| CONSTRUCTION COST ESTIMATE WORKSHEET | ||||||||||||||
| COST SUMMARY | ||||||||||||||
| A/E ESTIMATE | GOV'T EST. | $0 | CONTRACTOR EST. | CONTRACT TYPE | ||||||||||
| A/E FIRM | PROJECT OFFICER: | Ben Buck | CONTRACTOR | (BID) | (DOC) | |||||||||
| A/E PROJECT MGR. | TEAM # | 1 | PROJECT MGR. | (I.O.) | (8A) | |||||||||
| DATE: | DATE: | SMALL PURCH. | ||||||||||||
| BUDGET | CONCEPT | 40% | 70% | 90% | FINAL | |||||||||
| PROJECT TITLE: | ||||||||||||||
| LOCATION | ||||||||||||||
| WORK REQUEST NO.: | ||||||||||||||
| PRIME CONTRACTOR | SUB CONTRACTOR | |||||||||||||
| CSI DIVISION | MATERIAL | LABOR | MATERIAL | LABOR | TOTAL | |||||||||
| 1.0 GENERAL REQUIREMENTS | 0 | |||||||||||||
| 2.0 SITE WORK | 0 | |||||||||||||
| 3.0 CONCRETE | 0 | |||||||||||||
| 4.0 MASONRY | 0 | |||||||||||||
| 5.0 METAL | 0 | |||||||||||||
| 6.0 CARPENTRY | 0 | |||||||||||||
| 7.0 MOISTURE & THERMAL PROTECTION | 0 | |||||||||||||
| 8.0 DOORS, WINDOWS, GLASS | 0 | |||||||||||||
| 9.0 FINISHES | 0 | |||||||||||||
| 10.0 SPECIALTIES | 0 | |||||||||||||
| 11.0 EQUIPMENT | 0 | |||||||||||||
| 12.0 FURNISHING | 0 | |||||||||||||
| 13.0 SEPECIAL CONSTRUCTION | 0 | |||||||||||||
| 14.0 CONVEYING SYSTEMS | 0 | |||||||||||||
| 15.0 MECHANICAL | 0 | |||||||||||||
| 16.0 ELECTRICAL | 0 | |||||||||||||
| SUB - TOTAL | 0 | 0 | 0 | 0 | 0 | |||||||||
| LABOR BURDEN | 0 | 0 | 0 | |||||||||||
| FICA | ||||||||||||||
| FUTA | ||||||||||||||
| SUTA | ||||||||||||||
| WORKMAN'S COMP | ||||||||||||||
| MATERIAL TAX | 0 | 0 | 0 | |||||||||||
| SUBTOTAL | 0 | 0 | 0 | 0 | 0 | |||||||||
| OVERHEAD (_______%) | 0 | 0 | 0 | 0 | 0 | |||||||||
| SUBTOTAL | 0 | 0 | 0 | 0 | 0 | |||||||||
| PROFIT (_____%) | 0 | 0 | 0 | 0 | 0 | |||||||||
| SUBTOTAL | 0 | 0 | 0 | 0 | 0 | |||||||||
| PRIME OVERHEAD ON SUB (______%) | 0 | 0 | 0 | |||||||||||
| SUBTOTAL | 0 | 0 | 0 | |||||||||||
| PRIME PROFIT ON SUB (______%) | 0 | 0 | 0 | |||||||||||
| SUBTOTAL | 0 | 0 | 0 | |||||||||||
| TOTAL | 0 | 0 | 0 | 0 | 0 | |||||||||
| 0 | 0 | 0 | 0 | 0 | ||||||||||
| TOTAL ESTIMATE/BID | 0 | 0 | 0 | 0 | 0 | |||||||||
| page 1 of 2 | ||||||||||||||
| CONSTRUCTION COST ESTIMATE WORKSHEET | ||||||||||||||
| CSI DIVISION WORKSHEET | ||||||||||||||
| A/E ESTIMATE | GOV'T EST. | 0 | CONTRACTOR EST. | CONTRACT TYPE | ||||||||||
| A/E FIRM | PROJECT OFFICER: | Ben Buck | CONTRACTOR | (BID) | (DOC) | |||||||||
| A/E PROJECT MGR. | TEAM # | 1 | PROJECT MGR. | (I.O.) | (8A) | |||||||||
| DATE: | DATE: | SMALL PURCH. | ||||||||||||
| BUDGET | CONCEPT | 40% | 70% | 90% | FINAL | |||||||||
| PROJECT TITLE: | 0 | |||||||||||||
| LOCATION | 0 | |||||||||||||
| WORK REQUEST NO.: | ||||||||||||||
| PRIME CONTRACTOR | SUB CONTRACTOR | |||||||||||||
| QUANTITY | MATERIAL COST | LABOR COST | MATERIAL COST | LABOR COST | ||||||||||
| ITEM DESCRIPTION (CSI DIV. ) | NO. OF | UNIT | PER | PER | PER | PER | ||||||||
| UNITS | MEASURE | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | UNIT | TOTAL | |||||
| 1.0 GENERAL REQUIREMENTS | 0 | 0 | 0 | 0 | ||||||||||
| Project Manager | 0 | 0 | 0 | 0 | ||||||||||
| Field Superintendent | 0 | 0 | 0 | 0 | ||||||||||
| Auto CAD Operator | 0 | 0 | 0 | 0 | ||||||||||
| Clerical | ||||||||||||||
| OFF-SITE Office | 0 | 0 | 0 | 0 | ||||||||||
| Storage Trailer | 0 | 0 | 0 | 0 | ||||||||||
| Utilities | 0 | 0 | 0 | 0 | ||||||||||
| Clean Up | 0 | 0 | 0 | 0 | ||||||||||
| Vehicles | 0 | 0 | 0 | 0 | ||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| Liability Insurance | 0 | 0 | 0 | 0 | ||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 2.0 SITE WORK | 0 | 0 | 0 | 0 | ||||||||||
| Manhole | 0 | 0 | 0 | 0 | ||||||||||
| Repair Street | 0 | 0 | 0 | 0 | ||||||||||
| Repair Sidewalk | 0 | 0 | 0 | 0 | ||||||||||
| Boring for 16"Stl Sleeve & 4-4"PVC Conduit | 0 | 0 | 0 | 0 | ||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| 0 | 0 | 0 | 0 | |||||||||||
| PAGE/DIVISION TOTALS | 0 | 0 | 0 | 0 | ||||||||||
| page 2 of 2 |
Sheet2
&A Page &P
Sheet3
Sheet4
Sheet5
Sheet6
Sheet7
Sheet8
Sheet9
Sheet10
Sheet11
Sheet12
Sheet13
Sheet14
Sheet15
Sheet16
File details come from the government source that posted it. Updated .