Newaygo Volume 2_Updated per Addendum 2.pdf

PDF 118 KB Posted

Attached to
RFP For Roofing and Parking Package
Solicitation number
RFP-NEWS-190000000321-3
Issued by
Oceana County, Michigan

About this file

This document is a comprehensive Work Category Description for a roofing and parking lot project in Newaygo, Michigan, involving The Christman Company as the Construction Manager. The project encompasses multiple work categories, including earthwork, site utilities, flat roofing, sheet metal work, and shingle roofing for what appears to be a middle school and high school facility. The scope includes complete site clearing, excavation, grading, demolition of existing roofing systems, installation of new EPDM and shingle roofing, asphalt paving, site furnishings, and associated utility work. The project requires careful coordination, adherence to specific work hours (Monday through Friday, 7am-3:30pm), and compliance with environmental and safety regulations, including asbestos and lead-based paint management.

The contract emphasizes strict requirements for waste management, site cleanup, material storage, and coordination between subcontractors. There are specific provisions for permits, inspections, utility coordination, and site-specific safety protocols. A Construction Manager's allowance of $5,000 is included for the earthwork category, and the project requires detailed unit pricing for various elements such as aggregate base, excavation, asphalt sections, and hydro seeding. The work categories must provide full-time on-site supervision, comply with all local and state regulations, and meet specific scheduling and sequencing requirements to ensure project completion within the designated timeframe.

View the file

Other files

File Type Posted
Bid Pack 5 Specifications.pdf PDF
Middle School Roof.pdf PDF
Addendum 2 Write Up.pdf PDF
Addendum 1 Write Up.pdf PDF
High School Roof.pdf PDF
HS Parking Lot.pdf PDF
The Christman Company Front End - Bid Package 5.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roofing and Parking Lot Newaygo, MI

Proposal Section Work Category Description

The Christman Company WC 00-1 WC 00 General Requirements For all Subcontractors

Work Category No. 00 – General Requirements for All Subcontractors

Work Included:

1. All permits, fees, inspections and approvals required by governing jurisdictions are included within base bid. Coordinate well in advance (at least 24 hours), required inspections and testing with the Construction Manager. This will include liaison between state and local agencies to ensure code compliance and for securing approval for the facility.

2. Excessive noise and vibration creating equipment shall be prohibited within close proximity of existing Structures/Buildings or occupied spaces. All proposed equipment scheduled for project shall be reviewed with the Construction Manager prior to delivery onsite.

3. Each WC is responsible to clean the trash and debris generated from their specific task being done. In addition, for every crew of 40 hours worked, each contractor will be required to provide 4 hours of unidentifiable clean-up at the discretion and direction of the Site Superintendent.

The Construction Manager will provide dumpsters for concrete, cardboard, wood and metals as part of the recycling program. An additional container for general debris will be provided as well. Non participation will result in the Construction Manager hiring labor force and the financial burden will be the responsibility of the noncompliant contractor in the form of a deductive change order to their contract.

See section 017419 for additional information on the Construction Waste Management Plan.

4. In order for all subcontractors to coordinate the work as it is performed the required work days and hours are required by all subcontractors. This will be the minimum hours and days required. Should a contactor need more time or days it will be prearranged with the Christman Superintendent 7 days in advance. Four day work weeks will not be allowed on this project at any time.

Standard Work Week- Monday thru Friday

Standard Work Hours-7am until 3:30pm

5. Cleanup is required on a daily basis, and/or as directed by the Construction Manager. Cleanup dunnage, shipping materials and associated materials/debris generated from installation and dispose of properly. At no time will shipping containers, crates, materials, piles of debris, tarps, boxes, etc. be left on site, un-attended and stored on site, subject to unsafe conditions (i.e. access, fire and slip hazards and wind blown debris).

6. All material stored on site must be easily moved. All small part boxes must be stored on a mobile cart.

Large objects can be stored on pallets as long as contractor provides pallet jack for movement. No ground storage will be allowed. All conduit, pipe or materials (4” diameter and smaller) inside the building must be stored on a mobile pipe rack.

7. At least two (2) weeks prior to starting on-site, meet with the Construction Manager, Architect and Engineer to discuss and resolve any issues relating to status of material procurements, site conditions, access, staging/storage requirements, safety, testing, sequencing and scheduling of work.

8. Any work that could interfere with existing owners operation, i.e. use of certain roads, parking lots, access to buildings, shall require pre-task planning with the Construction Manager and shut-down notification requests shall be prepared (72) hrs in advance of any work being scheduled. Pre-task planning shall review and discuss scheduling, coordination with Owner operations, working durations, safe practices and procedures.

9. Protect existing structures, equipment, and finishes, including new work in place, from damage during the performance of this work category. Any protection removed to facilitate other work shall be reinstalled

Proposal Section Work Category Description

The Christman Company WC 00-2 WC 00 General Requirements For all Subcontractors

/ replaced by the trade needing access.

10. Include all layout and engineering for each work category. Unless otherwise indicated in Section 00210, two control lines and one bench mark will be provided by the Construction Manager for Trade Contractor use.

11. Prior to commencing with installation, verify all field conditions and measurements and report any discrepancies to the Construction Manager.

12. Whenever possible all embeds to be furnished to other trades shall be fabricated / modified by the providing contractor with holes / tabs, etc. to allow easy for installation by the installing contractor.

13. Provide full-time on-site supervision during the performance of your work (including work performed by sub-contractors). Supervision will be responsible for coordination, scheduling, safety, manpower, and other activities necessary to achieve safety, quality and scheduling requirements set forth under this work category. Supervision shall not be removed from this project without prior written consent and approval of the Construction Manager.

14. Full compliance with all site specific rules and regulations, including (but not limited to) OSHA, State Authorities, Local Authorities, and the Construction Manager. This subcontractor shall submit, prior to performing any work on-site, a copy of their site specific safety program/manual.

15. Should Subcontractor require on-site trailer or storage units, Subcontractor shall obtain approval from the Construction Manager on size, count and where to locate, prior to delivery on-site. Subcontractor to arrange and pay for service to trailers, including (but not limited to) electrical, phone, etc.

16. For material deliveries, if traffic control is required, Subcontractor to arrange manpower accordingly and provide signage, barricading, flagman etc., necessary for the safe performance of own work and protection of the public. Staging, storage on-site, and all deliveries required to support this installation must be reviewed and approved in advance by the Construction Manager.

17. Furnish and receive all required materials and deliver FOB jobsite. All deliveries shall be closely coordinated with the Construction Manager and 72 hour advance notice shall be given prior to delivery.

Unless noted otherwise, deliveries must be coordinated to be complete with unloading during normal working hours.

18. This subcontractor will receive and handle all respective material and properly store/protect before, during and after installations. Excessive and out-of-sequence deliveries will be prohibited and subject to re-handling and removal offsite as directed by the Construction Manager.

19. Unless noted otherwise in Section 00210, furnish all hoisting, lifting, scaffolding, and handling to complete your own work.

20. Hoisting of materials and equipment over occupied areas will not be permitted, unless areas below are vacated or occupancy access is controlled during lifting. Each subcontractor will be required to notify Construction Manager seven (7) days in advance of required hoisting over occupied areas. Pre-Task planning and shut-down notifications will be required to assure minimum interruptions to Owner operations. In general, any hoisting equipment required to be used on-site must be reviewed in advance with Construction Manager for coordination of site logistics, safety procedures (including FAA approvals if required), access, lift swing areas, duration and overall activities relating to this hoisting equipment.

21. Approved O&M manuals are required at least 2 weeks prior to equipment start-up, start of warranty, and Owner training, but no later than thirty (30) days prior to substantial completion.

22. In the event of any jurisdictional or labor issues, the subcontractor assigned the work shall arrange to

Proposal Section Work Category Description

The Christman Company WC 00-3 WC 00 General Requirements For all Subcontractors complete all work as required to avoid any interruptions/continuity of work on this project at no additional cost. All labor requirements pertaining to the project will be met.

23. Cooperate fully with representatives from Architect, Engineer, Owner, Construction Manager and independent testing agency, and allow for in progress inspections, including providing access to areas of work, when required.

24. This project may require multiple phases, which will require re-mobilization. All costs for multiple phasing shall be included.

25. Each Trade Contractor shall assume full responsibility for all pre-ordered products after their arrival at this designated location. This includes transportation, storage, start-up, warranty services, and installation in accordance with the General Conditions unless otherwise specified.

26. Critical Scheduling and Sequencing of Work:

The Construction Manager shall provide overall scheduling and coordination for the entire project. All Trade Contractors shall acknowledge the Construction Manager's right to establish and set up, or subsequently modify the sequencing and scheduling of all work on this project for the earliest completion and/or benefit to the Owner. More restrictive sequencing to coordinate the Owner's on-going operations and/or for the coordination of the various trades shall be spelled out by the Work Category descriptions or as otherwise directed by the Construction Manager. All Trade Contractors agree to cooperate and alter their operations to maintain these more specified restrictions and sequences of the work.

A. Subcontractor agrees to work concurrently with other subcontractors and the Construction Manager, according to the Master Project Schedule.

B. Subcontractor shall confirm fabrication lead times, installation durations and sequencing for their Work in writing within two weeks of award, and report any discrepancies to Construction Manager.

C. Scheduling updates and proper coordination and communication with other trades shall be accomplished as follows:

Weekly sub-progress meetings

Safety meetings, BIM meetings, scheduling meetings, pre-installation meetings, etc.

27. Construction Waste Management And Disposal – Review Spec Section 017419 Construction Waste Management And Disposal

28. General Commissioning Requirements – Review Spec Section 019113 General Commissioning Requirements.

29. Indoor Air Quality Management Plan – During Construction. Comply with site specific IAQ Management Plan for this project.

30. Be advised the existing building contains asbestos. A full report is available in the bid documents. It is each contractor’s responsibility to review the report and comply with the MIOSHA standards. The owner will be responsible for all removal. If Asbestos Containing Materials are encountered, stop work and immediately report it to Christman. It is the responsibility of each subcontractor to provide 2 hour asbestos awareness training for all employees working on this project. Proof of certification will be required prior to work starting on site.

31. Be advised the existing building contains lead based paint. A full report is at The Christman Company site office. It is each contractor’s responsibility to review the report and comply with the MIOSHA standards for Lead as applicable to the scope of work. If your scope of work will require you to perform a Lead Exposure

Proposal Section Work Category Description

The Christman Company WC 00-4 WC 00 General Requirements For all Subcontractors

Assessment as indicated by the Standard, it must be coordinated with The Christman Company. Additionally, if you intend to use historical data in lieu of an Exposure Assessment, the data must be submitted to The Christman Company prior to performing the work.

It is the responsibility of each Trade Contractor, when sanding, scraping, removing, cutting, or otherwise disturbing these materials, to comply with all Federal, State, Local, and OSHA guidelines and regulations.

Waste generated by sanding, scraping or stripping paint is a hazardous material. It must be collected at the work location and legally disposed of. Ground and all areas adjacent to work zones must be protected from contamination by paint removal waste. Each Trade Contractor is also responsible for proper notification to other trades, containment, disposal of debris, clean-up, air-monitoring, etc.

32. It is noted that time is of the essence. Bidder to include all necessary overtime and plan to work weekends to meet the durations and sequence of the bid schedule. It is noted that contractors working in both buildings will need to have separate crews as needed to maintain the pace of the schedule. Any delay will result in paying for overtime of subsequent trades.

33. If any items are duplicated in two separate work categories, both contractors shall include the scope in their base bid. A future change order will be issued to remove the duplicate scope if needed.

End of Work Category No. 00

Proposal Section Work Category Description

The Christman Company Page WC 02 -1 WC 02 Earthwork

Work Category No. 02 – Earthwork and Site Utilities

Work Included:

The subcontractor shall timely perform all Earthwork and Site Utility work, as detailed below, in accordance with the contract documents (including Bidding Requirements, Proposal Section, Contract Forms, General Conditions, Supplemental Conditions, General Requirements, Addenda, etc.), including, but not limited to, the following Specification Sections and Work Scope Items. Unless otherwise noted, this contractor is responsible for all items specified in the following specifications sections:

All work categories to include Division 00 and 01.

101453 Traffic Signage

129300 Site Furnishings

311000 Site Clearing

312000 Earth Moving

321216 Asphalt Paving

329300 Plants

334100 Storm Utility Drainage Piping

Work Category Notes:

1. Demolition and clearing/grubbing of the entire site, including, but not limited to, the removal of trees, tree roots, topsoil removal, vegetation and deleterious materials as shown or specified, asphalt, concrete, hard surfaces, fences, handrails, retaining walls, posts, gates, signs, etc. Includes all labor, material, accessories, and equipment for a complete installation.

2. Provide all mass excavation, grading, compaction, backfill, berms and off-site borrowed fill to final subgrade elevations as shown or specified, including backfill required around the building foundations, foundation walls, retaining walls, sidewalks, curb and gutters, drives, asphalt paving, etc. This is to include all rough and final grading to +/- 0.1’. All unsuitable soils and materials shall not be permitted to be stockpiled and must be removed on a daily basis.

3. Coordinate and develop soil erosion plan with the Construction Manager for submission to appropriate jurisdiction. Furnish and install soil erosion control measures as shown and/or specified. Maintain soil erosion control measures during the course of this project. Remove erosion control and clean all catch basins and/or pipe as required at completion of project. All inspection logs to be copied directly to the Construction Manager and copies shall be kept within a soil erosion control manual, located within the Construction Manager’s trailer.

4. Provide all cutting, patching and repairs by a qualified person as required of existing roadways, landscape areas, paving, hardscape, etc. disturbed by this scope of work.

5. Provide all required sedimentation and water pollution control shown, specified or necessary to perform the work in this package or the work of others, including maintenance and removal upon completion and acceptance of work by the governing agency.

6. Provide all dewatering (ground and rain water) as necessary until final grade and complete and operational storm system is available. All ground water will be diverted so as not to interfere with construction or

Proposal Section Work Category Description

The Christman Company Page WC 02 -2 WC 02 Earthwork public traffic flow and the operations of the existing facility. All drainage inlets shall be protected as specified. Maintenance of dewatering system to be considered a 24 hour/7 day week assignment.

7. This subcontractor shall participate in all coordination meetings (internal and meetings with local agencies and those having jurisdiction) concerning the relocation of existing utilities so as not to impact the existing facility operations. Include temporary utilities and provisions as necessary to allow relocation of existing utilities without interruption of service to existing facilities. This contractor to provide for temporary support and protections for any existing utility or other piping encountered during performance of this work. Include verification of existing utility locations prior to excavations, and monitoring during excavation and backfill.

8. Provide all right-of way bonds, permits, etc. as required by city, county, and state agencies relative to the work within this package.

9. Prior to any imported soils entering project site, provide material analytical soils reports and documentation that material is free of contaminants/hazardous materials.

10. Clean roads and staging areas of any tracking dirt or debris generated during site clearing and excavation as necessary or as directed by the Construction Manager. Dust control and street cleaning on a regular basis as job conditions require.

11. Strip and stockpile topsoil for re-use. Re-spread topsoil to within specified tolerances, upon completion of rough grading. Large clumps of dirt and stones shall be removed from topsoil. If Topsoil is deemed unsuitable for new growth this needs to be brought to the Construction Manager’s attention before topsoil is stripped.

12. Where existing asphalt paving is removed at the entrances, provide temporary measures to ensure pavement that remains will not be damaged. Example: providing gravel at edge of pavement so save the sawcut edge.

13. Furnish and install all bituminous paving including, sealers, joint filler, etc as indicated on the drawings and specifications. Includes all labor, material, accessories, and material for a complete installation.

14. Furnish all layout and controls for this work category by a qualified surveyor. This is required.

15. Saw cut and prepare edge for patch work/new work. Complete all patching of asphalt paving to match existing conditions in surrounding streets necessary for the curb cuts at new entrances and exits.

16. Coordinate re-installation of manhole and catch basin covers prior to installation of asphalt work, including all final adjustments of manhole and catch basin castings.

17. Provide final grading and proof roll aggregate base for approval and acceptance prior to installing base course. Identify soft spots and bring to the attention of the construction manager. All repairs will be performed by this WC.

18. Provide line striping and markings for finished project; complete all cleaning and layout required for pavement markings.

19. Furnish and install all fine grading, plants, trees, stone, sub-base, topsoil, soil amendments, fertilizers, seeding, edging, and site furnishings. Includes all labor, material, accessories, and equipment for a complete installation.

20. This work category is responsible for re-establishing grass in all green areas adjacent to the work area.

21. Backfill and compact all excavations created by this work.

Proposal Section Work Category Description

The Christman Company Page WC 02 -3 WC 02 Earthwork

22. Furnish and install all drain piping, pre-fabricated assemblies, sleeves, etc.

23. Furnish, install, and grade topsoil. Include necessary preparation of the soil (plowing, disking, rototilling, additives, etc.) for planting, seeding, etc. Prior to importing material, follow specifications and obtain required approvals for topsoil, trees, etc. Provide all raking, leveling and removal of miscellaneous stones and debris necessary to obtain final grades. This contractor is responsible for the removal and legal disposal of debris.

24. Field verification of underground piping, electrical conduit, site utilities, etc., prior to digging, trenching, plowing or spading operations.

25. Any saw cutting, grinding, chipping and patching work etc. generating concrete dust, shall be approved in advance by the Construction Manager. Dust control and safety procedures will be reviewed and enforced during this activity.

Specific Notes and Details:

The following details and notes are included in this Work Category; this list is to clarify the specific items noted below and does not exclude other details or otherwise limit the scope of work for this Work Category.

1. Include hand excavation to find all underground utilities before crossing them. Any un-marked line shall be carefully excavated around so identification can be made and this contractor shall keep an accurate as-built of all lines found.

2. Install and maintain any tracking surfaces that exit the site as needed. This contractor shall sweep the road of sand / mud daily or as required by the authority having jurisdiction and the CM.

3. Remove all excavation soils from the site as needed or requested by the CM

4. During the installation of underground utilities, provide necessary protection of open cuts that meets the MIOSHA standards outlined in Part 9 – Excavation, Trenching and Shoring.

5. Provide all final grading for landscape areas.

6. This contractor shall daily inspect and provide equipment and labor to maintain the site in a smooth and well drained condition in order to prevent standing rain water. This includes grading ruts from trucks, grade damage from other contractors, and new work as it is placed. Grade away from existing structures and building to ensure proper drainage.

7. Provide equipment on site for dust control as needed or directed by the Construction Manager.

8. Compaction to percentages specified of all fills placed on site.

9. Final setting of all underground structures furnished in this contract. Prior to asphalt paving or concrete placement this work category is responsible for any readjustment to underground structures and structure manhole that are necessary to maintain the current elevations and have proper Drainage.

10. All water necessary for grading and compaction shall be brought to the site by this WC

11. Clean the existing storm sewer structures once the soil erosion materials are removed if required.

12. WC 02 is responsible for all permits and associated fees for this scope of work as required.

13. Final tie-ins of all storm/sanitary sewer mains will be the responsibility of this Work Category.

14. WC 02 to provide labor materials and all dumpsters or hauling for all site demolition.

Proposal Section Work Category Description

The Christman Company Page WC 02 -4 WC 02 Earthwork

15. Salvage and Re-install all parking lot signage (handicap signs, stop signs, directional signs, etc.)

Related Work by Others:

1. Refer to Sections 00210 and 01019 for testing requirements and responsibilities.

Allowances:

This Contractor shall include in their Base Bid a Construction Manager’s allowance of $5,000. Reference Section 01020 for specific instructions on allowances.

Unit Prices:

Unit Prices are to be complete furnished in-place operations, and include all costs, incidental materials and work, insurance, fringes, bonds, engineering, overhead and profit. Reference the Trade Contract Proposal form for unit pricing required.

Aggregate Base (CIP) $__________/CY Sand Base (CIP) $__________/CY Excavation of Unsuitable Soils $__________/CY 4” underdrain (HDPE with sock) $__________/LF Heavy Duty Asphalt Section $__________/TON Standard Duty Asphalt Section $__________/TON Hydro Seeding $__________/SY

End of Work Category No. 02

Proposal Section Work Category Description

The Christman Company Page WC 14 -1 WC 14 Roofing

Work Category No. 14 - Flat Roofing & Sheet Metal

Work Included:

The subcontractor shall timely perform all Roofing & Sheet Metal work, as detailed below, in accordance with the contract documents (including Bidding Requirements, Proposal Section, Contract Forms, General Conditions, Supplemental Conditions, General Requirements, Addenda, etc.), including, but not limited to, the following Specification Sections and Work Scope Items. Unless otherwise noted, this contractor is responsible for all items specified in the following specifications sections:

All work categories to include Division 00 and 01.

073113 Asphalt Shingles (Removed per Addendum 2)

075323 Ethylene-Propylene-Diene-Monomer (EPDM) Roofing

077100 Roof Specialties

Work Category Notes:

1. Furnish and install all roof shingles, membrane roofing, metal roofing, built-up roofing, roof insulation, roof expansion joints, roof hatches and accessories, gutters and downspouts, overflow scuppers, walkway protection, ballast, flashings, copings, gravel stops, reglets, termination bars, trim, sealants, ice and water shield, etc., indicated by the contract documents (not just limited to the roof plan) or as required for a complete installation, including labor, materials, equipment, adhesives, fasteners and accessories.

2. Include installation and removal of a perimeter fall protection system in conjunction with roofing installation. Fall Protection measures must be maintained at all times

3. Where perimeter details cannot be completed immediately, provide temporary weather protection (i.e.

extend and secure membrane over parapet walls, if required).

4. There is not a mechanical contractor or electrician on this project. Any temporary disconnecting of roof equipment must be done by a qualified subcontractor that will be hired by this WC. Prior to subcontractor being on site, The Christman Company needs to be notified.

5. Furnish all hoisting, lifting, and handling, etc. of materials as required for this W.C.

6. Provide broom cleaning of concrete and metal deck roof areas, just prior to installation of roofing systems, i.e. tracked dirt, unidentifiable debris.

7. All fire stopping, flashings, roof termination details shall be inspected and documented by Construction Manager prior to being covered up and concealed.

8. All specified warranty requirements shall be met by this W.C., including all costs of inspection and observation by manufacturer’s representatives as required.

9. Subcontractor and manufacturer’s representatives shall attend a Pre-Roofing Conference at the project site at a time determined by Owner, Architect, and the Construction Manager.

10. All materials and equipment shall be secured at all times for wind loads.

Proposal Section Work Category Description

The Christman Company Page WC 14 -2 WC 14 Roofing

Specific Notes and Details:

1. WC 14 to remove the existing roof system and accessories to facilitate the installation of a new roof.

Include all necessary temporary provisions to maintain a weather tight condition on the new and existing roof during the roofing operations. Any resulting damage from improper protection will be the responsibility of WC 14. PROTECTING THE EXISTING BUILDING FROM WATER DAMAGE IS

ESSENTIAL.

2. WC 14 to furnish and install any necessary roof blocking this is shown or not shown on the drawings that is necessary to provide a complete and warrantable roof system.

3. WC 14 to furnish dumpsters for work associated with demolition of existing roof system. This work category to provide waste recycling information to the Construction Manager for these dumpsters furnished in this work category.

4. All metal coping and coping flashing to be furnished and installed by WC 14.

5. Include all necessary flashing and roofing for completing all scuppers

6. All new Ice and Water Shield to be included in base bid for the MS roof. If existing can be salvaged a credit will be taken. Provide lineal foot price on bid form. (Moved to WC 14A per Addendum 2)

7. All clean up and restoration of landscaping, green areas, or paved surfaces along the existing building caused from removal of existing roof will be the responsibility of this WC.

8. There will be no site fence at the Middle School. It is the responsibility of this contractor to provide warning line on the ground to prevent students or staff walking in an area where roofing material could fall. (Moved to WC 14A per Addendum 2)

9. Existing roof drains will be the sole responsibility of this contractor. WC 27 will install new roof drains indicated at HS.

10. All vents called out on Middle School drawings for the shingle roof will be furnished and installed by this WC. (Moved to WC 14A per Addendum 2)

Related Work by Others:

1. Assist WC 27 with the installation of the new roof drains in order to ensure they are properly installed and integrated with the roofing system.

Allowances:

This Contractor shall include in their Base Bid a Construction Manager’s allowance of $0. Reference Section 01020 for specific instructions on allowances.

Unit Prices:

Unit Prices are to be complete furnished in-place operations, and include all costs, incidental materials and work, insurance, fringes, bonds, engineering, overhead and profit. Reference the Trade Contract Proposal form for unit pricing required.

End of Work Category No. 14

Proposal Section Work Category Description

The Christman Company Page WC 14A -1 WC 14A Shingle Roofing

Work Category No. 14A – Shingle Roofing (Added per Addendum 2)

Work Included:

The subcontractor shall timely perform all Shingle Roofing & Sheet Metal work, as detailed below, in accordance with the contract documents (including Bidding Requirements, Proposal Section, Contract Forms, General Conditions, Supplemental Conditions, General Requirements, Addenda, etc.), including, but not limited to, the following Specification Sections and Work Scope Items. Unless otherwise noted, this contractor is responsible for all items specified in the following specifications sections:

06 10 00 Rough Carpentry

07 31 13 Asphalt Shingles

07 71 00 Roof Specialties

Work Category Notes:

1. Furnish and install all roof shingles, roof insulation, roof expansion joints, gutters and downspouts, overflow scuppers, flashings, copings, gravel stops, reglets, termination bars, trim, sealants, ice and water shield, etc., indicated by the contract documents (not just limited to the roof plan) or as required for a complete installation, including labor, materials, equipment, adhesives, fasteners and accessories.

2. Include removal of perimeter fall protection system in conjunction with roofing installation.

3. Where perimeter details cannot be completed until the building skin is complete, provide preliminary weather protection (i.e. extend and secure membrane over parapet walls, if required).

4. Coordinate with mechanical contractor and steel contractor for installation of roof curbs for mechanical equipment and roof hatches.

5. Furnish all hoisting, lifting, and handling, etc. of materials as required for this W.C.

6. Provide broom cleaning of concrete and metal deck roof areas, just prior to installation of roofing systems, i.e. tracked dirt, unidentifiable debris.

7. All flashings, roof termination details shall be inspected and documented by Construction Manager prior to being covered up and concealed.

8. All specified warranty requirements shall be met by this W.C., including all costs of inspection and observation by manufacturer’s representatives as required.

9. Subcontractor and manufacturer’s representatives shall attend a Pre-Roofing Conference at the project site at a time determined by Owner, Architect, and the Construction Manager.

10. All materials and equipment shall be secured at all times for wind loads.

Specific Notes and Details:

The following details and notes are included in this Work Category; this list is to clarify the specific items noted below and does not exclude other details or otherwise limit the scope of work for this Work Category.

1. Roofer to supply and install all underlayment’s, flashings, ice and water shield, shingles, shingle vents as shown or required.

2. Roofer is responsible for all demolition of existing roof and repair of underlayment if needed.

3. The roofer is responsible for all dumpsters for their work.

Proposal Section Work Category Description

The Christman Company Page WC 14A -2 WC 14A Shingle Roofing

4. All new Ice and Water Shield to be included in base bid for the MS roof. If existing can be salvaged a credit will be taken. Provide lineal foot price on bid form.

5. There will be no site fence at the Middle School. It is the responsibility of this contractor to provide warning line on the ground to prevent students or staff walking in an area where roofing material could fall.

6. All vents called out on Middle School drawings for the shingle roof will be furnished and installed by this WC.

Related Work by Others:

1. Roof sump pans, roof drains, overflow roof drains, roof stairs and ladders – furnished and installed by others

Allowances:

This Contractor shall include in their Base Bid a Construction Manager’s allowance of $0. Reference Section 01020 for specific instructions on allowances.

Unit Prices:

Unit Prices are to be complete furnished in-place operations, and include all costs, incidental materials and work, insurance, fringes, bonds, engineering, overhead and profit. Reference the Trade Contract Proposal form for unit pricing required.

End of Work Category No. 14A

Proposal Section Work Category Description

The Christman Company Page WC 28 -1 WC 28 Electrical Systems

Work Category No. 00 – General Requirements for All Subcontractors
End of Work Category No. 00
Work Category No. 02 – Earthwork and Site Utilities
End of Work Category No. 02
Work Category No. 14 - Flat Roofing & Sheet Metal
End of Work Category No. 14