NOAA Standard Specification MOC-573-2 Overhaul Repair of Hydraulic Cylinders.pdf

PDF 20 KB Posted

Attached to
Drawings and Reference Materials for RFP 1305M225R0034 - NOAA Ship Thomas Jefferson FY26 Dockside Repair Services.
Solicitation number
1305M225R0034
Issued by

About this file

This document is a National Oceanic and Atmospheric Administration (NOAA) Marine Operation Center Standard Specification for the overhaul and repair of hydraulic cylinders. The specification outlines a detailed process for removing, inspecting, and reinstalling hydraulic cylinders, which includes disconnecting and capping hydraulic lines, transporting the cylinder to a repair facility, and performing a comprehensive overhaul.

Key requirements include completely disassembling the cylinder, cleaning all parts, preparing external surfaces, and reassembling using new seals, gaskets, and fittings. The specification mandates a thorough quality assurance process, including component inspection, bench testing at system working pressure, and cycling the cylinder through a minimum of four operational evolutions. The contractor must provide a condition report detailing inspection results and recommendations for restoring the cylinder to manufacturer specifications. The document is specifically focused on maintaining the operational integrity of hydraulic systems in marine environments.

View the file

Other files

File Type Posted
ATTACHMENT IV Updated v3 - Pricing Schedule (1).pdf PDF
ATTACHMENT IV Updated v3 - Pricing Schedule (1).xlsx XLSX spreadsheet
625-6634893J_Doors Hatches Windows and Airports_102475074.pdf PDF
Federon Drawings (1).pdf PDF
ABS Approved drawing.png PNG image
T1657912 Doors and Hatches RL_102474204.pdf PDF
TJ-311-05 Engine Ships Service Generator Series 60.pdf PDF
634-6634945B Deck Covering Schedule.pdf PDF
Thomas Jefferson_FY2026 Dockside Repair Package Rev A_2025JUN27_Signed.pdf PDF
TJ_FY2026 DS_ Fwd Crane Hose Inventory.pdf PDF
TJ-573-01-1_Fwd_Crane_Hydraulic_Pump_SPI.pdf PDF
TJ_FY2026 DS_ Aft Crane Hose Inventory.pdf PDF
ATTACHMENT IV Updated - Pricing Schedule.pdf PDF
625-6634817E WT Door Hydraulic System Arrangement and Details.pdf PDF
525-6634754E Fills Vents Soundings Arrngmnt Details.pdf PDF
501-6634830 Piping Module No 2.pdf PDF
TJ-583-6634804B Rescue Boat Davit Hydr Sys.pdf PDF
TJ Trim Stability Booklet Rev F.docx DOCX document
601-6634920 Joiner Arrangement Lower Deck and Flat.pdf PDF
NOAA Standard Specifications MOC-300-3_General Requirements for Electrical_Electronic Items.pdf PDF
NOAA Standard Specification MOC-631-2D Coatings for Steel Surfaces.pdf PDF
TJ-152-002B Deck Extension Structure Grating Replacement.pdf PDF
TJ-583-03A Davit Hydrographic Survey Launch (HSL).pdf PDF
TJ-551-002A_Compressed Air System Piping Diagram Modification (As Built).pdf PDF
504-6634727A Clock System Wiring.pdf PDF
320-6634677 Cableway Routing and Penetrations - redline.pdf PDF
TJ-524-001 Sea Chest Cross-Over Piping.pdf PDF
TJ_NONE_TJ-320-100_RevNO REVISION_Sht1 THRU 3_N_A_ELECTRICAL REMOVALS MODIFICATIONS INCIDENTAL TO BRIDGE NAVIGATION SYSTEMS (1).pdf PDF
TJ-202-010rA_EDG.pdf PDF
TJ-582-002A New Transom Mooring Chock Inst.pdf PDF
TJ-593-007 SEWAGE TANK AERATION SYSTEM INSTALLATION_124644075.pdf PDF
TJ Memo 835-003_-_Fixed Ballast Installation FEA Memo.docx DOCX document
551-6634801_Rev E Compressed Air Sys Diag.pdf PDF
622-6634895 Machinery Space Floor Plates and Grating.pdf PDF
TJ-551-003C SSDG UPGRADES COMPRESSED AIR MODS.pdf PDF
185-001-NEW PLTF INCID SEWAGE AERATION SYSTEM_124647688.pdf PDF
101-6634870 Structural Module 11_124642565.pdf PDF
TJ-170-6634883-F.pdf PDF
TJ_85_TJ-085-002_RevJ_BOOKLET OF GENERAL PLANS.pdf PDF
601-6634921 Joiner Arrangement Main Deck.pdf PDF
085-6980295E TJ Tank Capacities Soundings.pdf PDF
TJ-583-6634886H BOAT HANDLING STOWAGE.pdf PDF
TJ-835-003_-_Fixed Ballast Installation FEA Memo_122914139.pdf PDF
512-6634856_HVAC Arr Details FCSLE Deck Fr 19-50.pdf PDF
261-6634755D Fuel Oil Service Diagram.pdf PDF
TJ-432-001 Data Phone Arrangement.pdf PDF
TJ-551-004 Whistle Comp Air System Arrangement Details.pdf PDF
TJ-101-001_-_Fixed Ballast Installation_122913467.pdf PDF
514-3275003-11 REV A AC PIPING INSTL MN DK.pdf PDF
NOAA Standard Specification 505-1B_Valve Overhaul and Tests.pdf PDF
Show 40 more

Latest 50 of 164 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOC-573-2

September 2000

National Oceanic and Atmospheric Administration Marine Operation Center

Standard Specification MOC-573-2

OVERHAUL/REPAIR OF HYDRAULIC CYLINDERS

1. SCOPE: This specification provides the minimum requirements for the overhaul and/or repair of hydraulic cylinders.

2. REFERENCES

None

3. REQUIREMENTS

3.1 Tag out system controllers and actuators to preclude

inadvertent operation and secure the movable member to prevent movement while cylinder is removed.

3.1.1 Disconnect and cap hydraulic lines from the cylinder.

Ensure containment is provided to prevent spillage of oil.

Hydraulic lines and inlet/outlet ports shall be capped or plugged with threaded fittings to prevent leakage or contamination of the system.

3.1.2 Remove the cylinder from the ship and transport to

repair facility.

3.2 Perform the following work on the removed cylinder:

3.2.1 Completely disassemble the cylinder and clean all

parts.

3.2.2 Prepare and preserve the external painted surfaces in

accordance with the identified painting specification or as original.

3.2.3 Reassemble the cylinder under clean conditions using

new "O" rings, seals, gaskets, packing, and piston rings.

Materials used shall meet or exceed original manufacturers specifications. During reassembly lubricate the above with a product equal to Hilton's Hyper-Lube, that is compatible with the system fluid.

3.2.4 Provide and install new nuts, washers, bolts, studs and inlet and outlet fittings.

3.3 Reinstall the cylinder in its original location.

MOC-573-2

September 2000

3.4 Top off hydraulic reservoir to full mark and purge all air from the system taking care to contain any fluid bled off.

3.5 Remove tag outs.

4. QUALITY ASSURANCE

4.1 After disassembly, inspect all components for trueness of bore and rod, wear, damage, corrosion or pitting. Provide a Condition Report detailing the inspection results, contractor's corrective action recommendations, and list of additional parts, material and labor not covered by this specification, required to restore the cylinder to the manufacturers specifications.

4.2 After reassembly, bench test the assembly at system working pressure to prove smoothness of operation and tightness of sealing surfaces.

4.3 Cycle the cylinder through a minimum of four evolutions to demonstrate operation and tightness of all disturbed fittings and connections. Upon satisfactory demonstration of operation and tightness apply "Denso tape" to all connections.

END OF SPECIFICATION