NOAA Standard Specification AMC-505-1B_Valve Overhaul and Tests.pdf

PDF 27 KB Posted

Attached to
MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS Federal contract opportunity
Solicitation number
1305M226Q0100REF
Issued by
Department of Commerce National Oceanic and Atmospheric Administration

About this file

This is a Standard Specification document for valve overhaul and testing services for the National Oceanic and Atmospheric Administration (NOAA) Atlantic Marine Center, issued in August 1995 (superseding the September 1990 version AMC-505-1A).

The specification establishes general requirements for overhauling and testing valves on NOAA ships and boats. Contractors must remove specified valves to a suitable machine shop for overhaul unless welded ends prevent removal or other specifications apply, in which case in-place overhaul is acceptable. Standard overhaul procedures include complete disassembly with matchmarking, thorough cleaning to bright metal, stem straightening to within 0.002 inch total indicator runout with 32 RMS finish on packing surfaces, visual inspection of all parts and fasteners, and cleaning and truing of gasket mating surfaces. Contact fit requirements vary by valve type: globe valves require 360-degree continuous contact with bluing transfer lines not exceeding 1/16-inch width; gate valves require 360-degree continuous contact with transfer lines not exceeding 3/16-inch width in the lower 50-percent of seating surface; plug valves require minimum 80-percent plug-to-bore surface contact; and swing-check valves require 360-degree continuous disc-to-seat contact. All gaskets, fasteners, rubber seals, and non-metallic seats must be renewed, with specific packing requirements for different valve types per MIL-P-24503, DOD-P-24583, and MIL-P-24396 Type B standards.

Additional requirements address sea valve fastener materials (nickel-copper preferred with condition reporting required), interior steel valve coating with epoxy primer, waster and spool piece removal and inspection, and special handling for transducer sea chest valves. Hydrostatic testing must use clean water at 150-percent of maximum operating pressure (minimum 50 psig), with no leakage allowed in open position tests. Seat leakage limits are specified by valve type and diameter. Quality assurance requires preliminary inspections and tests by the Contractor before COTR witnessing of final bluing contact inspection and acceptance hydrostatic tests. Any valve failing seat leakage testing must be renewed or reworked and retested until acceptance.

View the file

Other files for this federal contract opportunity

Other files attached to MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS, newest first.
File Type Posted
TJ-573-01 Cranes Deck and Boom O M.pdf PDF
TJ_FY2027 DD_Fire System Inventory_Fixed Semi-Cylinders.pdf PDF
NOAA Standard Specification MOC-167-1 Refurbishment of Water Tight Closures.pdf PDF
NOAA Standard Specification MOC-100-1A_Abs Load Line Survey.pdf PDF
48026A-GI INDUSTRIAL-NOAA T JEFFERSON-POTBD_UTT.pdf PDF
1102-35 - Safe Use of Rigging Equipment (public).docx DOCX document
NF 57-07-12 - DryDock-UWILD Inspection Checklist (public).pdf PDF
Steyr Motors Marine Engines Manual.pdf PDF
TJ-233-03 EMD Engine 12-645F7B.pdf PDF
TJ-311-03 EDG Alternator.pdf PDF
Capstan_SA-1128 Manual for SA1014.pdf PDF
436-6634707 Machinery Alarm and Monitoring System Dk Pln - redline.pdf PDF
528-6634786E Plumbing and Deck Drains Arrangement and Details_130709483.pdf PDF
512-6634856_HVAC Arr and Details FCSLE Deck Fr 19-50.pdf PDF
TJ-079-03E Trim and Stability Booklet_101947795.pdf PDF
525-6634754E Fills Vents and Soundings Arrngmnt and Details.pdf PDF
TJ-528-009A - Grey Water and Sewage Modifications.pdf PDF
612-6634889D Lifelines Handrails and Stanchions.pdf PDF
TJ-611-6634891F DECK FITTINGS ARRANGEMENT and DETAILS.pdf PDF
163-6634821_Seachest Details.pdf PDF
243-6634740_Propeller Shafting Arrangement and Details.pdf PDF
TJ-582-002A New Transom Mooring Chock Inst.pdf PDF
636-6634911 Acoustic Tile Installation Arr.pdf PDF
601-6634921 Joiner Arrangement Main Deck.pdf PDF
320-6634691 Cable Wtrtight Penetrations - redline.pdf PDF
TJ_985_985-6634639_RevP_Sht1 THRU 3_ABS_FIRE CONTROL PLAN.pdf PDF
259-6634767 Diesel Engine Exhaust Arrangement.pdf PDF
514-3275003-12_91762335.pdf PDF
512-6634850F HVAC ARRNGMNT ENGRM_124644191.pdf PDF
TJ-583-022A Platform and Grating Mods.pdf PDF
101-6634867 Structural Module 8.pdf PDF
512-3275003-7 HVAC MODS 01 LVL AND ABV REV B.pdf PDF
801-6634641_Table of Offsets.pdf PDF
101-6634866_Structural Module Assembly No 7.pdf PDF
TJ-529-001A Cross Flooding Piping Installation.pdf PDF
TJ-562-001A Rudder Arrangment and Details_102457373.pdf PDF
562-6634741D Rudder Arrangement and Details.pdf PDF
073-6634629_Resilient and Dim Mounting List.pdf PDF
101-6634864 Structural Module 5.pdf PDF
259-6634766 Engine Exhaust System.pdf PDF
TJ-437-004 TLI Electrical Modifications.pdf PDF
TJ_FY2027 DD_Fire System Inventorya.pdf PDF
TJ_FY2027 DD_Fire System Inventory_Portables.pdf PDF
NOAA Standard Specification AMC-240-1 Propulsion Shafts and Propellers.pdf PDF
NOAA Standard Specification MOC-000-1G_General_Requirements for Ship Repair Work on NOAA_Ships.pdf PDF
NOAA Standard Specification 000-2D Temporary-Services-Contractor-Facility.pdf PDF
NOAA Standard Specification AMC-233-1A Overhaul of Diesel Engines.pdf PDF
NOAA Standard Specification AMC-583-1B General Requirements for Life Raft Inspections.pdf PDF
NOAA Standard Specification AMC-635-2 Thermal Insulation for Compartments.pdf PDF
NOAA Standard Specification AMC-505-2_Hydrostatic Pressure Tests.pdf PDF
Show all 50

MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMC-505-1B

AUGUST 1995

SUPERSEDING

AMC-505-1A

SEPTEMBER 1990

NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION (NOAA)

ATLANTIC MARINE CENTER

STANDARD SPECIFICATION AMC-505-1B

VALVE OVERHAUL AND TEST

1. SCOPE. This specification contains the general requirements for overhaul and test of valves on and for NOAA ships and boats.

2. REFERENCES.

None

3. REQUIREMENTS.

3.1 Standard Overhaul. Overhaul all specified valves as

follows:

3.1.1 Except for valves which have welded ends preventing

removal without cutting the welds, or unless otherwise specified in the detail specification or other applicable procurement document, remove all specified valves from the ship or boat to a suitable machine shop for overhaul and tests. Specified valves which are not removed from the ship or boat shall be overhauled in place. See paragraph 3.2 for special requirements for sea valve removals.

3.1.2 Tag each valve prior to removing from the ship or

boat.

3.1.3 Completely disassemble each valve. Matchmark valve

parts. Thoroughly clean bonnets, stems, discs, gates, globes, seats, bodies, and other metal parts to bright metal.

3.1.4 Deleted.

3.1.5 Clean and chase all valve stem threads. Check stems

for straightness. Straighten stems to within 0.002 inch total indicator runout (TIR). Polish stems to a 32 Root-Mean-Square (RMS) finish in way of packing surface and remove all raised edges.

3.1.6 Visually inspect all parts, including all fasteners, for deterioration and other defects. Clean, dress, and true gasket mating surfaces.

3.1.7 Check the disc-to-seat, globe-to-seat, and plug-to-

bore contact fits using the bluing transfer method. Machine, grind, lap, spot-in, and recheck contact fits as necessary to obtain the following contacts:

a. Globe, globe angle, and globe stop-check valves shall have a 360-degree continuous globe-to-seat contact with a bluing transfer line not exceeding 1/16-inch width.

b. Gate valves shall have a 360-degree continuous gate-to-seat contact with a bluing transfer line which does not exceed 3/16-inch width. The transfer line shall appear within the lower 50-percent of the gate seating surface at the top and bottom of the gate.

c. Plug valves shall have a minimum 80-percent plug-to-bore surface contact, evenly distributed over 100-percent of the area.

d. Swing-check valves shall have a 360-degree continuous disc-to-seat contact.

3.1.8 If unable to obtain the above specified contact fits

by machining, grinding, and lapping, renew the globes, plugs, discs, gates, and renewable seats. Contractor may, at their option and at no additional cost to the Government, renew globes, plugs, discs, gates, and renewable seats after initial inspections and before machining, grinding, or lapping the existing parts to obtain the required contact fits.

3.1.9 (Modified and relocated to section 3.2)

3.1.10 Reassemble each valve. Insure that discs, gates, and plugs are in the half-open position during reassembly to avoid damaging seats or bending stems. Renew all gaskets, fasteners, rubber seals, and non-metallic seats. In butterfly valves, renew boots, o-rings, o-ring fasteners, and teflon bushings. Renew valve stem packing in feed water, condensate, and steam valves with packing conforming to MIL-P-24503 and DOD- P-24583. Renew valve stem packing in all other valves with packing conforming to MIL-P-24396, Type B.

3.1.11 Prior to disassembling and overhauling a valve, the

Contractor may, at their option and at no additional cost to the Government, renew the valve with an identical valve. If this option is exercised, the new valve must be tested and meet the same acceptance criteria as prescribed herein for overhauled valves. If a valve is determined after disassembly to be nonrepairable, the Government will negotiate an equitable cost adjustment, limited to the difference between the cost of the new valve and the costs which would have been incurred had the valve been overhauled. For valves of 3-inch IPS size and below, the cost adjustment will be limited to the costs incurred associated with disassembling the valves.

3.2 Additional Sea Valve Requirements.

3.2.1 Inspect all studs, bolts, and nuts in line and bonnet

flanges of non-ferrous sea valves to determine the material. If the fasteners are not nickel-copper (Monel), submit a Condition Report giving the actual material, condition, and recommendations.

3.2.2 Coat the interior of each steel valve, excluding

seating and polished surfaces, with the same epoxy primer used on the underwater body.

3.2.3 Remove all waster pieces and spool pieces installed

between the sea valves and the ship's hull. Thoroughly clean the waster and spool pieces, and inspect for deterioration or other defective conditions. Inspect all fasteners and submit a Condition Report same as specified above for sea valves.

3.2.4 Whenever a transducer sea chest valve is required to

be removed for overhaul, extreme care must be taken to prevent damaging the transducer assembly. Remove and reinstall the transducer assembly in accordance with the transducer manufacturer's technical manual, a copy of which will be provided by the COTR within 48 hours after requested.

3.3 Tests. After reassembling or renewing, conduct hydrostatic tests of each valve as follows:

3.3.1 All tests shall be performed using clean water as the

test medium. Unless otherwise specified, the test pressure shall be 150-percent of the maximum operating pressure of the system from which the valve was removed, but not less than 50 pounds-per-square-inch-gage (psig).

3.3.2 With the valve in the open position, test each valve

body for 10 minutes. No leakage is allowed.

3.3.3 Seat each plug and butterfly valve with hand force.

Seat all other valves using the torque values listed in the following table as the maximum allowable seating force applied to the handwheel.

Total Tangential Force Handwheel Diameter (pounds) on Rim of Handwheel

2 inches and below 90 3 inches 98 4 inches 106 5 inches 112 6 inches and greater 118 plus 3 pounds for each inch above 6, not to exceed 150 pounds.

3.3.4 Test each globe, angle globe, and globe stop-check

valve by applying test pressure in the direction tending to open the valve. Test each butterfly, gate, and plug valve by applying test pressure alternately on both sides of the disc, gate, or plug. Hold test pressure for a minimum of 3 minutes if there is no evidence of leakage. If there is evidence of leakage, hold the test pressure and measure the leakage rate.

3.3.5 Test each globe stop-check valve and swing-check

valve by applying test pressure in direction tending to close the valve (back pressure) for a minimum of 5 minutes. If leakage occurs, hold the test pressure and measure the leakage rate.

Globe stop-check valves shall be tested with stems in the open position. The test back pressure for valves having a pressure rating of 150 psig and below shall be 50 psig, and for valves having a pressure rating over 150 psig shall be 100 psig.

3.3.6 The seat leakage shall not exceed the following:

a. Check valve back pressure tests -- For valves up to and including 2 inches, the leakage rate shall not exceed 25 cc/hour/inch diameter. For valves 2-1/2 to 10 inches, the leakage rate shall not exceed 50 cc/hour/inch diameter. For valves over 10 inches, the leakage rate shall not exceed 100 cc/hour/inch diameter.

b. Soft-seated valves -- No leakage shall be permitted.

c. Metal-to-metal seated valves -- For valves less than 1 inch, the leakage rate shall not exceed 10 cc/hour. For larger valves, the leakage rate shall not exceed 10 cc/hour/inch of nominal pipe size.

3.3.7 Any valve which fails a seat leakage test shall be

renewed or overhauled and retested until an acceptable test is performed.

3.4 Reinstallation. After tests have been accepted by the COTR, reinstall each valve, using new flange gaskets.

4. QUALITY ASSURANCE.

4.1 Prior to requesting the COTR to witness the final bluing

contact inspection or the final acceptance hydrostatic tests of a valve, the Contractor shall perform preliminary inspections and tests which meet the acceptance criteria stated above.

4.2 After acceptable preliminary inspections and tests have been conducted, the Contractor shall notify the COTR and conduct final acceptance bluing contact inspection and final acceptance hydrostatic tests of each valve in the COTR's presence.

END OF SPECIFICATION