Amendment 0002 - Door Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002 A400-4 - ENLARGED PLANS ELEVATIONS PHASE D.pdf | ||
| Amendment 0002 SF30.pdf | ||
| Amendment 0002 A400-1 - ENLARGED PLANS ELEVATIONS PHASE A.pdf | ||
| Amendment 0001 GS01P10BZC0022.pdf | ||
| pre-proposaslattendees.pdf | ||
| PreProposalConference.pdf | ||
| FINAL WORKING DOC 041910 - DO NOT DELETE.pdf | ||
| Phase III Complete Spec.pdf | ||
| ONeill SF1442.pdf | ||
| Wage Determination MA100001 4.16.2010.pdf | ||
| RFP 2 AGREEMENT.pdf | ||
| REPSANDCERTS1.doc | DOC document | |
| RFP 2 SOLICITATION.pdf | ||
| Pre Bid.doc | DOC document | |
| Short List Revised.doc | DOC document | |
| Short List.doc | DOC document | |
| ONeil RFP I Amendment 0001.doc | DOC document | |
| O'Neill Phase I RFP Final 030410.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE SHEDULE
S E E S C H E D U L E
SEE SHEDULE
S E E S C H E D U L E
SEE SCHEDULE
S E E S C H E D U L E
SEE SHEDULE
S E E S C H E D U L E
SEE SHEDULE
S E E S C H E D U L E
COORDINATE W/ DOOR
COORDINATE W/ DOOR
COORDINATE W/ DOOR
S E E S C H E D U L E
2" TYP 2" TYP 2" TYP
4"4"
SEE SHEDULE
S E E S C H E D U L E
4"4"
4" 4" 6
SEE SHEDULE
4" 4"
A
DOOR TYPES
TYPE
B
TYPE
G
TYPE
D
TYPE
E
TYPE
F2
TYPE
F
TYPE
F1
TYPE
F3
TYPE
FRAMES TYPES
C
TYPE
WOOD WOOD
SOLID
CORE
GLASSGLASS
GLASSGLASS
GLASSGLASS
TEMP
GLASS
SOLID
CORE
TEMP
GLASS
TEMP
GLASS
TEMP
GLASS
SOLID
CORE
PROVIDED
BY
DEMOUNT-
ABLE
PARTITION
MANUF.
SW
SW
SEALANT 1/2"
WALL + 1"
1 15/16" 1 15/16"
VIF
SEALANT
/1
W A L L
2"
3 5/8" METAL STUD FRAMING
V
IF
/1
SEALANT 1/2"
WALL + 1"
1 15/16" 1 15/16"
VIF
SEALANT
W A L L
2"
3 5/8" METAL STUD FRAMING
V
IF
/1
GENERAL NOTES:
1. GENERAL CONTRACTOR SHALL VERIFY ALL
DOOR/FRAME SIZES, DIMENSIONS, DOOR SWIGNS,
DOOR/FRAME MATERIALS, DOOR/FRAME TYPES, FRAME
WIDTH AND DEPTH, THROAT DEPTH AND FRAME HEAD
HEIGHT.
2. GENERAL CONTRACTOR SHALL VERIFY AND
COORDINATE ALL DOOR HARDWARE REQUIREMENTS
FOR ALL FRAMES INDICATED. ALL SUBMITTALS ISSUED
TO THE ARCHITECT SHALL REFLECT THIS FIELD
VERIFIED COORDINATION.
3. ALL WOOD DOORS ARE TO HAVE SOLID CORE.
4. ALL FRAMES SHALL BE SHIMMED/CAULKED IN
ACCORDANCE WITH ACCEPTED PRACTICES.
5. ALL HOLLOW METAL FRAMES IN MASONRY WALLS ARE
TO BE GROUTED SOLID, INCLUDING HEADS.
6. REFER TO FINISH PLAN FOR FINISHES. FOR EXISTING
DOORS SEE NOTE 7 ON FINISH PLANS.
7. REFER TO PLANS FOR PROPER DOOR SWINGS.
8. ALL WOOD DOOR EDGES SHALL BE FACTORY FINISHED
AND SHALL MATCH DOOR FACE VENEER AND FINISH.
9. ALL HOLLOW METAL FRAMES SHALL BE WELDED, NO
KNOCK-DOWN FRAMS WILL BE ACCEPTED.
10. GENERAL CONTRACCTOR SHALL VERIFY ALL DOOR
UNDERCUT AND LOUVER LOCATIONS WITH MECHANICAL
DRAWINGS.
11. THE USE OF THRU-BOLTING FOR ANY DOOR HARDWARE
WILL NOT BE ACCEPTED.
12. ALL HARDWARE FOR ALUMINUM DOORS/FRAMES ARE TO
BE PROVIDED BY THE DOOR/FRAME MANUFACTURER
EXCEPT LOCK CYLINDERS WHICH WILL BE PROVIDED
BY THE REMAINING DOOR HARDWARE SUPPLIER.
HARDWARE IS TO BE COORDINATED WITH THE
HARDWARE ON THE REMAINDER OF THE PROJECT.
13. GENERAL CONTRACTOR SHALL COORDINATE WHERE
DOORS/FRAMES REQUIRE CONDUITS OR WIRING
INSTALLED DURING FRAME INSTALLATION FOR FUTURE
ELECTRICAL CONNECTIONS FOR LOCKS, STRIKES, ETC.
MATERIALS
HOLLOW METAL - H.M.
ALUMINUM - AL. ALUM.
GLASS - GL
WOOD - WD
MARBLE - MAR.
FIBERGLASS REINFORCED
POLYESTER ON ALUM. FRAME -
FRP.
SOLID CORE - SC.
MINERAL CORE - MC.
ACOUSTICAL CORE - AC.
RATING
"A" LABEL - 1/2 HR. MIN. RATING
"B" LABEL - 1/2 HR. MIN. RATING
"C" LABEL - 3/4 HR. MIN. RATING
GLASS
IG INSULATED
SW SWITCHABLE PRIVACY
GLASS
CRB CLEAR RATED GLASS
HARDWARE SETS - NOTE: TO CONFPRM TO BUILDING STANDARD MASTER KEY SYSTEM
HARDWARE SET NO. 1
EACH SINGLE DOOR TO
RECEIVE:
1 EA. CLASSROOM TYPE,
3 EA. HINGES
1 EA. WALL STOP
3 EA. SILENCERS
NOTE: PROVIDE ELECTRIFIED
HINGE FOR SWITCHABLE
PRIVACY GLASS IN WIRING,
CONTRACTOR TO COORDINATE
HARDWARE SET NO. 2
EACH SINGLE DOOR TO
RECEIVE:
1 EA. STOREROOM TYPE,
3 EA. HINGES
1 EA. WALL STOP
3 EA. SILENCERS
1 EA. CLOSER
HARDWARE SET NO. 3
EACH SINGLE DOOR TO
RECEIVE:
1 EA. PASSAGE TYPE,
1 EA. SINGLE DUMMY TYPE
(WITH DOOR PAIR)
3 EA. HINGES
3 EA. SILENCERS
GENERAL HARDWARE NOTES:
1. MOUNTING HEIGHTS SHALL BE AS FOLLOWS:
DOOR LEVERS - 38" TO CENTERLINE
CYLINDERS - 48" TO CENTERLINE
PUSH PLATE - 48" TO CENTERLINE
PULL PLATE - 42" TO CENTERLINE
BUTTS - TOP HINGE - 5" DOWN
- TOP HINGE - 10" UP
EMER. EXIT. HWD. - 42" TO CENTERLINE
2. ALL HANDSETS SHALL BE LEVER TYPE. ALL
HARDWARE SHALL COMPLY WITH ALL A.D.A.
HARDWARE.
3. ALL PANIC HARDWARE SHALL BE OPERATED
WITH A FORCE OF 15 POUNDS TO COMPLY WITH
A.D.A. REQUIREMENTS
4. THE DOOR OPENING FORCE FOR ALL INTERIOR
DOORS MUST NOT EXCEED 5 POUNDS.
5. ALL LOCKSETS TO BE GRADE 1.
6. GC TO COORDINATE DOOR HARDWARE WITH
DEMOUNTABLE PARTITION MANUFACTURER.
HARDWARE SET NO. 4
EACH PAIR OF DOORS TO RECEIVE:
3 EA. HINGES 4 1/2" X 4 1/2"
2 EA. EXIT DEVICE
2 EA. LEVER PASSAGE TYPE
1 EA. CLOSERS
3 EA. SILENCERS
1 EA. MAGNETIC LOCKS
HARDWARE SET NO. 5
EACH SINGLE DOOR TO RECEIVE:
MANUFACTURER:
BLUMCRAFT H-100-F FOR WOOD
DOOR,
SCHLEGE,
BEST,
OR APPROVED EQUAL
4 EA. HINGES
3 EA. SILENCERS
1 EA. MAGNETIC LOCKS
1 EA. CLOSER
JAMB J-1 HEAD H-1
JAMB J-3 HEAD H-3
SEALANT
SEALANT
JAMB J-2 HEAD H-2
W A L L
2"
V .I .F
WALL + 1"
V.I.F.
SUB FLOOR
FLOORING
STRIP
TRANSITION
ADA COMPLIANT
TILE
OR
STONE
HORIZONTAL REVEALS
TO ALIGN WITH
EXTERIOR WINDOWS
HORIZONTAL REVEALS
TO ALIGN WITH
EXTERIOR WINDOWS
A/E CON. NO.
SHEET SIZE: 30x42
C E R T
IF
IC
A T
IO
N S
K E Y P L A N
MARK DATE DESCRIPTION
R E V
IS
IO
N N O T E S
C O N T R A C T O R S
B U
IL
D
IN
G
P R O J E C T
D R A W
IN
G
A/E TASK NO.
CONS. CONTR.
CONS. WORK
PRIME A/E
SUB A/E
CONSTR. CON.
NAME
STREET
CITY / ST. / ZIP
BUILDING NO.
OTHER
BUILDING NOs.
FACILITY CODE
PROJECT
TITLE
PROJECT
DESCRIPTION
PROJECT NO.
GSA PM
SUBMISSION
SUB. DATE
DRAWING TITLE
FLOOR NO.
DRAWN BY
CHECKED BY
DRAWING NO.
DISCIPLINE SHEET TYPE SEQUENCE
BBIX, L.L.C.
THOMAS P. O'NEILL FEDERAL BUILDING
10 CAUSEWAY STREET
BOSTON, MA 02111
ELIZABETH MEES COTR/PM
GENERAL SERVICES ADMINISTRATION
NEW ENGLAND REGION (REGION 1)
PROPERTY OF THE UNITED
STATES GOVERNMENT FOR
OFFICIAL USE ONLY
VMA00011
MA0153ZZ
PHASE A
N.I.C.
GS-01P-09-BW-D-0037
GS-P-01-10-BW-5018
BUILDING
NORTH
10TH FLOOR
FINAL WORKING DOCUMENTS
DOOR SCHEDULE PHASE A
10TH & 11TH FLOOR RENOVATION PHASE III
JD
JD
04/15/2010
A600.1
1/4" = 1'-0"
DOOR TYPE LEGEND
3" = 1'-0"
HEAD AND JAMB DETAILS
FULL SIZE
TRANSITION STRIP
1/4" = 1'-0" 1A
TYPICAL DEMOUNTABLE PARTITION EAST ELEVATION (ALTERNATE NO.4)
1/4" = 1'-0"
TYPICAL PARTITION NORTH ELEVATION
1/4" = 1'-0" 3A
TYPICAL DEMOUNTABLE PARTITION WEST ELEVATION (ALTERNATE NO.4)
1 5/17/10 AMENDMENT NO 3
1/4" = 1'-0"
TYPICAL GWB (BASE) PARTITION EAST ELEVATION
1/4" = 1'-0"
TYPICAL GWB (BASE) PARTITION WEST ELEVATION
File details come from the government source that posted it. Updated .