(N)NAVFAC RFI Form.docx

DOCX document 25 KB Posted

Attached to
B564 INSTALL CWP EVAPORATOR
Solicitation number
ACQR6101754
Issued by

About this file

This document is a Request for Information (RFI) form from the Naval Facilities Engineering Command (NAVFAC) related to a specific contract opportunity for installing a Controlled Pure Water (CPW) Evaporator at Naval Submarine Base New London in Groton, CT. The solicitation (ACQR6101754) is limited to pre-qualified contractors from the MACC ML-C00068 list, which includes seven specific companies such as Benaka Inc., CCI Utility and Construction Services, and Ocean Construction Services.

The project requires comprehensive installation services including a new mezzanine, stairs, railings, bollards, transfer pump, concrete housekeeping pad, piping, supports, exhaust stack, roof penetration, fire protection, electrical systems, and associated work within Building 564's Enclosed Storage Area. The RFI form provides a standardized mechanism for contractors to request additional information, with a clear disclaimer that the form does not authorize proceeding with work and that any changed conditions must be reported to the Contracting Officer within 20 calendar days.

View the file

Other files

File Type Posted
RFP_ACQR6101754_R1.pdf PDF
(E)DBA CT20250024 4.25.25.pdf PDF
Amendment 00002.pdf PDF
Amendment 00001.pdf PDF
RFP_ACQR6101754.pdf PDF
(C)Engineering Calculation.pdf PDF
(F)UFGS 01 31 23.13 20.pdf PDF
(I)2016-R-0149.pdf PDF
(L)Base Requirements.pdf PDF
(O)PriceProposalForm.docx DOCX document
(B)Drawings.pdf PDF
(G)CERT-141.pdf PDF
(H)Guide to Sales and Use Taxes.pdf PDF
(J)Map to B135.pdf PDF
(K)Base Map.pdf PDF
(A)B564 CPW EVAP Specifications.pdf PDF
(D)NEPA.pdf PDF
(E)DBA CT20250024.pdf PDF
(M)Base Access Pass Request.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NUMBER:

REQUEST FOR INFORMATION
RFI NUMBER:

CONTRACT TITLE:

PRIME CONTRACTOR:

SUBCONTRACTOR/SUPPLIER:

SUBJECT/TITLE OF RFI:

DRAWING(S):

DETAIL(S):

SPECIFICATION:

CPM ACTIVITY NUMBER:

COST EFFECT: INCREASE: |_| DECREASE: |_| NONE: |_|

INFORMATION REQUESTED & RECOMMENDED SOLUTION:

Date Response Required By: Date: Signature:

From:

To: Field Office Name Code

RECOMMENDATION:

Date: Signature:

From: Field Office Name To: Prime Contractor

REPLY:

Date: Signature:

The RFI system is intended to provide an efficient mechanism for responding to contractor’s request for information ONLY. This system DOES NOT authorize the contractor to proceed with work - to do so, the contractor proceeds at his own risk. If the contractor considers the RFI response a changed condition, written notice to the Contracting Officer is required within 20 calendar days.

DISTRIBUTION: Original to File via REICC |_| PL/DM |_| ET |_| A/E |_| PC # via AROICC/CONTRACT OFFICER

File details come from the government source that posted it. Updated .