About this file

This document is a NOAA Marine Operations Center Standard Specification (MOC-300-3) detailing general requirements for electrical and electronic work on marine vessels. The specification provides comprehensive guidelines for contractors performing electrical and electronic system installations, repairs, and modifications, with specific requirements including:

Key technical requirements mandate that all work must comply with IEEE and U.S. Coast Guard electrical standards, using best marine and shipbuilding practices. Contractors must ensure all materials are marine-service suitable, match existing equipment's original characteristics, use low-smoke cabling, properly replace or repair any disturbed components, securely fasten electronic racks, maintain original paint/finish, extend electrical cabling through junction boxes, identify and label all cables, and assign manufacturer warranties to the government. The specification concludes with a quality assurance provision requiring that all disturbed and installed devices must be fully operational upon work completion.

View the file

Other files

File Type Posted
ATTACHMENT IV Updated v3 - Pricing Schedule (1).pdf PDF
ATTACHMENT IV Updated v3 - Pricing Schedule (1).xlsx XLSX spreadsheet
625-6634893J_Doors Hatches Windows and Airports_102475074.pdf PDF
Federon Drawings (1).pdf PDF
ABS Approved drawing.png PNG image
T1657912 Doors and Hatches RL_102474204.pdf PDF
TJ-311-05 Engine Ships Service Generator Series 60.pdf PDF
634-6634945B Deck Covering Schedule.pdf PDF
Thomas Jefferson_FY2026 Dockside Repair Package Rev A_2025JUN27_Signed.pdf PDF
TJ_FY2026 DS_ Fwd Crane Hose Inventory.pdf PDF
TJ-573-01-1_Fwd_Crane_Hydraulic_Pump_SPI.pdf PDF
TJ_FY2026 DS_ Aft Crane Hose Inventory.pdf PDF
ATTACHMENT IV Updated - Pricing Schedule.pdf PDF
625-6634817E WT Door Hydraulic System Arrangement and Details.pdf PDF
525-6634754E Fills Vents Soundings Arrngmnt Details.pdf PDF
501-6634830 Piping Module No 2.pdf PDF
TJ-583-6634804B Rescue Boat Davit Hydr Sys.pdf PDF
TJ Trim Stability Booklet Rev F.docx DOCX document
601-6634920 Joiner Arrangement Lower Deck and Flat.pdf PDF
NOAA Standard Specification MOC-631-2D Coatings for Steel Surfaces.pdf PDF
TJ-152-002B Deck Extension Structure Grating Replacement.pdf PDF
TJ-583-03A Davit Hydrographic Survey Launch (HSL).pdf PDF
TJ-551-002A_Compressed Air System Piping Diagram Modification (As Built).pdf PDF
504-6634727A Clock System Wiring.pdf PDF
320-6634677 Cableway Routing and Penetrations - redline.pdf PDF
TJ-524-001 Sea Chest Cross-Over Piping.pdf PDF
TJ_NONE_TJ-320-100_RevNO REVISION_Sht1 THRU 3_N_A_ELECTRICAL REMOVALS MODIFICATIONS INCIDENTAL TO BRIDGE NAVIGATION SYSTEMS (1).pdf PDF
TJ-202-010rA_EDG.pdf PDF
TJ-582-002A New Transom Mooring Chock Inst.pdf PDF
TJ-593-007 SEWAGE TANK AERATION SYSTEM INSTALLATION_124644075.pdf PDF
TJ Memo 835-003_-_Fixed Ballast Installation FEA Memo.docx DOCX document
551-6634801_Rev E Compressed Air Sys Diag.pdf PDF
622-6634895 Machinery Space Floor Plates and Grating.pdf PDF
TJ-551-003C SSDG UPGRADES COMPRESSED AIR MODS.pdf PDF
185-001-NEW PLTF INCID SEWAGE AERATION SYSTEM_124647688.pdf PDF
101-6634870 Structural Module 11_124642565.pdf PDF
TJ-170-6634883-F.pdf PDF
TJ_85_TJ-085-002_RevJ_BOOKLET OF GENERAL PLANS.pdf PDF
601-6634921 Joiner Arrangement Main Deck.pdf PDF
085-6980295E TJ Tank Capacities Soundings.pdf PDF
TJ-583-6634886H BOAT HANDLING STOWAGE.pdf PDF
TJ-835-003_-_Fixed Ballast Installation FEA Memo_122914139.pdf PDF
512-6634856_HVAC Arr Details FCSLE Deck Fr 19-50.pdf PDF
261-6634755D Fuel Oil Service Diagram.pdf PDF
TJ-432-001 Data Phone Arrangement.pdf PDF
NOAA Standard Specification MOC-573-2 Overhaul Repair of Hydraulic Cylinders.pdf PDF
TJ-551-004 Whistle Comp Air System Arrangement Details.pdf PDF
TJ-101-001_-_Fixed Ballast Installation_122913467.pdf PDF
514-3275003-11 REV A AC PIPING INSTL MN DK.pdf PDF
NOAA Standard Specification 505-1B_Valve Overhaul and Tests.pdf PDF
Show 40 more

Latest 50 of 164 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOC-300-3

September 2000

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

MARINE OPERATIONS CENTER

STANDARD SPECIFICATION MOC-300-3

GENERAL REQUIREMENTS FOR ELECTRICAL/ELECTRONIC ITEMS

1. SCOPE. This specification provides general requirements for work performed on electrical and electronic systems.

2. REFERENCES.

2.1 IEEE STD 45-1988, Recommended Practice for Electric

Installations on Shipboard (series)

2.2 U. S. Coast Guard 46 CFR 110 through 113, “Subchapter J - Electrical Engineering”

3. REQUIREMENTS.

3.1 The contractor shall accomplish all work in these

specifications in accordance with the requirements of References

2.1 and 2.2, and using the best marine and shipbuilding practices.

3.2 The quality of all materials provided by the contractor

shall be in accordance with References 2.1 and 2.2, suitable for marine service, and have the same shape, color, and finish as the existing or damaged materials when they were new.

3.3 All new cabling shall be low smoke and sized for the cable’s intended use.

3.4 All machinery, piping, cabling, ducts, insulation, paint

work, deck tile, or any other article removed, disturbed, or damaged in the process of accomplishing the work required by these specifications shall be replaced, renewed, or repaired.

All paneling removed shall be replaced, including any required alterations. Paneling damaged by the contractor shall be renewed equal to the original when new. All flanges and joints broken or loosened shall be properly remade using new gaskets of the proper size and material.

3.5 All electronic racks installed shall be securely fastened to overhead and deck structural or steel members to prevent movement.

3.6 Any disturbed painted or varnished surfaces shall be

cleaned, painted, and/or varnished with original type and color of paint or varnish.

MOC-300-3

September 2000

3.7 Any extension of electrical cabling shall be through a

junction box. Any removal of electrical cabling shall be to the nearest junction box.

3.8 All electrical junction boxes, receptacles, hangers, and

miscellaneous electrical fittings shall be in accordance with References 2.1 and 2.2.

3.9 All electrical cabling installed by the contractor shall be run behind paneling in existing cableways and shall be securely banded to the hangers. If existing cableways are not available, new cableways shall be established.

3.10 All electrical cabling installed by the contractor shall be identified at each end with embossed metal tags. Where cables are marked within a junction or terminal box, nonconductive labels shall be used. The contractor shall number cabling with a marking system similar to that used on the ship.

3.11 All manufacturer's or supplier's standard warranties on

equipment installed on the ship shall be assigned in writing by the contractor to the Government.

3.12 Three copies all manufacturer's technical manuals, prints, and drawings shall be delivered to the COTR. Spare parts and surplus installation materials shall be delivered to the COTR.

4. QUALITY ASSURANCE.

4.1 All items disturbed and all devices used, repaired, altered, furnished, or installed by the contractor shall be demonstrated to be fully operational upon completion of work.

END OF SPECIFICATION