This document outlines supplemental conditions for contractors working off-site at Argonne National Laboratory, including insurance requirements, environmental and safety compliance, and other terms. Key details include indemnification of the laboratory and government for liability, a requirement for contractors to carry at least $1 million in general liability, auto, and workers' compensation insurance and name the laboratory as an additional insured. Contractors must also comply with all applicable environment, safety, and health regulations, and submit job safety analyses for laboratory review and approval depending on risk level. The document specifies recordkeeping, reporting, and other compliance responsibilities for off-site contractors working at the laboratory.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ANL-366-O (October 21, 2022)

WORK BY CONTRACTORS OFF THE ARGONNE SITE

SUPPLEMENTAL CONDITIONS

1. APPROVAL TO PROCEED

____ This contract is designated low risk/moderate risk. The contractor shall not commence in-person work under this contract unless and until the contractor receives approval to proceed from the Technical Representative.

___This contract is designated high risk. The contractor shall not commence in-person work under this contract unless and until the contractor receives written notice to proceed issued by the Procurement Representative.

2 INDEMNITY

(a)The contractor shall indemnify and hold UChicago Argonne, LLC(Laboratory or Argonne), the University of Chicago, and the United States Government, and their directors, officers, trustees, agents, servants, and employees, jointly and severally harmless against any loss or damage (including loss or damage from any personal injuries or death of persons, and loss of or damage to property), and any expense in connection therewith (including expenses of litigation, together with attorneys’ fees incident thereto) arising out of or connected with the performance of work under this contract by the contractor, its subcontractors, and their agents, representatives, servants, and employees. This requirement shall survive termination or expiration of this agreement.

(b)The contractor shall immediately notify the Laboratory of any injury or death and of any loss of or damage to property of the Laboratory or the United States Government, or any third party, and shall furnish the Laboratory with a statement concerning such injury, death, damage, or loss in such detail as the Laboratory may require.

3. INSURANCE

A. The Contractor shall have and maintain during the life of this contract the following insurance coverage, provided by an insurance carrier rated “A” or better by A.M. Best with coverage valid within the location(s) where the work is conducted.

LINE OF COVERAGE LIMITS

GENERAL LIABILITY

Commercial General Liability Occurrence basis

General Aggregate Limit Applies Per Policy

EACH OCCURRENCE $2,000,000

Expense Personal & Adv Injury General Aggregate Products – COMP/OP

AGG

$2,000,000

AUTOMOBILE LIABILITY

Any Auto

COMBINED SINGLE LIMIT $1,000,000

WORKER’S

COMPENSATION AND

EMPLOYERS’

LIABILITY

WC

STATUTORY

LIMITS

OTHER

$1,000,000

$1,000,000

$1,000,000

E.L. EACH ACCIDENT

E.L. DISEASE EA EMPLOYEE

E.L. DISEASE-POLICY LIMIT

B. All policies, excluding Worker’s Compensation, shall provide by appropriate language that UChicago Argonne, LLC, the University of Chicago and the United States Government are additional insureds; that the insurance afforded by such policies is primary insurance; and, that all rights of the insurer for contribution from other insurers of UChicago Argonne, LLC, the University of Chicago and the United States Government are waived. All of contractor’s insurers shall agree to waive rights of subrogation against the additional insureds.

C. In the event that the work authorized by this contract has been designated as “High Risk” by the

Laboratory, The Contractor agrees to deliver to the Laboratory before any work is performed hereunder, certificates of the insurance companies as to the particulars of the insurance coverage above referred to, and such certificates shall contain a provision that such insurance will not be canceled, changed or allowed to lapse in the policies except upon not less than ten (10) days prior notice thereof to the Laboratory.

4. ENVIRONMENT, SAFETY AND HEALTH

The contractor and its subcontractors shall take all reasonable precautions in the performance of the work under this contract to protect the safety and health of the Laboratory personnel, the U.S. Department of

Energy (DOE) personnel, and members of the public, as well as protection of the environment. This includes compliance with all the applicable environment, safety and health regulations and requirements, including applicable safety, security, site access, site orientation and environmental requirements of the facility at which work is performed and reporting requirements of DOE as identified by the Laboratory in writing from time to time. The regulations and requirements include Title 29 of the Code of Federal

Regulations (CFR), Labor including but not limited to part 1910 and 1926, Title 40 CFR, Protection of

Environment, and 49 CFR, Transportation as well as other applicable state, federal, and local regulations.

The requirements also include the National Fire Protection Association (NFPA) 70E, “Standard for

Electrical Safety in the Workplace.” The Laboratory shall notify the contractor, in writing, of any noncompliance with the provisions of this clause and the corrective action to be taken. After receipt of such notice, the contractor shall immediately take corrective action. In the event the contractor fails to comply with regulations and requirements of this clause, the Laboratory may, without prejudice to any other legal and contractual rights of DOE or the Laboratory, issue an order stopping all or any part of the work. The contractor shall promptly evaluate and resolve any noncompliance with applicable ES&H requirements. If the contractor fails to provide resolution or if, at any time, the contractor’s acts or failure to act causes substantial harm or an imminent danger to the environment or health and safety of employees or the public, the Laboratory Procurement Official may issue an order stopping work in whole or in part. Any stop work order issued by a Laboratory Procurement Official under this clause (or issued by the contractor to a subcontractor) shall be without prejudice to any other legal or contractual rights of the Government/Laboratory. In the event that the Laboratory Procurement Official issues a stop work order, an order authorizing the resumption of the work may be issued at the discretion of the Laboratory

Procurement Official. The contractor shall not be entitled to an extension of time or additional fee or damages by reason of, or in connection with, any work stoppage ordered in accordance with this clause.

In the event the Laboratory subsequently issues an order to the contractor to resume work, the contractor shall make no claim for an extension of time or for compensation for damages by reason of, or in connection with, such work stoppage. The contractor shall assure that all its personnel and all subcontractors are aware of and are following the contractor’s job safety analysis (JSA) as well as all regulations in this clause.

In addition to the stop work order process above, any person shall have the authority to stop work activity which is deemed to be in imminent danger of causing a fatality or serious injury by contacting technical representative or project manager as soon as possible. Such authority also rests with the corresponding host facility individuals.

a. Reporting Requirements for Incidents and Unauthorized Releases

i. All incidents and unauthorized releases to the environment involving contractors and subcontractors occurring at the site must be reported by the contractor immediately by dialing

911 and following all site-specific emergency procedures. The incident or unauthorized release must also be reported immediately to the Project Specialist, Technical Representative or Project

Manager. When this type of incident occurs or when the contractor is issued a Notice of Safety violation, the contractor shall complete an ANL-240, Incident Investigation and Analysis Report and ensure that any person and all witnesses to the incident complete an ANL-239, Incident

Description and submit these to the Project Specialist/Technical Representative or Project

Manager within 24 hours. Contractor personnel must be made available upon request by the

Laboratory for interviews or to assist in other investigation activities of the Laboratory. The types of emergencies that must be reported include but are not limited to: fire, explosion, personnel injury/illness, security incident, vehicle accident, utility failure, tornado sighting, possible contamination incident, or toxic or flammable material spill or release.

ii. The contractor is not authorized to dispose of any material at the site unless written approvals are obtained from the host facility. This includes but is not limited to the use of garbage and recycling dumpsters, the sinks in buildings, and discharges to the sewer systems.

b. Job Safety Analysis (JSA)

i. For moderate and high risk work the contractor must submit and have reviewed by the

Laboratory a JSA which details the specific hazards associated with each phase of the job as well as the mitigating actions the contractor shall take to reduce the risk of injury. Safety Data

Sheets (SDS) are to be submitted as part of this analysis. (sample JSA forms are provided below.)

ii. Specific procedures in the areas of fall protection, excavation, trenching, confined space, and hoisting and rigging may be required as job conditions dictate and as required by the host facility. Names and qualifications of competent persons as defined by OSHA must be maintained on the job site.

iii. The contractor’s ES&H representative shall provide a Job Safety Orientation to all contractor and subcontractor personnel and have it reviewed by the Laboratory prior to their starting work.

The orientation as a minimum shall include a review of the JSA, all related permits and plans and a review of the emergency numbers, egress routes and assembly points. All contractor personnel shall sign the JSA form to indicate having received the orientation.

iv. The JSA must be revised to incorporate changes made during the work. The revisions must be documented by the contractor and reviewed by the Project Specialist/Technical Representative prior to the activity taking place. All personnel affected by any revisions shall be notified and advised by the contractor.

c. Environmental Plan

To the extent required by the project scope of work, an Environmental Plan shall be prepared by the contractor and reviewed by the Technical Representative before the work can begin.

The Environmental Plan must be reviewed if any changes are made to the project work scope. If revisions are required, the Plan shall be updated by the contractor and approved by the Laboratory

Technical Representative prior to the activity taking place.

d. Contractor ES&H Representative

For high risk work the contractor shall designate and identify a competent person within its organization whose duty shall be the implementation of the contractor’s ES&H program on the work site.

The Contractor ESH Representative shall be present at all times work is being performed.

Duties include, but are not limited to: enforcing the contractor’s safety program as well as the requirements of the work site, providing job specific safety orientation, prevention of accidents, investigation of incidents/accidents, making daily inspections and reporting safety related information.

The Contractor ESH Representative must have the authority to stop work and change the operation to correct any deficiencies or to eliminate any hazards observed.

e. Environment, Safety and Health Documentation

The contractor shall possess the following documents, certificates, etc. along with any other documentation as may be required:

i. Equipment inspection documentation required by 29 CFR 1926, Subpart N must be with the contractor’s equipment including personnel lifts, cranes, augers, suspended scaffolds, winches, spreader beams, and lifting devices.

ii. If the contractor intends to administer first aid or Cardio Pulmonary Resuscitation (CPR), the contractor must comply with 29 CFR 1926, and supply a list of the names of personnel who will administer first aid or CPR, along with current certification. This list shall be part of the

JSA.

iii. Safety Data Sheets (SDSs) must be maintained by the contractor at the job site. SDSs for all products and materials brought on site shall be accessible to all workers on the job site. In addition, all SDSs must be submitted as part of the JSA

iv. Pressure vessel certificates per 29 CFR 1926.29.

v. Documentation of personnel training and/or proof of proficiency required by OSHA for confined space training, competent persons for excavations and scaffolding, and fall protection training. In addition, documentation of appropriate NFPA 70E training of all electrical workers must be submitted.

vi. The contractor shall, without additional expense to the Laboratory, be responsible for obtaining all necessary environmental licenses and permits

f. Site Access, Orientation, and Security

The contractor shall comply with all site access, site orientation, and site security requirements of the facility at which the work is performed as may be revised from time to time, i including but not limited to REAL ID requirements, pandemic controls, etc. Failure to adhere to such requirements will result in denial of contractor personnel access to the site. The Laboratory is not responsible or liable for, and contractor shall not attempt to invoice for, any delays or costs resulting from or arising out of site entry denial due to contractor’s failure to comply with this provision.

g. Equipment and Tool Inspection

All tools and equipment brought to the work site by the contractor will be inspected for compliance with OSHA and work site requirements prior to use. Tools and equipment may also be randomly inspected throughout the duration of the contract. Items found out of compliance shall be immediately removed from service, tagged out of service, and taken off site by the contractor by the end of that work shift.

h. Site Rules

The following acts or conduct are prohibited at the work site. Violations will result in disciplinary action. Contractor is responsible for communicating these rules to its personnel and subcontractors.

The Laboratory or site host may add additional rules at any time.

i. Possession of weapons, firearms, ammunition, explosives or any other apparatus or material hazardous to the public or property.

ii. Possession or illegal use of controlled substances or intoxicants or being under their influence.

iii. Behavior inconsistent with Argonne’s Code of Conduct, available at this website.

iv. Stealing, misuse or destruction of Government or host facility property.

v. Violation of site traffic and parking regulations. Possession of a valid and appropriate driver’s license is required to drive on-site.

vi. Using host facilities such as the cafeteria and washrooms while wearing extremely dirty or contaminated shoes or clothes.

i. Work Site Safety Requirements https://www.anl.gov/argonne-code-of-business-ethics-and-conduct

The following requirements must be implemented on the job site and included in the contractor’s

JSA as appropriate. The Laboratory may add additional requirements at any time. The list is not intended to be exhaustive and specific hazards are to be addressed in the JSA.

i. The contractor shall conduct work through the use of on-site permits as required by the site at which work is to be performed. Such permits include work entry, energized electrical work, open flame, confined space entry, digging, concrete coring, using powder actuated tools, moving Government or host property and removing asbestos.

All contractor personnel performing work for the Laboratory, both on and off site, are responsible for complying with the “Employer Payment for Personal Protective Equipment –Final Rule” issued by OSHA. The Laboratory is not responsible for the provision of nor payment for PPE required by or issued to workers other than direct Laboratory employees, temporary and permanent.

ii. Contractor personnel shall wear safety glasses with rigid side shields as needed in the work area unless a higher level of eye protection is required for special hazards. All eye protection must meet the requirement of 29 CFR 1926.102. Safety glasses must be American National Standards

Institute (ANSI) approved and be marked with the ANSI marking “Z87.1” designation.

iii. Hard hats shall be worn at all times in the work area as required by the JSA. Hard hats shall meet the ANSI Z89.1 standard as defined by 29 CFR 1926.100 and bear the “Z89-.1” designation.

High voltage exposure work requires hard hats shall meet ANSI Z89.2 standards and bear the

“Z89.2” designation.

iv. All personnel shall wear clothing suitable for the work and weather conditions. The minimum shall be short sleeve (1.4 length) shirt, long trousers, and sturdy over-the-ankle work boots providing ankle protection. In addition, any work that presents a hazard to the feet or toes requires the use of steel toes or metatarsal guards.

v. Ground fault circuit interrupters must be provided for electric hand tools and portable generators.

The assured equipment grounding program is not an acceptable alternative.

vi. All vehicles and mobile powered equipment, except automobiles and pickup trucks, must have backup alarms.

vii. Personnel lifts must be equipped with audible motion alarms for movement in any direction.

All lifts must be equipped with a safety foot pedal for operation movement.

viii. If required by the equipment manufacturer, roll-over protection structures shall be provided.

Any modifications to lifting and hoisting equipment must be approved by the equipment manufacture.

ix. Emergency egress routes must be kept clear at all times, including doors, corridors, work site, and staging areas.

x. No alarms, safety devices, etc. shall be disabled without approval of the work site officials.

(a)Lockout/tag-out procedures shall be enforced. Contractor personnel must be trained in lockout/tagout prior to participating in lockout/tagout of hazardous energy sources and working on lockout/tagout systems or equipment. Contractors must verify that the energy source is de-energized before starting work on the system.

(b)Fire watches shall be maintained during and for a minimum of thirty minutes after burning, welding, or other fire or spark generating work is completed. A “Multi-purpose” Class A-B-C dry chemical fire extinguisher, ten pound (minimum) with a pressure gauge, and current inspection (within last 12 months) shall be within the work area.

(c) Metal ladders are prohibited.

xi. The contractor’s competent person performing the daily inspections required by OSHA, such as trench and excavation, ladder, and scaffold inspections shall document each inspection. Such documentation shall be signed and include the date, time, and conditions found. Documentation shall be available for review for the duration of the project.

j. Respiratory Protection

If personnel are required to wear respirators, the contractor must have a written respiratory protection program.

Prior to using a respiratory protection device, such as dust/mist masks, including those made of paper, half face air purifying respirators, full face air purifying respirators, any atmosphere supplying respirator, the contractor shall have:

1. Medical certification records as required by 29 CFR 1910 and 1926

2. Training records which document that the employee was trained in and has mastered the training subjects in ANSI Z88.2-1992, Section 7.2.

3. Fit test records that document the employee was fit tested by a competent fit tester with reliable testing equipment according to testing requirement of ANSI Z88.2-1980, Section 6.11.

k. Intoxicants.

Contractor and subcontractor personnel are prohibited from possessing, using, consuming, selling, manufacturing, or distributing illicit controlled substances or alcoholic beverages under any of the following conditions: while operating vehicles during work performance, during working hours, on Laboratory premises, or on any other host facility premises during the performance of the work. Illicit controlled substances include drugs that are not legally obtainable, drugs that are legally obtainable but have been illegally obtained, and prescription drugs that are being used for other than prescribed purposes. Please note that although some states (including Illinois) allow medical marijuana prescriptions or recreational usage of marijuana, federal laws and regulations do not acknowledge marijuana prescriptions or allow recreational usage. Accordingly, marijuana, even if it is medically prescribed or is used recreationally in a state that allows this, remains an illicit controlled substance under these terms and conditions and federal law. The personal property of contractor and subcontractor personnel is subject to reasonable lawful search with or without notice when justified by circumstances or workplace conditions. The

Laboratory intends that any search undertaken for drugs will not be casual, routine, or random, but will occur only when sufficient corroborating evidence exists as justification. If contractor or subcontractor personnel substance abuse presents a threat to the health, safety, or welfare of the employee, other employees, or the public; to

Laboratory, public, or private property; or to Argonne’s security interests, the individual may be disqualified from site access.

FAR/DEAR Clauses

The clauses below that reference Federal Acquisition Regulations (FAR) and Department of Energy

Acquisition Regulations (DEAR) citations are based on such clauses with modifications to identify appropriate parties and are not quoted verbatim from such regulations. The clause dates provided are for the most recent versions of the clause current as of the contract issuance date.

Definitions: As used herein, “Argonne National Laboratory,” “Argonne,” “ANL” and “Laboratory” are used interchangeably to mean Argonne National Laboratory, operated by UChicago Argonne, LLC, acting under

Prime Contract No. DE-A02-06CH11357 between UChicago Argonne, LLC and the Government for the operation of Argonne National Laboratory. “Government” means the United States of America and includes the United States Department of Energy (“DOE”) or any duly authorized representative thereof. “Laboratory

Procurement Official” means the person identified in the body of the agreement as the authorized contact for the Contractor.

Contractor shall flow down these clauses to the extent necessary to ensure compliance with contract requirements or as otherwise indicated within the clause.

DEAR 970.5204-3 ACCESS TO AND OWNERSHIP OF RECORDS (OCT 2014)(DEVIATION)(MAY 2015)

(a) Government-owned records. Except as provided in paragraph (b) of this clause, all records acquired or generated by the contractor in its performance of this contract, including records series described within the contract as

Privacy Act systems of records, shall be the property of the Government and shall be maintained in accordance with 36 Code of Federal Regulations (CFR), Chapter XII, -- Subchapter B, “Records Management.” The contractor shall ensure records classified as Privacy Act system of records are maintained in accordance with

FAR 52.224.2 “Privacy Act.”

(b) Contractor-owned records. The following records are considered the property of the contractor and are not within the scope of paragraph (a) of this clause.

1. Employment-related records (such as worker’s compensation files; employee relations records, records on salary and employee benefits; drug testing records, labor negotiation records; records on ethics, employee concerns; records generated during the course of responding to allegations of research misconduct; records generated during other employee related investigations conducted under an expectation of confidentiality;

employee assistance program records; and personnel and medical/health-related records and similar files), and non-employee patient medical/health-related records, except those records described by the contract as being operated and maintained by the contractor in Privacy Act system of records.

2. Confidential contractor financial information, internal corporate governance records and correspondence between the contractor and other segments of the contractor located away from the DOE facility (that is, the contractor's corporate headquarters);

3. Records relating to any procurement action by the contractor, except for records that under 48 CFR

970.5232‑3 are described as the property of the Government; and

4. Legal records, including legal opinions, litigation files, and documents covered by the attorney-client and attorney work product privileges; and

5. The following categories of records maintained pursuant to the technology transfer clause of this contract:

a. Executed license agreements, including exhibits or appendices containing information on royalties, royalty rates, other financial information, or commercialization plans, and all related documents, notes and correspondence.

b. The contractor's protected Cooperative Research and Development Agreement (CRADA) information and appendices to a CRADA that contain licensing terms and conditions, or royalty or royalty rate information.

c. Patent, copyright, mask work, and trademark application files and related contractor invention disclosures, documents and correspondence, where the contractor has elected rights or has permission to assert rights and has not relinquished such rights or turned such rights over to the

Government.

(c) Contract completion or termination. Upon contract completion or termination, the contractor shall ensure final disposition of all Government-owned records to a Federal Record Center, the National Archives and Records

Administration, to a successor contractor, its designee, or other destinations, as directed by the Contracting

Officer. Upon the request of the Government, the contractor shall provide either the original contractor-owned records or copies of the records identified in paragraph (b) of this clause, to DOE or its designees, including successor contractors. Upon delivery, title to such records shall vest in DOE or its designees, and such records shall be protected in accordance with applicable federal laws (including the Privacy Act) as appropriate. If the contractor chooses to provide its original contractor-owned records to the Government or its designee, the contractor shall retain future rights to access and copy such records as needed.

(d) Inspection, copying, and audit of records. All records acquired or generated by the contractor under this contract in the possession of the contractor, including those described at paragraph (b) of this clause, shall be subject to inspection, copying, and audit by the Government or its designees at all reasonable times, and the contractor shall afford the Government or its designees reasonable facilities for such inspection, copying, and audit;

provided, however, that upon request by the Contracting Officer, the contractor shall deliver such records to a location specified by the Contracting Officer for inspection, copying, and audit. The Government or its designees shall use such records in accordance with applicable federal laws (including the Privacy Act), as appropriate.

(e) Applicability. This clause applies to all records created, received and maintained by the contractor without regard to the date or origination of such records including all records acquired from a predecessor contractor.

(f) Records maintenance and retention. Contractor shall create, maintain, safeguard, and disposition records in accordance with 36 Code of Federal Regulations (CFR), Chapter XII, -- Subchapter B, “Records Management” and the National Archives and Records Administration (NARA)-approved Records Disposition Schedules.

Records retention standards are applicable for all classes of records, whether or not the records are owned by the Government or the contractor. The Government may waive application of the NARA-approved Records

Disposition Schedules, if, upon termination or completion of the contract, the Government exercises its right under paragraph (c) of this clause to obtain copies of records described in paragraph (b) and delivery of records described in paragraph (a) of this clause.

(g) Subcontracts

The contractor shall include the requirements of this clause in all subcontracts that contain the Radiation

Protection and Nuclear Criticality clause at 952.223-72, or whenever an onsite subcontract scope of work

(i) could result in potential exposure to: A) radioactive materials; B) beryllium; or C) asbestos or (ii) involves a risk associated with chronic or acute exposure to toxic chemicals or substances or other hazardous materials that can cause adverse health impacts, in accordance with 10 CFR part 851. In determining its flow-down responsibilities, the contractor shall include the requirements of this clause in all onsite subcontracts where the scope of work is performed in: (A) Radiological Areas and/or

Radioactive Materials Areas (as defined at 10 CFR 835.2); (B) areas where beryllium concentrations exceed or can reasonably be expected to exceed action levels specified in 10 CFR 850; (C) an Asbestos

Regulated area (as defined at 29 CFR 1926.1101 or

29 CFR 1910.1001); or (D) a workplace where hazard prevention and abatement processes are implemented in compliance with 10 CFR 851.21 to specifically control potential exposure to toxic chemicals or substances or other hazardous materials that can cause long term health impacts.

DEAR 952.223-72 RADIATION PROTECTION AND NUCLEAR CRITICALITY (APR1984)

The Contractor shall take all reasonable precautions in the performance of work under this contract to protect the safety and health of employees and of members of the public against the hazards of ionizing radiation and radioactive materials and shall comply with all applicable radiation protection and nuclear criticality safety standards and requirements (including reporting requirements) of DOE. The Contractor shall submit a management program and implementation plan to the Contracting Officer for review and approval within30 days after the effective date of this contract or modification. In the event that the Contractor fails to comply with said standards and requirements of DOE, the Contracting Officer may, without prejudice to any other legal or contractual rights of DOE, issue an order stopping all or any part of the work. Thereafter, a start order for resumption of the work may be issued at the discretion of the Contracting Officer. The Contractor shall make no claim for an extension of time or for compensation or damages by reason of or in connection with such work stoppage.

FAR 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)

a. The Contractor shall comply with agency personal identity verification procedures identified in the contract that implement Homeland Security Presidential Directive-12 (HSPD-12), Office of

Management and Budget (OMB) guidance M-05-24, and Federal Information Processing

Standards Publication (FIPS PUB) Number 201.

b. The Contractor shall account for all forms of Government-provided identification issued to the

Contractor employees in connection with performance under this contract. The Contractor shall return such identification to the issuing agency at the earliest of any of the following, unless otherwise determined by the Government;

1. When no longer needed for contract performance.

2. Upon completion of the Contractor employee’s employment.

3. Upon contract completion or termination.

c. The Laboratory Procurement Official may delay final payment under a contract if the Contractor fails to comply with these requirements.

d. The Contractor shall insert the substance of clause, including this paragraph (d), in all subcontracts when the subcontractor’s employees are required to have routine physical access to a Federally-controlled facility and/or routine access to a Federally- controlled information system. It shall be the responsibility of the prime Contractor to return such identification to the issuing agency in accordance with the terms set forth in paragraph (b) of this section, unless otherwise approved in writing by the Laboratory Procurement Official.

Job Safety Analysis Forms

Fill out one of the forms below that apply

ANL-209COS – Off-Site Construction Job Safety Analysis

ANL-209HOS – Off-Site High Risk Job Safety Analysis

ANL-209MOS – Off-Site Moderate Risk Job Safety Analysis

ANL-209LOS – Off-Site Low Risk Job Safety Analysis https://anl.box.com/s/v34p6wkjhqsx2rglic8qt393epc61lzk https://anl.box.com/s/s6c6n0jautfmmt6touq8nhqx0ka63o1l https://anl.box.com/s/mdnww5pi7k91dl5aq14pgue0pyy0wn6x https://anl.box.com/s/6l9fw9wn4dhwh6xuckohvdxwfdjgu3hk

File details come from the government source that posted it. Updated .