N69450-20-R-0018 Section C
0100000 – General Information Table of Contents
Spec Item Title 1 General Information
1.1 Outline of Services
1.2 Acquisition of Additional Work
1.3 Background Information
1.4 Navy PBSA Approach
1.5 Standard Template
1.6 Related Information
1.7 Verification of Workload and Conditions
1.8 Contractor's Knowledge
1.9 Technical Proposal Certification
0100000 – General Information Spec Item Title Description 1 General Information
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at Navy Operation Support Center (NOSC) Chattanooga, TN, NOSC Knoxville, TN, NOSC St. Louis, and NOSC Kansas City by means of performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).
Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff -N/A Annex 4 Public Safety -N/A Annex 5 Air Operations -N/A Annex 6 Port Operations -N/A Annex 7 Ordnance -N/A Annex 8 Range Operations -N/A Annex 9 Health Care Support -N/A Annex 10 Supply -N/A Annex 11 Personnel Support -N/A Annex 12 Morale, Welfare and Recreation Support -N/A Annex 13 Galley -N/A Annex 14 Housing -N/A Annex 15 Facilities Support 1502000 Facility Investment 1503010 Custodial 1503020 Pest Control 1503030 Integrated Solid Waste Management 1503050 Grounds Maintenance and Landscaping 1503060 Pavement Clearance Annex 16 Utilities -N/A Annex 17 Base Support Vehicles and Equipment -N/A Annex 18 Environmental -N/A
1.2 Acquisition of
Additional Work
The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.3 Background Information Navy Operational Support Centers (NOSC) are training facilities for Navy and Marine Reservists. Reserve Sailors and Marines will assemble at the NOSC and perform Drill Activities. Although Reservists perform drills on weekends, the NOSCs are fully operational throughout the entire year.
1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.
The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.
Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.
Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated to the Exhibit Line Items.
1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
1.7 Verification of
Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.
All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.
As prescribed in FAR 52.237-1, offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.
This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.9 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.
0200000 – Management and Administration Table of Contents
2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment
2.3.3 Partnering
2.3.3.1 Informal Partnering
2.3.3.2 Contract Partnering Administration
2.3.3.3 Contract Partnering Session Attendees
2.3.4 Permits and Licenses
2.3.5 Insurance
2.3.5.1 Certificate of Insurance
2.3.5.2 Minimum Insurance Amounts
2.3.6 Protection of Government Property
2.3.7 Government Information Technology (IT) System
2.3.8 Directives, Instructions, and References
2.3.9 Invoicing Procedures
2.3.10 Forms
2.4 Government-Furnished Property, Materials and Services
2.4.1 Government-Furnished Facilities (GFF)
2.4.2 Government-Furnished Utilities
2.4.3 Government-Furnished Materials (GFM)
2.4.4 Government-Furnished Equipment (GFE)
2.4.5 Government-Furnished Services (GFS)
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Safeguarding Information
2.6.2 Work Reception
2.6.3 Work Control
2.6.4 Work Schedule
2.6.5 Deliverables
2.6.6 Service Interruptions
2.6.7 NAVFAC MAXIMO
2.6.7.1 NAVFAC MAXIMO Data
2.6.7.2 NAVFAC MAXIMO Method of Data Entry
2.6.7.3 NAVFAC MAXIMO Access
2.6.7.4 NAVFAC MAXIMO Training
2.6.8 Quality Management System (QMS)
2.6.8.1 Quality Management (QM) Plan
2.6.8.2 Quality Inspection and Surveillance
2.6.8.3 Quality Inspection and Surveillance Report
2.6.9 Property Management Plan
2.6.10 System and Equipment Replacement
2.7 Personnel Requirements
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
2.8.4 Access to Installation
2.8.4.1 DBIDS Program
2.8.4.2 DBIDS Credentials
2.8.5 Access to Buildings
2.8.6 Access Arrangements
2.8.6.1 Escort Arrangements for Secured Areas
2.8.7 Security Clearances
2.8.8 Access to Sensitive Unclassified Information
2.8.9 Employee Status
2.9 Contractor Safety Program
2.9.1 Contractor Safety Requirements
2.9.1.1 Experience Modification Rate (EMR)
2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DAOSHA RT) Rate
2.9.1.3 Total Recordable Case (TRC) Rate
2.9.2 Accident Prevention Plan (APP)
2.9.3 Activity Hazard Analysis (AHA)
2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.4.1 Alcohol and Drug Abuse Prevention Plan
2.9.5 Accident and Damage Reporting
2.9.5.1 Accident Reporting and Notification Criteria
2.9.6 Fire Protection
2.9.7 Monthly On-Site Labor Report
2.9.8 OSHA Citations and Violations
2.9.9 Safety Inspections and Monitoring
2.9.10 Safety Certification
2.9.11 Safety Apparel on Jobsites
2.9.12 Emergency Medical Treatment
2.9.13 Excavations
2.10 Environmental Management and Sustainability
2.10.1 Energy Management Program
2.10.1.1 Water Conservation Plan
2.10.1.2 Energy Efficient Products
2.10.2 Environmental Protection
2.10.2.1 ODS Requirements for Refrigerant Recycling
2.10.2.2 Solid Waste Management and Recycling
2.10.2.3 Non-Regulated Waste Disposal
2.10.2.4 Regulated Waste Disposal
2.10.2.5 Spill Prevention, Containment, and Clean-up
2.10.2.6 Hazardous Material Management
2.10.2.7 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.8 Noise Control
2.10.2.9 Salvage
2.10.2.10 Asbestos Containing Material (ACM)
2.10.3 Sustainable Procurement and Practices
2.10.3.1 Environmentally Preferable Products
2.10.3.2 Use of Recovered Materials
2.10.3.3 Use of Biobased Products
2.11 Disaster Preparedness
2.12 Warranty Management
2.13 Recurring Work Procedures
2.13.1 Recurring Work Preparation of Proposals
2.13.2 Notification to the Government for Work Above the FFP Limitations
2.13.3 Recurring Work Exhibit Line Item Numbers (ELINs)
2.14 Non-recurring Work
2.14.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.14.1.1 Acceptance and Performance
2.14.1.2 Invoicing and Receiving Payment
2.14.2 Unit Priced Labor (UPL)Work (Negotiated)
2.14.2.1 Non-recurring Work Preparation of Proposals
2.14.2.1.1 Labor Requirements
2.14.2.1.2 Material and Equipment Requirements
2.14.2.2 Issuance of Final Task Order
2.14.3 Non-Recurring Work ELINS
0200000 - Management and Administration
2 Management and
Administration
2.1 Definitions and
Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2 General Information
2.2.1 Government Regular
Working Hours The Government's regular working hours are from 0700-1630, five days per week, Monday through Friday, except observed Federal holidays.
Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO or COR approval.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor Working Hours
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.
2.2.2 Wage Determinations Wage Determinations are included in J-0200000-02.
2.2.3 Requirements
Hierarchy Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.
2.3 General Administrative
Requirements
2.3.1 Required Conferences
and Meetings
The Contractor may be required to attend administrative and coordination meetings. The Contractor shall attend meetings as shown in Contractor Partnering Level below and as deemed necessary for the award of this contract.
2.3.2 Training for
Maintenance and Operation of New and Replacement Systems and Equipment
When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.
2.3.3 Partnering To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and subcontractors teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
Partnering should accomplish three goals:
- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.
- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.
- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.
2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.3.2 Contract Partnering
Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.
Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.
The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.
2.3.3.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
President/Vice President
* Project Manager
* Quality Manager Site Safety and Health Officer
2.3.4 Permits and Licenses The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
0200000 - Management and Administration Spec Item Title Description
2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.
2.3.5.1 Certificate of Insurance The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO and COR by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.5.2 Minimum Insurance
Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
Comprehensive General Liability: $500,000 per occurrence
Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes
Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers
Other as required by state law
2.3.6 Protection of
Government Property During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.
2.3.7 Government
Information Technology (IT) System
Additional information about NMCI may be obtained at http://www.eds.com/nmci.
2.3.8 Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.9 Invoicing Procedures Refer to Section G for invoicing instructions. Refer to Invoice Form in J- 0200000-04 for sample.
2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.
2.4 Government-Furnished
Property, Materials and Services
In accordance with Section H paragraph H.13 Government Property, the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, equipment and services for use in connection with this contract as stated below.
2.4.1 Government-Furnished
Facilities (GFF)
Government will not provide GFF.
2.4.2 Government-Furnished The Government will furnish water and electricity at existing outlets
Utilities required for the work to be performed under the contract at no cost to the Contractor. Information concerning the location of existing outlets may be secured from the KO or COR. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, State, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.
2.4.3 Government-Furnished
Materials (GFM)
Government will not provide GFM.
2.4.4 Government-Furnished
Equipment (GFE)
Government will not provide GFE.
2.4.5 Government-Furnished
Services (GFS)
Government will not provide GFS.
2.5 Contractor-Furnished
Items
Except for items identified as Government Furnished, the Contractor shall provide all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to perform the requirements of this contract. Lack of availability of labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, or any other item necessary to perform the requirements of this contract shall not relieve the Contractor from the requirements to complete all work within the time limits specified herein. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no additional cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO and COR may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards.
Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Safeguarding
Information
The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-171.
Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF) and shall not contain any information associated with Government property beyond that included in this PWS and the attachments.
The Contractor shall develop Plans of Action and Milestones (POA&Ms) per NIST SP 800-171, track accomplishment, and submit to the Government per Section F.
If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government per Section F.
2.6.2 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.
2.6.3 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO or COR. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
2.6.4 Work Schedule The Contractor's work shall not interfere with normal Government business. In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO and COR of any difficulty in scheduling work due to Government controls. The notification shall include, at a minimum, the following:
• The date and time the work was initially coordinated.
• The name and phone number of the Government person with whom the work was initially coordinated.
• The name and phone number of the Government person who prevented the work from being performed as previously coordinated.
• The alternative date and time that the Government person requested the work be accomplished.
2.6.5 Deliverables Records and reports are specified in Section C and listed as deliverables in Section F. The Contractor shall submit accurate and complete documents within the required timeframes as specified in Section F.
Government acceptance of deliverables will not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website.
Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.
2.6.6 Service Interruptions If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the affected tenants and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.
Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.
The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.
2.6.7 NAVFAC MAXIMO MAXIMO is the Computerized Maintenance Management System (CMMS) used by the Government for asset management and condition assessment of CNIC and NAVFAC assets. The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:
2.6.7.1 NAVFAC MAXIMO
Data
Required data fields for work orders are indicated in the Service Provider Information provided in J-0200000-06. Asset data requirements are indicated in the Asset Information provided in J-0200000-07.
Specification and Characteristic Meter Reading Interfaces data requirements are provided on J-0200000-08 / -09 respectively.
Specified data shall be provided for all work performed in 1502000 Facility Investment. Further instructional information detailing the process for submitting the specified information for NAVFAC MAXIMO Data Reporting is provided in J-0200000-10.
The Service Provider, Asset, Specification, and Characteristic Meter Reading Interfaces are used in multiple processes for loading data into MAXIMO by the Government and the format may be updated periodically.
As part of the update, the Contractor may be asked to modify the file to add/move columns in their submission. The Contractor also shall provide up to 10 extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar days’ notice of modifications to the Service Provider, Asset, Specification, or Characteristic Meter Reading Interfaces file format.
2.6.7.2 NAVFAC MAXIMO
Method of Data Entry
The Contractor shall provide data for NAVFAC MAXIMO using the methods detailed below:
DIRECT ENTRY: The Contractor shall manually enter required work order and condition assessment data directly into NAVFAC MAXIMO.
The Contractor shall ensure all information is updated by the end of each workday for all work performed.
If the Contractor does not have access to NAVFAC MAXIMO at contract start, work order and condition assessment data shall be submitted in a pipe delimited flat-file following the NAVFAC MAXIMO Data Reporting process described in J-0200000-10 per Section F. Any failures in processing of the flat-file shall be corrected and resubmitted by the Contractor. In order to demonstrate the ability to properly format the flat-file, the Contractor shall provide a Sample Pipe Delimited Flat-file prior to contract performance per Section F. Flat file submission of work order and condition assessment data will be allowed for a period not to exceed six months unless an extension is approved in writing by the KO.
The Contractor shall submit asset and specification data in a spreadsheet flat-file following the NAVFAC MAXIMO Data Reporting process described in J-0200000-08 per Section F.
2.6.7.3 NAVFAC MAXIMO
Access
The process for obtaining access and establishing MAXIMO accounts are detailed in the NAVFAC MAXIMO System Access Procedures provided in at the pre-performance meeting.
Once accounts have been established, MAXIMO can be accessed at https://maximo.navfac.navy.mil.
The Contractor shall provide all necessary computer equipment and Internet Service Provider (ISP) accounts to access MAXIMO for Direct Entry of required data.
The Contractor shall provide a list of personnel requiring MAXIMO accounts per Section F.
2.6.7.4 NAVFAC MAXIMO
Training
The Government will provide or make available initial training on NAVFAC MAXIMO to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data.
Additional training will be provided by the Government when there are significant changes to the NAVFAC MAXIMO software or data entry requirements. Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC MAXIMO.
2.6.8 Quality Management
System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:
• Accurate documentation of work processes, procedures, and output measures.
• A systematic procedure for assessing compliance with performance objectives and standards.
• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.
https://maximo.navfac.navy.mil/
• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.
2.6.8.1 Quality Management
(QM) Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. As part of the acceptance process, the QC Manager shall provide the Government a presentation of the Contractors QM Plan and jointly complete the Government’s QMS Pre-Performance Review Checklist. If any changes are made during the period of performance, submit to the KO and COR a revised QM Plan for acceptance.
The Contractor’s QM Plan shall include, at a minimum, the following:
• Policy and objectives of Quality Management System (QMS)
• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications
• Approach to assuring quality of services provided and conformance with performance objectives and standards
• Methods and procedures for effective planning, operation and control of processes and performance of work
• Procedures for inspection and surveillance of services o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work
• Documentation and records management
• Communication with government (customers)
2.6.8.2 Quality Inspection and
Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be turned over to the KO and COR within five calendar days of termination of the contract.
2.6.8.3 Quality Inspection and
Surveillance Report
The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include narrative of events; a tabulated summary and results of the quality inspection and surveillance events performed; inspection-driven corrective actions taken and the results attained; and management process adjustments during the previous month.
The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.
2.6.9 Property Management
Plan
The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Property, Materials and Services, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.
2.6.10 System and Equipment
Replacement The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work. Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced.
Substitutes for replacement components must be accepted by the KO prior to use. The KO or COR will furnish available information for the existing systems and equipment.
2.7 Personnel
Requirements
The Contractor shall comply with the personnel requirements stated below.
2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO and COR necessary to certify their qualifications.
The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.
2.7.1.1 Project Manager (PM) The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site within twenty-four hours after the Government’s Request.
The PM shall have at least three years of experience in managing a workforce providing services on contracts of similar size, scope and complexity. The PM shall not be the same person as the Quality Manager.
2.7.1.2 Quality Manager The Contractor shall provide a QCM who shall have full authority and responsibility for assuring performance objectives and standards identified in this contract are met. The QCM or alternate shall be available on-site within twenty-four (24) hours after the Government's request. The Quality Manager must report directly to a senior corporate official and shall not report directly to the Project Manager.
The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:
The Quality Manager shall have at least three years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager shall not be the same person as the Project Manager.
2.7.1.3 Site Safety and Health
Officer (SSHO)
The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project.
Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.
A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for acceptance in consultation with the Safety Office.
The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract. The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:
The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past, and have completed the OSHA 30-hour construction safety class or equivalent. The SSHO shall maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO may be the same person as the project manager if the individual has fulfilled the pre-requisite qualifications and experiences for SSHO and PM.
2.7.2 Employee
Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.
2.7.2.1 Employee Certification
and Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.
2.7.2.2 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO and COR reserve the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
2.7.2.4 Identification as
Contractor Employee
Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
2.7.2.5 Removal of Employees The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.
2.7.2.6 Proof of Legal
Residency
No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is furnished per Section F.
No employee or representative of the Contractor will be granted access to Government IT systems unless satisfactory Proof of United States of America Citizenship is furnished per Section F.
2.7.3 Enterprise-wide
Contractor Manpower Reporting Application (eCMRA)
The following manpower reporting is required by NMCARS 5237.102.
The Contractor shall report all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://doncmra.nmci.navy.mil.
Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk , linked at https://www.ecmra.mil.
2.8 Security Requirements The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO or COR when required to enter a Government site.
The Contractor shall ensure that all security/entrance clearances are obtained.
2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section F. The list shall include employee’s name, supervisor, company, and level of security clearance.
2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate that complies with State Vehicle Code. Vehicles shall meet all other requirement of the State Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration, if applicable.
2.8.3 Passes and Badges All Contractor employees shall obtain the required employee and vehicle passes. The Contractor employees must be able to obtain Common Access Cards (CAC) in accordance with security requirements. Each employee shall wear the Government issued badge over the front of the outer clothing. When an employee leaves the Contractor's service, the employee's Passes and Badges shall be returned within 10 calendar days.
2.8.4 Access to Installation All Contractor personnel shall obtain access to the installation by participating through enrollment and registration into the Defense Biometric Identification System (DBIDS).. Costs for obtaining passes through the DBIDS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge.
The Contractor shall furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. There are no fees associated with obtaining a DBIDS credential.
The Government performs background screening and credentialing.
Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
2.8.4.2 DBIDS Credentials Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.
The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification.
The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.
The Contractor shall immediately collect employee DBIDS credentials and notify the KO and COR in writing:
(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.
That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein
2.8.5 Access to Buildings The Contractor shall monitor and control access into restricted areas under their responsibility, allowing only those…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .