This document is a Performance Work Statement (PWS) for Integrated Solid Waste Management (ISWM) services at Naval Air Station Meridian, Mississippi and Joe Williams Field, Dekalb, Mississippi.
The PWS outlines the requirements for the Contractor to provide all labor, management, supervision, tools, materials, and equipment required to perform refuse collection and disposal services. Key details include:
- The PWS is for a performance-based service acquisition contract with defined performance objectives and standards.
- Services include non-residential solid waste collection, bulky waste collection, and solid waste disposal, with requirements for providing and maintaining waste containers.
- The contract is 100% set-aside for SBA certified HUBZone small businesses under solicitation N6945024R0090.
- The contract will be awarded by the Department of the Navy Naval Facilities Engineering Command.
- Non-recurring work may be ordered through task orders or FedMALL.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 2- SECTION J.pdf | ||
| Attachment 5 - J-0200000-06.xlsx | XLSX spreadsheet | |
| Amendment 0002 SF30_N6945024R0090.pdf | ||
| Attachment 3 - J-0200000-02.pdf | ||
| Attachment 4 - J-0200000-05.pdf | ||
| SF1449.pdf | ||
| Attachment J-0200000-06.xlsx | XLSX spreadsheet | |
| Amendment 0001 SF30_N6945024R0090.pdf | ||
| Solicitation SF1449 N6945024R0090_Conformed.pdf | ||
| Attachment J-0200000-05.pdf | ||
| N6945024R0090_Solicitation.pdf | ||
| Attachment J-0200000-06.xlsx | XLSX spreadsheet | |
| Attachment J-0200000-02.pdf | ||
| Attachment SECTION J.pdf | ||
| Attachment SECTION C.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C – 0100000 General Information
0100000 – General Information Spec Item Title 1 General Information
1.1 Outline of Services
1.2 Acquisition of Additional Work
1.3 Background Information
1.4 Navy PBSA Approach
1.5 Standard Template
1.6 Related Information
1.7 Verification of Workload and Conditions
1.8 Contractor's Knowledge
1.9 Technical Proposal Certification
N69450-24-R-0090 SECTION C
0100000 – General Information Spec Item Title Description 1 General Information
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at Naval Air Station Meridian, Mississippi, Joe Williams Field, Dekalb, Mississippi and outlying areas supported by this installation performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).
Annex 1 General Information 0100000 - General Information
Annex 2 Management and Administration 0200000 - Management and Administration
Annex 3 Command and Staff - N/A Annex 4 Public Safety - N/A Annex 5 Air Operations - N/A Annex 6 Port Operations - N/A Annex 7 Ordnance - N/A Annex 8 Range Operations - N/A Annex 9 Health Care Support - N/A Annex 10 Supply - N/A Annex 11 Personnel Support - N/A Annex 12 Morale, Welfare and Recreation Support - N/A Annex 13 Galley - N/A Annex 14 Housing - N/A Annex 15 Facilities Support
1503030 - Integrated Solid Waste Management Annex 16 Utilities - N/A Annex 17 Base Support Vehicles and Equipment - N/A Annex 18 Environmental - N/A
1.2 Acquisition of
Additional Work
The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.3 Background Information NAS Meridian is located in East Central Mississippi. Naval Air Station Meridian trains Sailors and Marines in aviation and technical related fields. It is home to Training Air Wing One, Training Squadron 9, Training Squadron 7, Naval Technical Training Center, Marine Aviation Training Support Squadron One and the Regional Counterdrug Training Academy.
0100000 – General Information Spec Item Title Description
1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.
The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.
Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.
Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated pro rata share to the Exhibit Line Items.
1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
0100000 – General Information Spec Item Title Description
1.7 Verification of
Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.
All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.
As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.
This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.9 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference in Section A – Solicitation/Contract Form including, but not limited to, proposed approaches, staffing, methodology, or work plans, will meet the performance objectives and standards set forth in this contract during execution thereof. The Contractor is not excused from meeting such performance objectives and standards in the event such proposal proves inadequate as conceived or executed to meet such performance objectives and standards. The Contractor understands that it bears all of the cost and performance risk associated with adopting acceptable additional (and/or alternative) means or methods of meeting the performance objectives and standards.
Section C – 0200000 Management and Administration
0200000 – Management and Administration Spec Item Title
2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Partnering
2.3.2.1 Informal Partnering
2.3.2.2 Contract Partnering Administration
2.3.2.3 Contract Partnering Session Attendees
2.3.3 Permits and Licenses
2.3.4 Insurance
2.3.4.1 Certificate of Insurance
2.3.4.2 Minimum Insurance Amounts
2.3.5 Protection of Government Property
2.3.6 Directives, Instructions, and References
2.3.7 Invoicing Procedures
2.3.8 Forms
2.4 Government-Furnished Items
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Dissemination of Information
2.6.2 Work Reception
2.6.3 Work Control
2.6.4 Work Schedule
2.6.5 Deliverables
2.6.6 Service Interruptions
2.6.7 Quality Management System (QMS)
2.6.7.1 Quality Management (QM) Plan
2.6.7.2 Quality Inspection and Surveillance
2.6.7.3 Quality Inspection and Surveillance Report
2.7 Personnel Requirements
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
0200000 – Management and Administration Spec Item Title
2.8.4 Access to Installation
2.8.4.1 DBIDS Program
2.8.4.2 DBIDS Credentials
2.8.5 Security Clearances
2.8.6 Employee Status
2.9 Contractor Safety Program
2.9.1 Contractor Safety Requirements
2.9.1.1 Experience Modification Rate (EMR)
2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate
2.9.2 Accident Prevention Plan (APP)
2.9.3 Activity Hazard Analysis (AHA)
2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.4.1 Alcohol and Drug Abuse Prevention Plan
2.9.5 Accident and Damage Reporting
2.9.5.1 Accident Reporting and Notification Criteria
2.9.6 OSHA Citations and Violations
2.9.7 Safety Inspections and Monitoring
2.9.8 Safety Certification
2.9.9 Safety Apparel on Jobsites
2.9.10 Emergency Medical Treatment
2.10 Environmental Management
2.10.1 Energy Management Program
2.10.2 Environmental Protection
2.10.2.1 Spill Prevention, Containment, and Clean-up
2.10.2.2 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.3 Noise Control
2.11 Disaster Preparedness
2.12 Recurring Work Procedures
2.12.1 Recurring Work Exhibit Line Item Numbers (ELINs)
2.13 Non-recurring Work
2.13.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.13.1.1 Acceptance and Performance
2.13.1.2 Invoicing and Receiving Payment
2.13.3 Non-recurring work ELINS
0200000 - Management and Administration Spec Item Title Description 2 Management and
Administration
2.1 Definitions and
Acronyms Definitions and Acronyms are listed in J-0200000-01.
2.2 General
Information
2.2.1 Government
Regular Working Hours
The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor Working Hours
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.
2.2.2 Wage
Determinations
Wage Determinations are included in J-0200000-02.
2.2.3 Requirements
Hierarchy
Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.
2.3 General
Administrative Requirements
2.3.1 Required
Conferences and Meetings
The Contractor shall attend administrative and coordination meetings. The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.
2.3.2 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.
The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.
0200000 - Management and Administration Spec Item Title Description
2.3.2.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.2.2 Contract Partnering
Administration Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.
2.3.2.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
* Small Business Award Recipient
* Authorized Agent of Subcontracting Affiliate(s)
2.3.3 Permits and
Licenses
The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
2.3.4 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause
52.228-5, INSURANCE – WORK ON A GOVERNMENT
INSTALLATION. This insurance must be maintained during the performance period.
2.3.4.1 Certificate of
Insurance
The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause per Section F.
2.3.4.2 Minimum
Insurance Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
Comprehensive General Liability: $500,000 per occurrence
Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes
Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers
Other as required by state law
0200000 - Management and Administration Spec Item Title Description
2.3.5 Protection of
Government Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.
2.3.6 Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.7 Invoicing
Procedures
Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version. Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and ELIN/Sub-ELIN.
2.3.8 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-04.
2.4 Government-
Furnished Items
No Government-Furnished Items will be provided.
2.5 Contractor-
Furnished Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.
Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Dissemination of
Information
If certain information cannot be provided to the public, state what information cannot be provided, when it will be provided, and to whom, e.g., DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.
2.6.2 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.
2.6.3 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government per Section F. A status update of any item of work must be provided within
0200000 - Management and Administration Spec Item Title Description two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
The Contractor shall provide work schedules for both Recurring and Non- Recurring Work per Section F. At a minimum, work schedules shall include:
Description of service(s) to be accomplished Location Date service(s) are scheduled to be accomplished
2.6.4 Work Schedule The Contractor's work shall not interfere with normal Government business.
In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Section F. At a minimum, the notification shall include the following:
The date and time the work was initially coordinated.
The name and phone number of the Government person with whom the work was initially coordinated.
The name and phone number of the Government person who prevented the work from being performed as previously coordinated.
The alternative date and time, the Government person requested the work be accomplished.
2.6.5 Deliverables Except where otherwise stated, deliverable requirements are specified in
Sections C, F, H, I, J, and within the Directives, Instructions, and References.
The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government. Status of Deliverables shall be provided per Section F.
Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2016 compatible format.
Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.
Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
2.6.6 Service
Interruptions
If any services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO and COR/PAR, in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO and COR/PAR as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored. Status of Deliverables shall be provided per Section F.
Scheduled outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.
The Contractor shall perform operational checks on all equipment affected and service interruptions, at no additional cost to the Government.
0200000 - Management and Administration Spec Item Title Description
2.6.7 Quality
Management System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:
Accurate documentation of work processes, procedures, and output measures.
A systematic procedure for assessing compliance with performance objectives and standards.
Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.
Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.
2.6.7.1 Quality
Management (QM) Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance, per Section F.
The Contractor’s QM Plan shall include, at a minimum, the following:
• Policy and objectives of Quality Management System (QMS)
• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications
• Approach to assuring quality of services provided and conformance with performance objectives and standards
• Methods and procedures for effective planning, operation and control of processes and performance of work
• Procedures for inspection and surveillance of services to include all contractual requirements.
o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work
• Documentation and records management
• Communication with government
2.6.7.2 Quality Inspection
and Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.
2.6.7.3 Quality Inspection
and Surveillance Report
The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The
0200000 - Management and Administration Spec Item Title Description
Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.
2.7 Personnel
Requirements The Contractor shall comply with the personnel requirements stated below:
2.7.1 Key Personnel
The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.
The Contractor shall submit an Organizational Chart per Section F showing the reporting relationships for key personnel who are affiliated this contract.
The chart shall include names of personnel, their position title, employer, and a brief description of their affiliation with this contract. The key personnel shall be revised as applicable.
Proposed substitutes of key personnel shall have comparable qualifications to those of the persons being replaced. The Contractor must submit a written substitution request to the KO prior to the transition date. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.
2.7.1.1 Project Manager
(PM)
The Contractor shall designate in writing an individual to serve as the PM. The HUBZone small business awardee must appoint a person from within its firm to serve as the PM and they shall have full authority to act on all contract related matters. The KO and COR/PAR must be able to easily access the PM by telephone and by e-mail during normal working hours. The PM shall have past experience managing a workforce and coordinating services on contracts of similar size, scope and complexity. **The PM may also serve as the QM and SSHO but a subcontractor cannot serve as the PM.**
2.7.1.2 Quality Manager
(QM)
The Contractor shall designate in writing a QM who is responsible for ensuring all services meet the performance standards expressed within the contract and will employ quality control measures when necessary to ensure achievement of all service related objectives. During working hours the QM must be easily accessible to the KO and COR/PAR by telephone and by e-mail.
The QM shall possess past work experience preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The QM may be an employee of the HUBZone small business awardee or may be an authorized representative of a subcontracting affiliate.
2.7.1.3 Site Safety and
Health Officer
(SSHO)
The SSHO must ensure that the requirements of 29 CFR 1925.1 are met for the project. The Contractor shall provide a SSHO whose duty and responsibility is to prepare and enforce the Contractor's safety program on this contract.
The SSHO shall possess the necessary training and experience prior to being appointed SSHO under this contract. Provide the credentials of the SSHO to the Contracting Officer (KO) for acceptance and approval.
0200000 - Management and Administration Spec Item Title Description
A Competent Person shall be provided to oversee any hazards activities identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan (APP).
The SSHO or an equally-qualified Designated Representative shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted APP.
If the SSHO is unable to be on-site during service performance then an equally-qualified Designated Representative will be appointed in writing by the SSHO to report all safety findings to the SSHO.
The Designated Representatives can perform safety duties in addition to their full-time occupation as a collateral duty. The Designated Representative must be well versed in the Contractor's APP and can supply a physical copy of the plan upon request from the KO or COR/PAR.
The SSHO may be the same person as the Project Manager (PM) and the Quality Manager (QM).
2.7.2 Employee
Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.
2.7.2.1 Employee
Certification and Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.
2.7.2.2 Employee
Appearance
The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
2.7.2.4 Identification as
Contractor Employee
Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in both verbal communication and electronic or written correspondence.
2.7.2.5 Removal of
Employees
The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.
0200000 - Management and Administration Spec Item Title Description
2.7.2.6 Proof of Legal
Residency No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is submitted per Section F.
2.8 Security
Requirements
The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The Contractor shall ensure that all security/entrance clearances are obtained.
The Contractor shall ensure that Contractor personnel do not present a risk to security. By entering the installation, Contractor personnel are subject to installation, state, local and federal regulations and laws, including but not limited to debarment and criminal prosecution.
2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section F. The list shall include employee’s name, supervisor, company, and level of security clearance.
2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate that complies with State Vehicle Code. Vehicles shall meet all other requirement of the State Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration, if applicable.
2.8.3 Passes and Badges All Contractor employees shall obtain the required employee and vehicle passes. The Contractor employees must be able to obtain Common Access Cards (CAC) in accordance with security requirements. Each employee shall wear the Government issued badge over the front of the outer clothing. When an employee leaves the Contractor's service, the employee's Passes and Badges shall be confiscated by the Contractor immediately and returned within 10 calendar days.
2.8.4 Access to
Installation
All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System
(DBIDS).
The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.
2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.
There are no fees associated with obtaining a DBIDS credential.
The Government performs background screening and credentialing.
Throughout the year, the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
2.8.4.2 DBIDS Credentials Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about
0200000 - Management and Administration Spec Item Title Description
DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.
The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification. The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.
The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:
(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.
2.8.5 Security
Clearances
The Contractor shall obtain all required corporate and personnel Security Clearances, prior to commencement of work, at no additional cost to the Government. The Contractor shall ensure that a list of all personnel with Security Clearances is maintained current, including clearances that are pending.
2.8.6 Employee Status The Contractor shall notify the KO of any changes to any employee’s status to include, but not limited to, termination, convictions/arrests, adverse actions taken on the job for any reason or any other documented misbehavior that may affect, or have the potential to affect, security standing in terms of access to federal facilities.
2.9 Contractor Safety
Program
The Contractor shall develop and implement a Safety Program detailing how the Contractor plans, staffs, performs, and controls all safety practices while delivering best value services to the Government without any accidents or mishaps. The Contractor’s safety program shall comply with all safety standards identified in the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, and Public Law 91-596, Occupational Safety and Health Act.
Any reference to “USACE" facilities, property, or equipment specified in EM 385-1-1 should be interpreted as Government facilities, property, and equipment.
2.9.1 Contractor Safety
Requirements
Neither Contractor nor any subcontractor may enter into contract with any subcontractor that fails to meet the below requirements. The term subcontractor in this and the following paragraphs means any entity holding a contract with the Contractor or with a subcontractor at any tier.
2.9.1.1 Experience
Modification Rate
(EMR)
Subcontractors on this contract must have an effective EMR less than or equal to 1.10, as computed by the National Council on Compensation Insurance (NCCI) or if not available, as computed by the state agency's rating bureau in the state where the subcontractor is registered, when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier.
The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable EMR range cannot be achieved. Relaxation of the EMR range will only be considered for approval on a case-by-case basis for special conditions and
0200000 - Management and Administration Spec Item Title Description must not be anticipated as tacit approval. Contractor's Site Safety and Health Officer (SSHO) must collect and maintain the certified EMR ratings for all subcontractors on the project and make them available to the Government at the Government's request.
2.9.1.2 OSHA Days Away
From Work, Restricted Duty, or Job Transfer (DART) Rate
Subcontractors on this contract must have a DART rate, calculated from the most recent, complete calendar year, less than or equal to 3.4 when entering into a subcontract agreement with the Prime Contractor or a subcontractor at any tier.
The Prime Contractor may submit a written request for additional consideration to the Contracting Officer where the specified acceptable OSHA Dart rate range cannot be achieved for a particular subcontractor.
Relaxation of the OSHA DART rate range will only be considered for approval on a case-by-case basis for special conditions and must not be anticipated as tacit approval. Contractor's Site Safety and Health Officer (SSHO) must collect and maintain self-certified OSHA DART rates for all subcontractors on the project and make them available to the Government at the Government's request.
2.9.2 Accident
Prevention Plan
(APP)
The Contractor shall develop and implement a site Accident Prevention Plan (APP). The APP shall be prepared by the Contractor’s SSHO and shall be followed by all Contractor employees, subcontractors, and vendors at each service site. The Contractor may submit an abbreviated APP in lieu of a full APP as described in EM 385-1-1, Appendix A, Paragraph 2. The APP must be submitted to the KO for acceptance and approval per Section F. The Contractor shall review, update, and submit revisions to the APP whenever a change in work conditions, hazards, or activities occur. Submittal of the APP shall include Activity Hazard Analyses (AHAs) and applicable compliance plans, programs, and procedures as specified below.
The Contractor shall not commence work until the APP has been accepted and no activity shall be started on site until the applicable AHAs and compliance plans have been accepted. Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract.
Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified.
2.9.3 Activity Hazard
Analysis (AHA)
The Contractor shall prepare Activity Hazard Analyses (AHAs) for all applicable common recurring work activities performed under this contract.
AHAs for recurring work shall be submitted with the APP and shall be updated as work activities or conditions change and additional AHAs prepared as new work activities are required. AHAs for non-recurring and one-time (e.g., non-recurring work task orders) work occurrences shall be submitted at least two working days prior to start of work. Specifically:
For contract modifications to recurring work requirements where changes are germane to the original contract, the Contractor shall revise applicable AHAs within 15 calendar days after modification is signed.
For contracts with non-recurring work ELINs, the Contractor shall submit an AHA on non-recurring work task orders, with the associated proposal, whenever the service environment or required task is different from the recurring work priced services.
0200000 - Management and Administration Spec Item Title Description
The Contractor shall follow the Risk Management Process for the development of Activity Hazard Analysis (AHA) in accordance with paragraph 01.A.14 and Appendix A of EM 385-1-1. A formatted outline of an AHA is provided in Figure 1-2 of EM 385-1-1.
During performance of services, the SSHO shall periodically review the AHA at each service site and for each sub-annex to assess the effectiveness of the Contractor’s overall APP. If changes to the AHAs are required, such changes shall be submitted to the KO for review and acceptance.
2.9.4 Safety and
Occupational Health (SOH) Risks and Compliance Plans
Based on a risk assessment of recurring and non-recurring work requirements and on mandatory OSHA compliance programs, the Contractor shall develop, provide and implement all applicable compliance plans, as necessary for the situation or types of work to be performed under this contract. Compliance plans, programs, and procedures along with their respective references are detailed in Appendix A, paragraph 3.i of EM 385-1-1 if utilizing a fully developed APP and detailed in Appendix, paragraph 3.k and 01.A.12.e if utilizing an abbreviated APP. These plans shall be submitted with the APP as outlined in section F and shall be updated as situations change. Additional compliance plans, programs, and procedures shall be developed as applicable when new types of work are required under this contract. Additional requirements for specific compliance plans are provided below.
2.9.4.1 Alcohol and Drug
Abuse Prevention Plan
The Contractor shall develop an alcohol and drug abuse prevention plan to explain how it will satisfy the drug-free work force requirement as stated in DFARS Clause 252.223-7004.
2.9.5 Accident and
Damage Reporting
The Contractor shall notify the Contracting Officer as soon as practical, but no more than four hours after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $2,000. Notification shall also be provided for any mishap occurring in any of the following high hazard areas: electrical (to include Arc Flash, electrical shock, etc.); uncontrolled release of hazardous energy (includes electrical and non-electrical); fall-from-height (any level other than same surface); and underwater diving. These mishaps shall be investigated in depth to identify all causes and to recommend hazard control measures.
Within notification include Contractor name; contract title; type of contract;
name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.
The Contractor shall conduct an accident investigation for recordable injuries and illnesses, for accidents requiring Medical Treatment, property damage accidents resulting in at least $20,000 in damages, and near misses as defined in EM 385-1-1, to establish the root cause(s) of the accident. The Contractor shall complete the applicable NAVFAC Contractor Incident Reporting System (CIRS), and electronically submit via the NAVFAC Enterprise Safety Applications Management System (ESAMS) per Section F. Required or special forms are provided within the Forms in J-0200000-04.
0200000 - Management and Administration Spec Item Title Description
For any weight handling equipment accident (including rigging gear accidents) the Contractor shall conduct an accident investigation to establish the root cause(s) of the accident and comply with additional requirements and procedures for accidents in accordance with NAVFAC P-307, Section 12.
The Contractor shall submit a WHE Accident Report (Crane and Rigging Gear) per Section F. No crane operations are allowed to proceed until cause is determined and corrective actions have been implemented to the satisfaction of the Contracting Officer.
For a near miss, the Contractor shall complete the applicable documentation in NAVFAC Contractor Incident Reporting System (CIRS), and electronically submit via the NAVFAC Enterprise Safety Applications Management System (ESAMS) per Section F.
2.9.5.1 Accident Reporting
and Notification Criteria
The following criteria and definitions apply to the accident reporting requirements specified above:
Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
1) Death, regardless of the time between the injury and death, or the length of the illness;
2) Days away from work (any time lost after day of injury/illness onset);
3) Restricted work;
4) Transfer to another job;
5) Medical treatment beyond first aid;
6) Loss of consciousness; or
7) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (6) above.
High Visibility Accident.