Pre-Proposal Meeting Presentation- Tower Removal_Final_Answers.pdf
PDF 1 MB Posted
- Attached to
- Tower Removal (Pueblo, Colorado)
- Solicitation number
- 3-B176-Q-00903-00
- Issued by
-
Department of Energy Office of Science
About this file
This presentation outlines the requirements for a federal contract to remove five communication towers at Pueblo Chemical Depot in Colorado. The contractor will remove two 100-foot guyed towers, three 30-foot self-supporting towers, and associated concrete foundations. Tower sections and other materials must be recycled or disposed of properly. Each work site must be returned to its natural condition.
The proposal submission is due November 13, 2023. Award of the contract is anticipated on November 22, 2023, with all work to be completed by January 19, 2024. The proposal must include technical and price proposals, forms ANL-70 and ANL-70B, pricing justification, certificate of insurance, and completed safety plans. Contractors must be registered in SAM.gov and follow all environmental, safety, and health requirements outlined in the presentation, which include developing activity hazard analyses and safety plans. The Department of Energy Office of Science is the contracting agency for this opportunity.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PROPOSAL
MEETING
Tower Removal Pueblo Chemical Depot (PCD) - Pueblo, Colorado Request for Proposal (RFQ) No. 3-B176-Q-00903-00 November 6, 2023
1:00-1:30 PM CDT
Microsoft Teams
PMO-IS Project Manager (PM): Stephen Tschopp OCF-PRO Procurement Specialist (PS): Molly Murtaugh ESH Safety Representative: Martin Flores
INTRODUCTIONS (PS)
▪ ANL-Procurement
▪ ANL-Project Management Team
▪ ANL-Safety Representative(s)
▪ ANL-Customer(s)
▪ Contractors and Subcontractors
EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS (PS)
The Pre-Proposal Meeting is for information purposes only. Oral explanations or instructions made prior to award of a contract are not binding. Changes resulting from the Pre-Proposal Meeting and/or Site Visit are official only if issued through an Amendment to the Request for Proposal (RFP).
To the extent that there are any inconsistencies between the information provided in this presentation and the requirements in the RFP Materials, the RFP Materials shall govern.
BASE SCOPE OF WORK
Please refer to the Statement of Work document provided in the RFP.
In general, the following scope of work will be performed.
1. Removal of (2) 100 ft guyed towers and (3) 30 ft self supporting towers
2. Removal of concrete (base and anchors) and fill holes with sandy loam
3. Haul away materials (steel should be placed in recycling dumpster at PCD)
4. Leave each of the tower sites in a clean condition, returned to natural condition
5. Remove camera mounted to railing at 100ft level on water tower
View looking up 100 foot towerBase of 100 foot tower
ENVIRONMENT, SAFETY & HEALTH REQUIREMENTS (ESH)
▪ PCD Safety Requirements
– Federal, State and Local Regulations
– Code of Federal Regulations (CFR’s)
• 29 CFR 1926 (OSHA Construction Standards)
• 29 CFR 1910 (OSHA General Industry Standards)
– Federal Communications Commission (FCC)
– National Environmental Policy Act (NEPA)
– Federal Aviation Administration (FAA)
– Telecommunications Industry Association (TIA)
– National Fire Protection Association (NFPA)
▪ Satisfy PCD safety and documentation requirements
– Submit a dig permit PCD-Form 385-21-4 (e)(R) July 2017
– Submit the following (all contained in the Site-Specific Safety Plan)
• Safety Site Plan
• Accident Prevention Plan
• Scope of Work
• Job Safety Analysis
• Documented training or certifications.
• Activity Hazard Analysis - Must define activity being performed, sequence of work, specific hazards, control measures
▪ Satisfy ANL safety and documentation requirements
▪ Prepare ANL-209HOS with assistance from ANL ESH and Tech Rep.
▪ Prepare Site Specific Safety Plan that includes:
– Scope of Work
– Personnel
– Work Plan
– Communications
– Task Hazard Analysis
– Written Safety Procedures, including but not limited to:
• PPE
• Hazard Communications
• Excavations including shoring requirement if needed
• Fall Protection and fall rescue plan
• Lift plan
– Tower rescue plan (Including High Angle rescue)
– Basic rules and safety regulations
– Safety survey form
– List of Safety Data Sheets
– Personnel credentials and certificates
• Crane Operator License
• Rigging Competent Person
• Signal Person Trianing
• Climber and Rescue Training
• Competent Climber
• Excavation Competent Person
• Hoisting and Rigging
• OSHA 30 hr construction
• CPR/AED/First Aid
• Silica Competent Person
Detailed
▪ Tower Removal
– Crane Requirements
• Lift Plan
• Operator License
• Signal Person Training
• Rigging Competent Person
• Contractor will need Climber and Rescue Training
• Argonne Crane form may be able to be used.
• Argonne Required 3rd Party Certification of Crane within 1 year.
• PCD requires Weight Load Test
– Also pertains to all lifting equipment below the hook (slings, chains, etc.)
– Safety Oversight
• Contractor safety personnel in conjunction with
Argonne representatives
▪ Excavation
– Excavation Requirements
• Excavation Competent Person
• Current inspection
• Obtain Dig Permit from PCD
• Silica Competent person
• Silica plan
– Safety Oversight
• Contractor safety personnel in conjunction with
Argonne representatives
• Dig Permit needed.
– Need to locate cables.
– Will be conducted by Department of
Public Works.
– This may take anywhere from one day to two weeks.
• Task Removal of concrete foundations for the five towers, including below-grade anchors
• Fill-in and grading of excavated areas to return the area to its original condition.
TEMPORARY SERVICES (PM)
▪ Temporary utilities, facilities and environmental protection will be determined by PCD and must be accepted and understood before proceeding with work.
SEQUENCE OF CONSTRUCTION / MILESTONE DATES /
SUBMITTAL OF SCHEDULE (PM)
EVENT DATE
Request for Clarification Accepted Until 11/07/2023
Request for Proposal Submittals 11/13/2023
Award of Contract (Anticipated) 11/22/2023
Completion of Contract (or sooner) 1/19/2024
PROPOSAL PACKAGE (PS)
Your Proposal must include the following:
If able to provide the requested services under the strict requirements stated in the Statement of Work, please submit a proposal, providing the below:
▪ TECHNICAL PROPOSAL
▪ PRICE PROPOSAL
▪ ANL-70 Request for Quotation
▪ ANL-70B Representations and Certifications
▪ Occupation of laborer performing the work (service professional, general technician, etc.) and accompanying CBA (if applicable)
▪ Price justification stated in ANL-70 RFQ
▪ Certificate of Insurance
▪ Written acceptance of the technical requirements listed in the Statement of Work, “Tower Removal,” dated 10/31/2023
▪ Completed and Returned Corporate Safety Plan
▪ Completed and Returned Contractor Information Safety Questionnaire
CONTRACTOR REQUIREMENTS
▪ Contractor must be registered ACTIVE in SAM.gov.
Questions?
Questions / Answers
Is there any badging/training required to be onsite?
Answer: A drivers license is required, PCD is limiting this contract to US citizens. Argonne will provide escort for the contractors while onsite. PCD does not require any training.
Will there be a site visit for this opportunity? Or, can we schedule a site visit?
Answer: Unfortunately, due to depot closures and the timing of the submittal it is not feasible to organize a site visit. This week the depot will be closed on Thursday for Veterans Day and is normally closed Friday – Sunday.
What is the length of the tower sections?
Answer: All towers were built with 10ft Rohn 55G sections. A base section or plate was embedded in concrete.
What is the size of the concrete?
Answer: The bases of the 100ft towers are 3’x3’, the depth is unknown. The guy anchors are estimated at 3’x3’x3’ and are a few feet below grade. The base of the 30ft towers are 6’x’6, it is unknown if this is just a wider pad on the base or if this size goes the depth of the embedded base. Photos of these and misc. concrete to be removed are shown in later slides.
Water Tower questions?
Answer: The water tower appears to be in good condition and well maintained. It has a ladder with a safety climb and an anti-climb section near the ground. The tower is in the chemical block, but now that chemicals have been destroyed the security is reduced. The gate to the chemical block is open during normal work hours. The camera is planned to be re-used, with an estimated value of $250k. Two cameras weighting about 50lb each are bolted together. The mount may weigh an additional estimated 100lb.
The conduit and electrical wires for the camera can be left in place.
Additional photos in later slides.
Camera and mount Water tower and ladder
Anti-climb at ladder base Top of ladder
30ft tower Base of 30ft tower – 6’x6’
Detail shot of base of 30ft tower Looking up 30ft tower – 10ft sections visible
Base of 100ft tower 3’x3’ Base plate of 100ft tower
Elevator rails and section break of 100ft tower 100ft tower
Poles to be removes at tower #2 concrete at base of poles
Misc concrete at tower #2
Misc concrete at tower #2 Misc concrete at tower #2, This pad a few inches thick
| Default Section |
| Slide 1: PRE-PROPOSAL MEETING |
| Slide 2: INTRODUCTIONS (PS) |
| Slide 3: EXPLANATION OR INTERPRETATION OF RFP DOCUMENTS (PS) |
| Slide 4: BASE SCOPE OF WORK |
| Slide 5: BASE SCOPE OF WORK |
| Slide 6: BASE SCOPE OF WORK |
| Slide 7: ENVIRONMENT, SAFETY & HEALTH REQUIREMENTS (ESH) |
| Slide 8: ENVIRONMENT, SAFETY & HEALTH REQUIREMENTS (ESH) |
| Slide 9: ENVIRONMENT, SAFETY & HEALTH REQUIREMENTS (ESH) Detailed |
| Slide 10: TEMPORARY SERVICES (PM) |
| Slide 11: SEQUENCE OF CONSTRUCTION / MILESTONE DATES / SUBMITTAL OF SCHEDULE (PM) |
| Untitled Section |
| Slide 12: PROPOSAL PACKAGE (PS) |
| Slide 13 |
| Slide 14 |
| Slide 15 |
| Slide 16 |