Attachment C_533 Instructions

View the file

Other files

File Type Posted
SF30_Amendment_03.pdf PDF
SAMDA_RFP_Q A_Set_3.pdf PDF
Enclosure_4.pdf PDF
RFP_NNG15543215_Rev2_Page119.pdf PDF
SF30_Amd_4.pdf PDF
SAMDA_RFP_Q A_Set_2.pdf PDF
Exhibits_3-5_(GPM)Rev2.pdf PDF
RFP_NNG15543215_Rev2_Page130.pdf PDF
Exhibits_3-5_(GPM)Rev1.pdf PDF
SF30_Amendment_01.pdf PDF
SAMDA_RFP_Q A_Set_1.pdf PDF
ENCLOSURE_4_DL_Position_Description_Rev1.pdf PDF
RFP_NNG15543215_Rev1Pg94.pdf PDF
SF30_Amendment_02.pdf PDF
ENCLOSURE_3_HISTORICAL_DL_RATE_DATA.pdf PDF
ENCLOSURE_1_QAP.pdf PDF
ATTACHMENT_G_-_IT_SECURITY_MANAGEMENT_PLAN.pdf PDF
RFP_NNG15543215R_SF33.pdf PDF
ATTACHMENT_K_-_PIV.pdf PDF
EXHIBITS_1-2_(CORE).pdf PDF
RFP_NNG15543215R_CoverLetter.pdf PDF
ENCLOSURE_2_RTO.pdf PDF
EXHIBITS_3-5_(GPM).pdf PDF
ATTACHMENT_A_-_SOW.pdf PDF
ATTACHMENT_E_-_SAFETY_ _HEALTH_PLAN.pdf PDF
ATTACHMENT_B_-_RATE_MATRICES.pdf PDF
RFP_NNG15543215R.pdf PDF
ATTACHMENT_H_-_OCI.pdf PDF
ATTACHMENT_D_-_CONTRACT_HISTORICAL_DATA.pdf PDF
ATTACHMENT_F_-_IT_SECURITY_APPLICABLE_DOCS.pdf PDF
ENCLOSURE_4_DL_Position_Description.pdf PDF
EXHBITS_6-13_(CORE_ _GPM).pdf PDF
EXHIBIT_14_PAST_PERFORMANCE_QUESTIONNAIRE.pdf PDF
ATTACHMENT_I_-_GFP.pdf PDF
ATTACHMENT_J_-_IAGP.pdf PDF
ENCLOSURE_3_HISTORICAL_DL_RATE_DATA.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT C

FINANCIAL MANAGEMENT REPORTING

REQUIREMENTS

RFP NNG15543215R

CONTRACT TBD

Contract TBD Attachment C

(06/2014) 2

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

For the Core baseline portion of the contract, the Contractor’s 533 Reports shall contain a summary of total Core baseline contract costs at the total contract level.

An individual 533 Report shall be provided for each Task Order at the total Task Order level, in addition to a cumulative 533 Report summarizing all Task Orders issued.

The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2E, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the

Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total

Cost amount shown in the current month for each individual Task Order and at the Core baseline total contract level. (For example, the Total Estimated Cost amount shown for

June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the

Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the tenth

(10th) working day following the close of the contractors' monthly accounting period.

The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

(06/2014) 3

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

Prime Direct Labor Hours - Onsite

(List applicable labor categories)

Prime Direct Labor Hours – Offsite

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours – Onsite

Subcontractor A Direct Labor Hours – Offsite

Subcontractor B Direct Labor Hours – Onsite

Subcontractor B Direct Labor Hours – Offsite

Subcontractor C Direct Labor Hours – Onsite

Subcontractor C Direct Labor Hours – Offsite

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours:

Total Prime and Subcontractors Hours – Onsite

Total Prime and Subcontractors Hours – Offsite

Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Prime Direct Labor Costs - Onsite

(06/2014) 4

Prime Direct Labor Costs – Offsite

Total Prime Direct Labor Costs

5. Prime Overhead Expenses:

Onsite Overhead

Offsite Overhead

Total Prime Overhead

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost

10. Fixed Fee

11. Total Cost-Plus-Fixed-Fee (CPFF)