P01 6a - 695-20-105 Specifications.pdf
PDF 2 MB Posted
- Attached to
- Z2DA--695-20-105: Upgrade Electrical System Area 2 Federal contract opportunity
- Solicitation number
- 36C25222B0010
About this file
This solicitation is for upgrade work to the electrical system at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The solicitation number is 36C25222B0010 and involves upgrading electrical systems in Area 2. The work includes improvements to electrical infrastructure in various buildings on the medical center campus including Buildings 5, 6, 7, 20, 43, 102, 107, 108, 144 and 70. The solicitation is from the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12. The anticipated award date is not specified.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SPECIFICATIONS
Department of Veterans Affairs Clement J. Zablocki VAMC
Upgrade Electrical System Area 2 VA Project No. 695-20-105
100% Construction Documents
July 16, 2021
Prepared by:
Apogee Consulting Group, PA
1151 Kildaire Farm Road Cary, NC 27511
Clement J. Zablocki VAMC July 16, 2021 Upgrade Electrical Systems Area 2 100% Construction Documents Milwaukee, WI Project No. 695-20-105
Thomas J. Smith, IV RA Registered Architect
Kevin T. Kublank, PE Electrical Engineer
DocuSign Envelope ID: DCDD2485-D328-4974-B2C2-2E1139F634C0
7/14/20217/14/2021
Milwaukee, WI Project No. 695-20-105
08-01-20
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
**VA TO PROVIDE EDITED DIV. 01 SPECIFICATIONS**
01 00 00 General Requirements 03-20 01 01 10 SN Special Notes 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 03-20 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 07-20 01 42 19 Reference Standards 09-19 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 09-13 01 81 13 Sustainable Construction Requirements 10-17
DIVISION 02 – EXISTING CONDITIONS
02 21 13 Site Surveys 08-16 02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 07-19
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 Bituminous Dampproofing 02-16 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 31 13 Access Doors and Frames 02-16
DIVISION 09 – FINISHES
09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-16
Milwaukee, WI Project No. 695-20-105
08-01-20
00 01 10-2
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 10 – SPECIALTIES
10 26 00 Wall and Door Protection 10-15
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17 26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 05 41 Underground Electrical Construction 01-17 26 05 73 Overcurrent Protective Device Coordination Study 01-18 26 08 00 Commissioning of Electrical Systems 11-16 26 24 13 Distribution Switchboards 01-18 26 24 16 Panelboards 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 32 13 Engine Generators 01-18 26 36 23 Automatic Transfer Switches 01-17 26 43 13 Surge Protective Devices 01-17
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16 31 23 23.33 Flowable Fill 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16 32 12 16 Asphalt Paving 09-15
DIVISION 34 – TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
Milwaukee, WI Project No. 695-20-105
SHEET NO. SHEET LIST BUILDING DRAWING
NUMBER
GENERAL INFORMATION
G-001 COVER SHEET 1 OF 79
G-100 TYPICAL ICRA DETAILS 2 OF 79
G-101 OVERALL ICRA FLOOR PLANS - BUILDING 6 6 3 OF 79
G-102 ENLARGED ICRA PLANS - BUILDING 6 6 4 OF 79
CIVIL
CD101 CIVIL DEMOLITION PLAN 107, 108,
T-114
CS101 CIVIL SITE & UTILITY PLAN 107, 108,
T-114
CS501 CIVIL PAVING AND CONSTRUCTION DETAILS 7 OF 79
ARCHITECTUR
E
A-001 PARTITION TYPES, ABBREVIATIONS AND
GENERAL NOTES
A-100 OVERALL FLOOR PLANS - BUILDING 6 6 9 OF 79
A-101 ENLARGED PLANS - BUILDING 6 6 10 OF 79
ELECTRICAL
E-001 ELECTRICAL GENERAL NOTES, SYMBOL LEGEND,
SCHEDULES, AND ABBREVIATIONS
ES101 ELECTRICAL SITE PLAN CAMPUS 12 OF 79
ES102 ELECTRICAL SITE PLAN BLDG 107 & 108 107, 108,
T-114
ES103 ELECTRICAL SITE PLAN ENLARGED PLAN 107, 108 14 OF 79
E-100 BUILDING 5 BASEMENT & FIRST FLOOR PLAN 5 15 OF 79
E-101 BUILDING 5 SECOND & THIRD FLOOR PLAN 5 16 OF 79
E-102 BUILDING 6 BASEMENT FLOOR PLAN 6 17 OF 79
E-103 BUILDING 6 FIRST FLOOR PLAN 6 18 OF 79
E-104 BUILDING 6 SECOND FLOOR PLAN 6 19 OF 79
E-105 BUILDING 6 THIRD & ATTIC FLOOR PLAN 6 20 OF 79
E-106 BUILDING 7 BASEMENT, FIRST, SECOND, &
THIRD FLOOR PLAN
7 21 OF 79
E-107 BUILDING 20 BASEMENT & FIRST FLOOR PLAN 20 22 OF 79
E-108 BUILDING 20 SECOND & THIRD FLOOR PLAN 20 23 OF 79
E-109 BUILDING 43 BASEMENT FLOOR PLAN -
PARTIAL
43 24 OF 79
E-110 BUILDING 43 FIRST FLOOR PLAN - PARTIAL 43 25 OF 79
E-111 BUILDING 43 SECOND & THIRD FLOOR PLAN 43 26 OF 79
E-112 BUILDING 102 BASEMENT FLOOR PLAN 102 27 OF 79
E-113 BUILDING 107 & 108 FLOOR PLANS 107, 108 28 OF 79
E-114 BUILDING 144 FLOOR PLAN 144 29 OF 79
Milwaukee, WI Project No. 695-20-105
E-115 BUILDING 70 BASEMENT FLOOR PLAN 70 30 OF 79
E-116 BUILDING 70 FIRST FLOOR PLAN 70 31 OF 79
E-117 BUILDING 70 SECOND FLOOR PLAN 70 32 OF 79
EP101 BUILDING 5, 6, & 43 ENLARGED FLOOR PLANS 5, 6, 43 33 OF 79
E-501 ELECTRICAL DETAILS 34 OF 79
E-600 EQUIPMENT LIST SCHEDULE & CABLE LIST
SCHEDULE
E-601 BUILDING 6 SINGLE LINE DIAGRAM - PARTIAL 6 36 OF 79
E-602 BUILDING 5 & 7 SINGLE LINE DIAGRAMS -
PARTIAL
5, 7 37 OF 79
E-603 BUILDING 20 SINGLE LINE DIAGRAM -
PARTIAL
20 38 OF 79
E-604 BUILDING 43 SINGLE LINE DIAGRAM -
PARTIAL
43 39 OF 79
E-605 BUILDING 107, 108, 102, & 144 SINGLE
LINE DIAGRAMS - PARTIAL
107, 108, 144, 102
E-606 BUILDING 70 C SINGLE LINE DIAGRAMS 70 41 OF 79
E-607 BUILDING 70 D SINGLE LINE DIAGRAMS 70 42 OF 79
E-608 PANEL SCHEDULES - BUILDING 5 43 OF 79
E-609 PANEL SCHEDULES - BUILDING 5 44 OF 79
E-610 PANEL SCHEDULES - BUILDING 5 45 OF 79
E-611 PANEL SCHEDULES - BUILDING 5 46 OF 79
E-612 PANEL SCHEDULES - BUILDING 6 47 OF 79
E-613 PANEL SCHEDULES - BUILDING 6 48 OF 79
E-614 PANEL SCHEDULES - BUILDING 6 49 OF 79
E-615 PANEL SCHEDULES - BUILDING 6 50 OF 79
E-616 PANEL SCHEDULES - BUILDING 6 51 OF 79
E-617 PANEL SCHEDULES - BUILDING 6 52 OF 79
E-618 PANEL SCHEDULES - BUILDING 6 53 OF 79
E-619 PANEL SCHEDULES - BUILDING 6 54 OF 79
E-620 PANEL SCHEDULES - BUILDING 6 55 OF 79
E-621 PANEL SCHEDULES - BUILDING 6 56 OF 79
E-622 PANEL SCHEDULES - BUILDING 6 57 OF 79
E-623 PANEL SCHEDULES - BUILDING 6 58 OF 79
E-624 PANEL SCHEDULES - BUILDING 6 59 OF 79
E-625 PANEL SCHEDULES - BUILDING 6 60 OF 79
E-626 PANEL SCHEDULES - BUILDING 7 61 OF 79
E-627 PANEL SCHEDULES - BUILDING 7 62 OF 79
E-628 PANEL SCHEDULES - BUILDING 7 63 OF 79
E-629 PANEL SCHEDULES - BUILDING 20 64 OF 79
E-630 PANEL SCHEDULES - BUILDING 20 65 OF 79
E-631 PANEL SCHEDULES - BUILDING 20 66 OF 79
E-632 PANEL SCHEDULES - BUILDING 20 67 OF 79
Milwaukee, WI Project No. 695-20-105
E-633 PANEL SCHEDULES - BUILDING 43 68 OF 79
E-634 PANEL SCHEDULES - BUILDING 43 69 OF 79
E-635 PANEL SCHEDULES - BUILDING 43 70 OF 79
E-636 PANEL SCHEDULES - BUILDING 43 71 OF 79
E-637 PANEL SCHEDULES - BUILDING 43 72 OF 79
E-638 PANEL SCHEDULES - BUILDING 43 73 OF 79
E-639 PANEL SCHEDULES - BUILDING 43 74 OF 79
E-640 PANEL SCHEDULES - BUILDING 43 75 OF 79
E-641 PANEL SCHEDULES - BUILDING 107 76 OF 79
E-642 PANEL SCHEDULES - BUILDING 108 77 OF 79
E-643 PANEL SCHEDULES - BUILDING 108 , 114, &
GENERATOR
E-644 PANEL SCHEDULES - BUILDING 144 79 OF 79
---INTENTIONALLY BLANK---
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 PROFESSIONAL SURVEYING SERVICES
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.16 USE OF ROADWAYS
1.17 RESIDENT ENGINEER'S FIELD OFFICE
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.20 TEMPORARY USE OF NEW ELEVATORS
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
1.23 NEW TELEPHONE EQUIPMENT
1.24 TESTS
1.25 INSTRUCTIONS
1.26 GOVERNMENT-FURNISHED PROPERTY
01 00 00 -2
1.27 RELOCATED EQUIPMENT AND ITEMS
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT
1.29 CONSTRUCTION SIGN
1.30 SAFETY SIGN
1.31 PHOTOGRAPHIC DOCUMENTATION
1.32 FINAL ELEVATION Digital Images
1.33 HISTORIC PRESERVATION
1.34 VA TRIRIGA CPMS
01 00 00 -3
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. See attached scope of work.
B. Visits to the site by bidders may be made only as described in the solicitation.
C. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
D. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access. Refer to Section 01 01 10-SN SPECIAL NOTES for information security, fingerprint, badging, construction door access and parking requirements.
E. Routine Inspections and Maintenance During Construction
1. Provide routine inspections and maintenance services as prescribed in Operations & Maintenance manuals required under this contract.
2. Provide services during construction and until items below are completed:
a) VA Inspection Complete
b) Training of VA Maintenance staff
c) Acceptance by VA of each system described in other specifications related to this contract.
d) O&M Manual submittals received, reviewed, and approved by VA
3. Systems included in this contract are:
a) Electrical Systems
b) Mechanical and Ventilation Systems to include Controls
c) Plumbing Systems
d) Doors/Hardware
F. Submit O&M manuals at substantial completion of work phases and update upon completion of final phase one spreadsheet based comprehensive summary schedule of routine inspection and maintenance for systems.
01 00 00 -4
List: specification section, article, and paragraph; description of systems/subsystems; O&M manual reference; frequency.
1.3 STATEMENT OF BID ITEM(S) – SEE BID SCHEDULE
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the beta.SAM.gov website where the solicitation is posted. Hard copies will be the responsibility and expense of the Contractor.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
5. A Special Agreement SAC form is required for every contract employee. See the SPECIAL NOTES specification for an example of
01 00 00 -5 this SAC form. This needs to be supplied to the COR for every contract employee on the jobsite. Even if the contractor has an active badge, a SAC form is needed for the COR’s records.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the COR. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the COR and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work.
With the written consent of the COR, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction
01 00 00 -6 materials, debris, standing construction equipment and vehicles at all times.
G. Execute work to interfere as little as possible with normal functioning of the Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by. All such actions shall be coordinated with the COR or Utility Company involved:
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
I. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
01 00 00 -7
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to ensure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, Contracting Officer, COR and Contractor.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, seven feet minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps
01 00 00 -8 and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 15 inches. Bottom of fences shall extend to one inch above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with COR to respond to an alarm from Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 21 days in advance of proposed interruption.
01 00 00 -9
Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
O. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
P. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.
01 00 00 -10
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
Q. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
R. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workers shall not pass through the service area during this period:
1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.
2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
01 00 00 -11
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
01 00 00 -12
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those
01 00 00 -13 facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any
01 00 00 -14 interpretation of or conclusion drawn from the data or information by the
Contractor.
B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.
C. A copy of the soil report will be made available for inspection by bidders upon request to the COR at the VA Medical Center, and shall be considered part of the contract documents.
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections.
The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and benchmarks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
01 00 00 -15
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.
Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
01 00 00 -16
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
E. Contractors shall update (as work is completed) the VA electrical, medical gas, domestic plumbing and mechanical piping master schematic books. These books are located in the FM office.
01 00 00 -17
F. MEP Coordination Drawings:
1. Prepare and provide coordination drawings showing the location of openings through slabs, the pipe sleeves/anchors and hanger inserts, as well as the location and elevation of utility lines, including, but not limited to, conveyor systems, pneumatic tubes, ducts, all existing utilities, and conduits and pipes 2 inches and larger in diameter. Drawings required for all areas being remodeled or new and ancillary areas required by such utility runs. Ancillary area drawings to include equal space on each side of main runs from main source to final location. These drawings, including plans, elevations, and sections as appropriate shall clearly show the manner in which the utilities fit into the available space and how they relate to each other and to existing building elements and controls for maintenance operations. Drawings shall be of appropriate scale to satisfy the previously stated purposes.
2. Drawings must be composite (with distinctive colors for the various trades) including but not limited to HVAC equipment, HVAC ductwork, mechanical piping, plumbing, fire protection, electrical, medical gases, telecommunications, etc. The submitted drawings for a given area of the project shall show the work of all trades which will be involved in that particular area. A complete composite drawing set or complete sets of separate reproducible drawings and AutoCAD files shall be received by the Government not less than 20 days prior to the scheduled start of the work in the area illustrated by the drawings, for the purpose of showing the contractor's planned method of installation.
3. The objectives of such drawings are to promote carefully planned work sequence and proper trade coordination, in order to assure the expeditious solutions of problems and the installation of lines and equipment as contemplated by the contract documents while avoiding or minimizing additional costs to the contractor and to the
Government. In the event the contractor, in coordinating the various installations and in planning the method of installation, finds a conflict in location or elevation of any of the utilities with themselves, with structural items or with other construction items, the contractor shall bring this conflict to the attention of
01 00 00 -18 the contracting officer immediately. In doing so, the contractor shall explain the proposed method of solving the problem or shall request instructions as to how to proceed if adjustments beyond those of usual trades coordination are necessary.
4. Contractor to include initial and two revisions as part of original contract. Utilities installation work will not proceed in any area prior to the submission and completion of the Government review of the coordinated drawings for that area, nor in any area in which conflicts are disclosed by the coordination drawings until the conflicts have been corrected to the satisfaction of the contracting officer. It is the responsibility of the contractor to submit the required drawings in a timely manner consistent with the requirements to complete the work covered by this contract within the prescribed contract time.
1.15 WARRANTY MANAGEMENT – NOT USED
1.16 USE OF ROADWAYS – NOT USED
1.17 RESIDENT ENGINEER'S FIELD OFFICE – NOT USED
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT – NOT USED
1.19 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials (debris removal, moving new equip/materials) and Contractor's personnel is permitted. Refer to the SPECIAL NOTES Specification 01 01 10-SN.
1. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
1.20 TEMPORARY USE OF NEW ELEVATORS – NOT USED
1.21 TEMPORARY TOILETS – NOT USED
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to
01 00 00 -19 the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
01 00 00 -20
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes will be cause for revocation (at CORs discretion) of use of water from Medical Center's system.
G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the
Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the
Contractor at Contractor's expense.
1.23 NEW TELEPHONE EQUIPMENT – NOT USED
1.24 TESTS – NOT USED
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a
01 00 00 -21 different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR, does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.25a ROUTINE INSPECTIONS AND MAINTENANCE DURING CONSTRUCTION
A. Provide routine inspections and maintenance services as prescribed in
Operations & Maintenance manuals required under this contract.
B. Provide services during construction and until items below are completed:
i. VA Inspection complete.
iii. Training of VA Maintenance staff
01 00 00 -22
iv. Acceptance by VA of each system described in other specifications related to this contract.
v. O&M Manual submittals received, reviewed, and approved by VA.
c. Systems included in this contract are:
i. Patient Lifts
ii. Elevators
iii. Plumbing/Medical Gas/Fire Protection
iv. HVAC
1.25b SUBMIT
A. Submit with O&M manuals [if phased work, submit at substantial completion of work phases and update upon completion of final work phase] one spreadsheet based comprehensive summary schedule of routine inspection and maintenance for systems. List: specification section, article, and paragraph; description of systems/subsystems; O&M Manual reference; frequency.
1.26 GOVERNMENT-FURNISHED PROPERTY – NOT USED
1.27 RELOCATED EQUIPMENT AND ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR.
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
01 00 00 -23
E. Contractor shall employ services of an installation engineer, who is an authorized representative of the manufacturer of this equipment to supervise assembly and installation of existing equipment, required to be relocated.
F. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
1.28 STORAGE SPACE FOR DEPARTMENT OF VETERANS AFFAIRS EQUIPMENT – NOT USED
1.29 CONSTRUCTION SIGN – NOT USED
1.30 SAFETY SIGN – NOT USED
1.31 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, provide photographic documentation of construction progress and at appropriate milestones.
B. Photographic documentation elements:
1. Each digital image shall be minimum size of 4 megapixels (MP).
2. Before construction, the construction area, adjacent utilities and adjacent structures surrounding the site shall be documented.
3. Before construction, the construction area, adjacent utilities and adjacent structures surrounding the site shall be documented.
4. As-built condition of new utilities shall be documented prior to placing concrete and/or backfilling. This process shall include all underground utilities at the site.
5. As-built conditions of electrical systems shall be documented. As-built conditions of exterior grade elevations shall be documented specifically to capture the waterproofing work.
6. As-built finished…