NOAA Standard Specification MOC-573-2 Overhaul Repair of Hydraulic Cylinders.pdf

PDF 20 KB Posted

Attached to
MO FY27 Thomas Jefferson Drydock REFERENCES and ATTACHMENTS
Solicitation number
1305M226Q0100REF
Issued by

About this file

This is a Standard Specification issued by the National Oceanic and Atmospheric Administration (NOAA) Marine Operation Center for the overhaul and repair of hydraulic cylinders.

The specification establishes minimum requirements for contractors performing hydraulic cylinder maintenance work on NOAA vessels. Work scope includes: tagout and securing of system controllers and actuators; disconnection and capping of hydraulic lines with containment measures; cylinder removal and transport to a repair facility; complete disassembly and cleaning of all parts; external surface preparation and preservation per identified painting specifications; reassembly under clean conditions using new O-rings, seals, gaskets, packing, piston rings, nuts, washers, bolts, studs, and inlet/outlet fittings that meet or exceed original manufacturer specifications; lubrication with a product equivalent to Hilton's Hyper-Lube compatible with system fluid; reinstallation in original location; reservoir top-off and system air purging; and tagout removal. Quality assurance requirements include post-disassembly inspection of all components for bore and rod trueness, wear, damage, corrosion, and pitting, with submission of a Condition Report detailing inspection results and corrective action recommendations. Post-reassembly requirements mandate bench testing at system working pressure to verify smooth operation and seal tightness, followed by minimum four-cycle operational demonstrations to verify fitting and connection tightness, with Denso tape applied to all connections upon successful completion.

View the file

Other files

File Type Posted
04950 - 04950SS 50MM TO 200MM.jpg JPG image
04004139a.pdf PDF
0400382d.PDF PDF
VDT-TM-91534-35 Technical User Manual Davit HN-9003 cover sheet.pdf PDF
TJ-573-01 Cranes Deck and Boom O M.pdf PDF
TJ-573-01 Cranes Deck and Boom O M_weight chart.pdf PDF
TJ-573-01-1_Fwd Crane - hydraulic pump supplemental parts info.pdf PDF
0400427a.pdf PDF
3.1 CERTIFICATE.pdf PDF
0400426f.pdf PDF
0400426.PDF PDF
VDT-IM-91534-35 User manual for installation of davit HN-9003 POEA-133M-15CN-0139MOA2-11(14) rev.00..pdf PDF
602-6634905_Hull Label Plates.pdf PDF
TJ-241-01 Reduction Gear Main Propulstion RS2719S (1).pdf PDF
DirecTV Configuration.pdf PDF
Davit Hose Inventory.xlsx XLSX spreadsheet
TJ-562-001A Rudder Arrangment and Details_102457373.pdf PDF
NOAA Standard Specification MOC-100-1A_Abs Load Line Survey.pdf PDF
Steyr Motors Marine Engines Manual.pdf PDF
Valeport Skin Valve Drawing.pdf PDF
Quincy QR-25 Series Model 350.pdf PDF
Register of Lifting Appliances_fillable.pdf PDF
320-6634679_Cableway Arrangement and Details.pdf PDF
TJ-528-010A - Waste Water Tank Structural Modifications_102021653.pdf PDF
801-6634641_Table of Offsets.pdf PDF
TJ-311-05 Engine Ship_s Service Generator Series 60.pdf PDF
624-6634931 Joiner Door Schedule.pdf PDF
501-6634831_Piping Module No 3.pdf PDF
259-6634766 Engine Exhaust System.pdf PDF
48026A-GI INDUSTRIAL-NOAA T JEFFERSON-POTBD_UTT.pdf PDF
TJ-583-023C Davit Hydraulic Modifications.pdf PDF
625-6634893J_Doors Hatches Windows and Airports.pdf PDF
TJ-436-001 Fire Detection and Alarm System.pdf PDF
eCFR __ 46 CFR Part 160 Subpart 160.151 -- Inflatable Liferafts (SOLAS).pdf PDF
NOAA Standard Specification AMC-634-1A_Deck Coverings.pdf PDF
501-6634830 Piping Module No 2.pdf PDF
NAVSEA Standard Item 009-32_Cleaning and Painting Requirements.pdf PDF
ABS Marine Vessel Rules.pdf PDF
TJ-233-01 Detroit Diesel 6V92.pdf PDF
TJ-651-02 Grease interceptor Gaylord Hood.pdf PDF
TJ-568-004D Bow Thruster Installation.pdf PDF
101-6634869 Structural Module 10.pdf PDF
633-67635_Installation Drawing ICCP Equipment.pdf PDF
TJ-635-6634624_Insulation Layout and Details.pdf PDF
512-6634841_ HVAC Diagram.pdf PDF
261-6634755D Fuel Oil Service Diagram.pdf PDF
436-6634706 Rev C_ACCU elementary wiring diagram - redline.pdf PDF
TJ-311-01 EDG Engine.pdf PDF
NF 57-07-12 - DryDock-UWILD Inspection Checklist (public).pdf PDF
TJ-233-03 EMD Engine 12-645F7B.pdf PDF
Show 40 more

Latest 50 of 214 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOC-573-2

September 2000

National Oceanic and Atmospheric Administration Marine Operation Center

Standard Specification MOC-573-2

OVERHAUL/REPAIR OF HYDRAULIC CYLINDERS

1. SCOPE: This specification provides the minimum requirements for the overhaul and/or repair of hydraulic cylinders.

2. REFERENCES

None

3. REQUIREMENTS

3.1 Tag out system controllers and actuators to preclude

inadvertent operation and secure the movable member to prevent movement while cylinder is removed.

3.1.1 Disconnect and cap hydraulic lines from the cylinder.

Ensure containment is provided to prevent spillage of oil.

Hydraulic lines and inlet/outlet ports shall be capped or plugged with threaded fittings to prevent leakage or contamination of the system.

3.1.2 Remove the cylinder from the ship and transport to

repair facility.

3.2 Perform the following work on the removed cylinder:

3.2.1 Completely disassemble the cylinder and clean all

parts.

3.2.2 Prepare and preserve the external painted surfaces in

accordance with the identified painting specification or as original.

3.2.3 Reassemble the cylinder under clean conditions using

new "O" rings, seals, gaskets, packing, and piston rings.

Materials used shall meet or exceed original manufacturers specifications. During reassembly lubricate the above with a product equal to Hilton's Hyper-Lube, that is compatible with the system fluid.

3.2.4 Provide and install new nuts, washers, bolts, studs and inlet and outlet fittings.

3.3 Reinstall the cylinder in its original location.

MOC-573-2

September 2000

3.4 Top off hydraulic reservoir to full mark and purge all air from the system taking care to contain any fluid bled off.

3.5 Remove tag outs.

4. QUALITY ASSURANCE

4.1 After disassembly, inspect all components for trueness of bore and rod, wear, damage, corrosion or pitting. Provide a Condition Report detailing the inspection results, contractor's corrective action recommendations, and list of additional parts, material and labor not covered by this specification, required to restore the cylinder to the manufacturers specifications.

4.2 After reassembly, bench test the assembly at system working pressure to prove smoothness of operation and tightness of sealing surfaces.

4.3 Cycle the cylinder through a minimum of four evolutions to demonstrate operation and tightness of all disturbed fittings and connections. Upon satisfactory demonstration of operation and tightness apply "Denso tape" to all connections.

END OF SPECIFICATION