General Decision Number: DC080003 06/06/2008 DC3

Superseded General Decision Number: DC20070003

State: District of Columbia

Construction Type: Building

County: District of Columbia Statewide.

BUILDING CONSTRUCTION PROJECTS (Does not include single family homes and apartments up to and including 4 stories)

Modification Number Publication Date 0 02/08/2008 1 04/18/2008 2 05/02/2008 3 05/09/2008 4 05/30/2008 5 06/06/2008

ASBE0024-001 10/01/2007

Rates Fringes

Asbestos Worker/Heat and Frost Insulator Includes the application of all insulating materials, protective coverings, coatings and finishes to all types of mechanical systems..........$ 27.88 13.88

ASBE0024-005 10/01/2007

Rates Fringes

Fire Stop Technician.............$ 22.95 6.39

Includes the application of materials or devices within or around penetrations and openings in all rated wall or floor assemblies, in order to prevent the pasage of fire, smoke of other gases. The application includes all components involved in creating the rated barrier at perimeter slab edges and exterior cavities, the head of gypsum board or concrete walls, joints between rated wall or floor components, sealing of penetrating items and blank openings.

BRDC0001-001 04/30/2007

Rates Fringes

Bricklayer......................$ 25.90 6.19

CARP0132-006 05/01/2008

Rates Fringes

Carpenters (Including Drywall Hanging).........................$ 25.37 6.55 Piledriver.......................$ 23.87 7.10

ELEC0026-003 09/03/2007

Rates Fringes

Communication Technician.........$ 23.15 3%+6.87

SCOPE OF WORK: Includes low voltage construction, installation, maintenance and removal of teledata facilities (voice, data and video) including outside plant, telephone and data inside wire, interconnect, terminal equipment, central offices, PABX, fiber optic cable and equipment, railroad communications, micro waves, VSAT, bypass, CATV, WAN (Wide area networks), LAN (Local area networks) and ISDN (Integrated systems digital network).

WORK EXCLUDED: The installation of computer systems in industrial applications such as assembly lines, robotics and computer controller manufacturing systems. The installation of conduit and/or raceways shall be installed by Inside Wiremen. On sites where there is no Inside Wireman employed, the Teledata Technician may install raceway or conduit not greater than 10 feet. Fire alarm work is excluded on all new construction sites or wherever the fire alarm system is installed in conduit. All HVAC control work.

* ELEC0026-016 06/02/2008

Rates Fringes

Electricians (Excluding Communication-Low Voltage Wiring)..........................$ 35.55 11.42+a

a. PAID HOLIDAYS: New Year's Day, Martin Luther King Jr.'s Birthday, Inauguration Day, Memorial Day, Fourth of July, Labor Day, Veterans Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day or days designated as legal holidays by the Federal Government.

ENGI0077-009 05/01/2008

Rates Fringes

Power equipment operators:

Boom Trucks.................$ 27.57 7.17+a Cranes (35 tons and above)..$ 28.74 7.17+a Cranes (under 35 tons)......$ 28.28 7.17+a Forklifts...................$ 21.00 7.17+a Piledrivers.................$ 28.28 7.17+a

a. PAID HOLIDAYS:

New Years Day, Inaugural Day, Decoration Day, Independence Day, Labor Day, Martin Luther King's Birthday, Veterans Day, Thanksgiving Day, Friday after Thanksgiving and Christmas Day.

b. PREMIUM PAY:

Tower cranes and cranes 100-ton and over to receive $1.00 per hour premium over Group One.

IRON0005-001 06/01/2007

Rates Fringes

Ironworkers:

Structural, Ornamental and Chain Link Fence............$ 26.73 11.995

IRON0201-003 05/01/2008

Rates Fringes

Ironworker (Reinforcing).........$ 26.15 12.08

LABO0657-001 06/01/2007

Rates Fringes

Laborer:Skilled..................$ 18.81 4.29

FOOTNOTE: Potmen, power tool operator, small machine operator, concrete labor including concrete preparation, signalmen, laser beam operator, waterproofer, open caisson, test pit, underpinnig, pier hole and ditches, laggers and all work associated with lagging that is not expressly stated, strippers, operator of hand derricks, vibrator operators, pipe layers, or tile layers (tile laid on road construction projects ONLY), operators of jackhammer, paving breakers, spaders or any machine that does the same general type of work, scaffold builders, operators of towmasters, scootcretes, buggymobiles and other machines of similar character, operators of tampers and rammers and other machines that do the same general type of work, whether powered by air, electric or gasoline builders of trestle scaffolds over one tier high and sand blaster, power and chain saw operators used in clearing, installers of well points, wagon drill operators, acetylene burners and licensed powdermen.

LABO0657-002 06/01/2007

Rates Fringes

Laborers:

Mason Tenders, Brick........$ 14.14 4.29 Mortarmen, Scaffold Builders....................$ 14.90 4.29

MARB0002-002 05/01/2007

Rates Fringes

Marble & Stone Mason.............$ 31.00 11.52

INCLUDES pointing, caulking and cleaning of All types of masonry, brick, stone and cement structures; EXCEPT pointing, caulking and cleaning of exisiting masonry, brick, stone and cement (restoration work)

MARB0003-001 05/01/2007

Rates Fringes

Mosaic & Terrazzo Worker, Tile Layer Marble Mason and Tile Layer.$ 24.67 8.78 Terrazzo Worker.............$ 25.42 8.78

MARB0003-004 05/01/2007

Rates Fringes

Marble, Tile & Terrazzo Finisher.........................$ 19.84 7.90

PAIN0051-004 06/01/2007

Rates Fringes

Glaziers Contracts $2 million and under.......................$ 24.12 7.46 Contracts over $2 million...$ 26.34 7.46

PAIN0051-010 06/01/2007

Rates Fringes

Painters:

Brush, Roller, Spray and Drywall Finisher............$ 23.31 7.31

PLAS0891-003 05/01/2007

Rates Fringes

Cement Mason/Concrete Finisher...$ 26.15 6.01

PLUM0005-007 10/21/2007

Rates Fringes

Plumbers Apartment Buildings over 4 stories (except hotels), schools, colleges and speculative office buildings, strip shopping centers, churches, water coolers, room air conditioning units, appliances, packaged ice machines and light commerical refrigeration and/or air conditioning systems serving a single business in a single story building and not to exceed

5. h.p. or tons, self-contained package unit up to including 5 h.p. or tons.$ 21.54 8.33+a ALL Other Work..............$ 33.92 12.94+a

a. PAID HOLIDAYS: Labor Day, Veterans' Day, Thanksgiving Day and the day after Thanksgiving, Christmas Day, New Year's Day, Martin Luther King's Birthday, Memorial Day and the Fourth of July.

PLUM0602-006 11/01/2007

Rates Fringes

Steamfitter, Refrigeration & Air Conditioning Mechanic (Including HVAC Pipe Work).......$ 33.27 13.57+a

a. PAID HOLIDAYS:

New Year's Day, Martin Luther King's Birthday, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and the day after Thanksgiving Day and Christmas Day.

SFDC0669-001 04/01/2008

Rates Fringes

Sprinkler Fitters................$ 29.35 14.30

SHEE0100-002 07/01/2007

Rates Fringes

Sheet Metal Worker (Including HVAC Duct Work)..................$ 31.54 11.65

SUDC2000-001 04/12/2000

Rates Fringes

ASBESTOS ABATEMENT WORKER

(Removal from Floors, Ceilings, Walls and Mechanical Systems)..............$ 10.60

Laborer, Unskilled...............$ 11.83 2.23

Pointer, caulker and cleaner INCLUDES pointing, caulking and cleaning of existing masonry, brick, stone and cement structures (restoration work); EXCLUDES pointing, caulking and cleaning of new or replacement masonry, brick, stone and cement......................$ 20.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

Other files

File Type Posted
Questions Answers as of 2 July 2008.pdf PDF
Amendment Number 000004.zip ZIP file
Amendment Number 000003.zip ZIP file
SF 30 -- Amendment 000002.pdf PDF
Amendment 000001.zip ZIP file
Attachment J-11 - Past Perfomance Questionnaire.pdf PDF
Attachment J-2 Wage Rate Determination Montgomery County MD070056 dtd 05-30-2008.htm HTM file
SF 1442 —
Attachment J-13 - Guide for Construction Site Signage.pdf PDF
Section A thru M.pdf PDF
Attachment J-9 - SF 1413 - Statement of Acknowledgement .pdf PDF
Attachment J-4 Sample Indirect Cost Worksheet Two Tier.xls XLS spreadsheet
Attachment J-16 - Construction Specs.zip ZIP file
Attachment J-14 Functional Description Information Form.pdf PDF
Attachment J-2 Wage Rate Determination Frederick Co MD030009 dtd 05-16-2008.htm HTM file
Attachment J-7 - SF 25 - Performance Bond.pdf PDF
Attachment J-3 -- Sample Construction Cost Estimate.xls XLS spreadsheet
Attachment J-6 - NIH 2582 - Contractor's Release for all Contracts.pdf PDF
Attachment J-8 - SF 25A - Payment Bond.pdf PDF
Attachment J-10 -- SF LLL - Disclosure of Lobbying Activities.pdf PDF
Attachment J-15 Update of Construction Details.pdf PDF
Attachment J-11 - Past Perfomance Questionnaire.pdf PDF
Attachment J-5 -- Statement of Work - Specificarion for Seed Project or Sample Task.PDF PDF
Attachment J-1 -- PACKAGING AND DELIVERY OF PROPOSALS.pdf PDF
Attachment J-12 Standard Details and References.pdf PDF
Attachment J-2 wage Rate Determination Baltimore City MD 070001 dtd 05-23-2008.htm HTM file
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .