day of inexcusable delay:

CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE

Contracting Officer

Supervisor

GS-14 / 5 $68.83 1 Hours $68.83

Contract Specialist

GS-13 / 5

GS-011 / 1

$58.25

$36.06

1 Hour

4 Hours

$58.25

$144.25

Legal Officer GS-14 / 4 $66.81 1 Hour $66.81

TOTAL PER DAY

$338.14

2. Estimated liquidated damages for Facility Engineering (COR/COTR) per day of inexcusable delay:

CLASSIFICATION GRADE RATE HOURS TOTAL HOURLY RATE

Construction Manager GS-13 / 5 $58.25 2 Hours $116.50

Project Engineer GS-12 / 6 $50.42 3 Hours $151.28

TOTAL PER DAY

$267.78

Grand Total Per Day $ 605.92

3. The Contractor shall pay liquidated damages to the Government in the amount of $605.92 for each calendar day of delay until the work is completed or accepted. The aforementioned costs were derived based upon historical trends associated with the time required of the parties to perform the additional contract administration which has not been completed by the Contractor within the specified time. The purpose of Liquidated Damages is compensatory only.

The government retains the right to seek actual damages so far as they are distinguishable and separate from the

Contractor failing to complete the work within the time specified in the contract.

4. The formulation of Liquidated Damages as detailed above are in accordance with Federal Acquisition Regulation

36.206 and will be assessed for each calendar day required to complete the construction work on this project past the scheduled completion date.

Elijah McIntosh

2026-03-05T12:54:33-0500
ELIJAH MCINTOSH

File details come from the government source that posted it. Updated .