Solicitation N6945020Q2809 Page 1 of 45
FY21 SOTEX ISWM
Performance Work Statement
0100000 – General Information Spec Item Title
1.1 Outline of Services
1.2 Project Location
1.3 Acquisition of Additional Work
1.4 Background Information
1.5 Verification of Workload and Conditions
1.6 Climate Patterns
1.7 Related Information
1.8 Navy Approach to Service Contracting
1.8.1 Partnering Philosophy
1.8.2 Contractor’s Knowledge
1.8.3 Industry Best Practices
1.9 Standard Template
1.10 Navy PBSA Approach
1.11 Technical Proposal Certification
Solicitation N6945020Q2809 Page 2 of 45
Performance Work Statement
0100000 – General Information Spec Item Title Description 1 General Information
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at Naval Air Station Corpus Christi; Naval Air Station Kingsville; Naval Air Auxiliary Landing Field Cabaniss, Navy Outlying Field Orange Grove, and Naval Air Auxiliary Landing Field Waldron, Texas by means of combination recurring work and non-recurring work..
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).
Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff (Not Applicable) Annex 4 Public Safety (Not Applicable) Annex 5 Air Operations (Not Applicable) Annex 6 Port Operations (Not Applicable) Annex 7 Ordnance (Not Applicable) Annex 8 Range Operations (Not Applicable) Annex 9 Health Care Support (Not Applicable) Annex 10 Supply (Not Applicable) Annex 11 Personnel Support (Not Applicable) Annex 12 Morale, Welfare and Recreation Support (Not Applicable) Annex 13 Galley (Not Applicable) Annex 14 Housing (Not Applicable) Annex 15 Facilities Support
1503030 Integrated Solid Waste Management Annex 16 Utilities (Not Applicable) Annex 17 Base Support Vehicles and Equipment (Not Applicable) Annex 18 Environmental (Not Applicable)
1.2 Project Location The work shall be performed at various locations and could vary from location to location. The following is an example of the dispersion of work at the various locations.
(1) Naval Air Station Corpus Christi, Texas 1503030 Integrated Solid Waste Management
(2) Naval Air Station Kingsville, Texas 1503030 Integrated Solid Waste Management
(3) Naval Air Auxiliary Landing Field Cabaniss 1503030 Integrated Solid Waste Management
(4) Naval Air Auxiliary Landing Field Waldron 1503030 Integrated Solid Waste Management
(5) NALF Orange Grove, Texas 1503030 Integrated Solid Waste Management
Solicitation N6945020Q2809 Page 3 of 45
Performance Work Statement
0100000 – General Information Spec Item Title Description
1.3 Acquisition of
Additional Work The Government reserves the right to acquire additional Integrated Solid Waste Management services at additional locations in addition to the services and locations identified in the recurring work requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the indefinite delivery indefinite quantity provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.4 Background Information The official step leading to the construction of Naval Air Station Corpus Christi, Texas was initiated by the 75th Congress in 1938. A board found that a lack of training facilities capable of meeting an emergency demand for pilots constituted a grave situation. They recommended the establishment of a second air training station, and further, that it be located on Corpus Christi Bay. NAS Corpus Christi was commissioned by its first skipper, Captain Alva Berhard, on March 12, 1941. The first flight training started on May 5, 1941. In support of the Naval Air Station Corpus Christi training mission are two nearby outlying landing fields owned by the Navy: Naval Air Auxiliary Landing Field Cabaniss, which is 8.0 miles (12.9 km) west of the Naval Air Station and Naval Air Auxiliary Landing Field Waldron which is 3.5 miles (5.6 km) southwest of the Naval Air Station.
In the fall of 1941, a group of Kingsville civic leaders decided that the city's desirable climate and scarcely populated area would be very suitable for a military airfield, much like the one in Corpus Christi. The city leaders wasted little time in making their belief known to the Department of Defense.
The Kingsville group picked out several good sites for airfields and presented them to Navy leaders at Naval Air Station Corpus Christi.
Among the most impressed of the Navy staff was Captain Alva Bernhard, who at the time was Naval Air Station Corpus Christi’s Commanding Officer. While the Navy made no immediate promises to the Kingsville group, that all changed on the morning of Dec. 7, 1941, when the Japanese bombed Pearl Harbor. Captain Bernhard, foreseeing an immense training buildup that would overtake Naval Air Station Corpus Christi’s capacity, immediately selected a site in Kingsville and put his plans into high gear for procurement and construction. Naval Air Station Kingsville, Texas opened July 4, 1942.
1.5 Verification of
Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, inventories, maps, floor plans, and tables to represent the type, quantity, and location of services to be provided.
As prescribed in FAR 52.237-1, offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
1.6 Climate Patterns The Corpus Christi, TX Bay area is within U.S. Climate Division 9, as assigned by the NOAA National Centers for Environmental information.
The area is classified as being humid, subtropical. The mean annual
Solicitation N6945020Q2809 Page 4 of 45
Performance Work Statement
0100000 – General Information Spec Item Title Description temperature is approximately 72.9 F; January is the average coldest month of the year, with a mean temperature of 54.6 F. August is the typically the hottest month with a mean temperature 86.6 F. There is no significant precipitation difference between the seasons. The average annual precipitation is 25.42”. (Sources: https://www.ncdc.noaa.gov/cag/ and https://www.plantmaps.com/koppen-climate-classification-map-united-states.php. Averages are determined over a 5 year period 2014-2018.)
1.7 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
1.8 Navy Approach to
Service Contracting
The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.
The Navy also supports the following principles:
1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.
Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.
1.8.2 Contractor's Knowledge The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle.
Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management https://www.ncdc.noaa.gov/cag/ https://www.plantmaps.com/koppen-climate-classification-map-united-states.php https://www.plantmaps.com/koppen-climate-classification-map-united-states.php
Solicitation N6945020Q2809 Page 5 of 45
Performance Work Statement
0100000 – General Information Spec Item Title Description to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).
1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.
The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.
Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the management and administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.
Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.
Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 must be priced and their price must be allocated across the Exhibit Line Items.
1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.11 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.
Solicitation N6945020Q2809 Page 6 of 45
Performance Work Statement
0200000 – Management and Administration Spec Item Title
2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Partnering
2.3.2.1 Informal Partnering
2.3.2.2 Contract Partnering Administration
2.3.2.3 Contract Partnering Session Attendees
2.3.3 Permits and Licenses
2.3.4 Insurance
2.3.4.1 Certificate of Insurance
2.3.4.2 Minimum Insurance Amounts
2.3.5 Protection of Government Property
2.3.6 Directives, Instructions, and References
2.3.7 Invoicing Procedures
2.3.8 Forms
2.4 Government-Furnished Property, Materials and Services
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Work Reception
2.6.2 Work Control
2.6.3 Work Schedule
2.6.4 Deliverables
2.6.5 Service Interruptions
2.6.6 NAVFAC MAXIMO
2.6.6.1 MAXIMO Data
2.6.6.2 MAXIMO Method of Data Entry
2.6.6.3 MAXIMO Access
2.6.6.4 MAXIMO Training
2.6.7 Quality Management System (QMS)
2.6.7.1 Quality Management (QM) Plan
2.6.7.2 Quality Inspection and Surveillance
2.6.7.3 Quality Inspection and Surveillance Report
2.7 Personnel Requirements
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
Solicitation N6945020Q2809 Page 7 of 45
Performance Work Statement
0200000 – Management and Administration Spec Item Title
2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
2.8.4 Access to Installation
2.8.4.1 DBIDS Program
2.8.4.2 DBIDS Credentials
2.8.5 Access to Buildings
2.8.6 Access Arrangements
2.8.7 Security Clearances
2.8.8 Employee Status
2.9 Contractor Safety Program
2.9.1 Accident Prevention Plan (APP)
2.9.2 Activity Hazard Analysis (AHA)
2.9.3 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.3.1 Alcohol and Drug Abuse Prevention Plan
2.9.3.2 Critical Lift Plan
2.9.3.3 Fall Prevention and Protection Plan
2.9.4 Crane Operations
2.9.4.1 Crane Inspections
2.9.4.2 Rigging Gear
2.9.4.3 Crane Operators
2.9.5 Accident and Damage Reporting
2.9.5.1 Accident Reporting and Notification Criteria
2.9.6 Fire Protection
2.9.7 Monthly On-Site Labor Report
2.9.8 OSHA Citations and Violations
2.9.9 Safety Inspections and Monitoring
2.9.10 Safety Certification
2.9.11 Safety Apparel on Jobsites
2.9.12 Emergency Medical Treatment
2.10 Environmental Management and Sustainability
2.10.1 Energy Management Program
2.10.1.2 Energy Efficient Products
2.10.2 Environmental Protection
2.10.2.1 Solid Waste Management and Recycling
2.10.2.2 Non-Regulated Waste Disposal
2.10.2.3 Regulated Waste Disposal
2.10.2.4 Spill Prevention, Containment, and Clean-up
2.10.2.5 Hazardous Material Management
2.10.2.6 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.7 Noise Control
2.10.2.8 Salvage
2.10.3 Sustainable Procurement and Practices
2.10.3.1 Environmentally Preferable Products
2.10.3.2 Use of Recovered Materials
2.10.3.3 Use of Biobased Products
2.11 Disaster Preparedness
2.12 Recurring Work Procedures
2.12.1 Recurring Work Exhibit Line Item Numbers (ELINs)
Solicitation N6945020Q2809 Page 8 of 45
Performance Work Statement
0200000 – Management and Administration Spec Item Title
2.13 Non-Recurring Work
2.13.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.13.1.1 Acceptance and Performance
2.13.1.2 Invoicing and Receiving Payment
2.13.2 Non-Recurring Work ELINS
Solicitation N6945020Q2809 Page 9 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description 2 Management and
Administration
2.1 Definitions and
Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2 General
Information
2.2.1 Government
Regular Working Hours
The Government's regular working hours are from 0730-1630, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO approval.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor Working Hours
The Contractor shall confine operations to daylight hours commencing not earlier than 0730 and continuing not later than 1630.
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F.
2.2.2 Wage
Determinations
Wage Determinations are included in J-0200000-02.
2.2.3 Requirements
Hierarchy
Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.
2.3 General
Administrative Requirements
2.3.1 Required
Conferences and Meetings
The Contractor shall attend administrative and coordination meetings. The Contractor shall attend meetings as documented in attachment J-0200000-03.
2.3.2 Partnering To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.
The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
Partnering should accomplish three goals:
Solicitation N6945020Q2809 Page 10 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description
- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.
- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.
- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.
2.3.2.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.2.2 Contract Partnering
Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.
Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.
The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.
2.3.2.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
President/Vice President
* Project Manager
* Quality Manager
* Site Safety and Health Officer
2.3.3 Permits and
Licenses
The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
2.3.4 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause
52.228-5, INSURANCE – WORK ON A GOVERNMENT
INSTALLATION. This insurance must be maintained during the performance period.
2.3.4.1 Certificate of
Insurance
The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material
Solicitation N6945020Q2809 Page 11 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.4.2 Minimum
Insurance Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
Comprehensive General Liability: $500,000 per occurrence
Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes
Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers
Other as required by state law
2.3.5 Protection of
Government Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.
2.3.6 Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-04. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.7 Invoicing
Procedures
Refer to Section G for invoicing instructions.
2.3.8 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.
2.4 Government-
Furnished Property, Materials and Services
The Government will not furnish or make available to the Contractor any Government-owned facilities utilities, materials, equipment and services for use in connection with this contract.
2.5 Contractor-
Furnished Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.
Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract per Section F.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to task orders during Government regular working hours and
Solicitation N6945020Q2809 Page 12 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.
2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO. Per Section F, a status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
2.6.3 Work Schedule The Contractor's work shall not interfere with normal Government business.
In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO of any difficulty in scheduling work due to Government controls.
2.6.4 Deliverables Deliverable requirements are specified in Sections C, F, H, I, J, and within the Directives, Instructions, and References. The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify data entry requirements and deliverables, as directed by the KO, at no additional cost to the Government.
Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2016 compatible format.
Deliverables shall include the company name, contract number, contract title, and date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.
Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.
2.6.5 Service
Interruptions
If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown, the Contractor shall notify the KO, affected tenants and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.
Solicitation N6945020Q2809 Page 13 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description
Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.
The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government..
2.6.6 NAVFAC
MAXIMO
MAXIMO is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment. The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:
2.6.6.1 NAVFAC
MAXIMO Data
Specified data shall be provided for all service order work performed in 1503030 Integrated Solid Waste Management. Service provider information shall include, but not be limited to, data listed within attachment J-0200000-
07. Further instructional information detailing the process for submitting the specified information for NAVFAC MAXIMO Data Reporting is provided in J-0200000-08.
2.6.6.2 NAVFAC
MAXIMO Method of Data Entry
The Contractor shall provide data for NAVFAC MAXIMO using the method detailed below:
DIRECT ENTRY: The Contractor shall manually enter required work order and condition assessment data directly into NAVFAC MAXIMO. The Contractor shall ensure all information is updated by the end of each workday for all work performed.
2.6.6.3 NAVFAC
MAXIMO Access
The process for obtaining access and establishing MAXIMO accounts are detailed in the NAVFAC MAXIMO System Access Procedures provided in J-0200000-09.
Once accounts have been established, MAXIMO can be accessed at https://maximo.navfac.navy.mil.
The Contractor shall provide all necessary computer equipment and Internet Service Provider (ISP) accounts to access MAXIMO for Direct Entry of required data.
A maximum of three (3) MAXIMO accounts will be approved for the Contractor. Changes of personnel requiring MAXIMO accounts more than once per year may result in required compensation to the Government for the administrative costs in processing account requests.
The Contractor shall submit a list of personnel requiring MAXIMO accounts per Section F.
2.6.6.4 NAVFAC
MAXIMO
Training
The Government will provide or make available initial training on NAVFAC MAXIMO to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data.
Additional training will be provided by the Government when there are significant changes to the NAVFAC MAXIMO software or data entry requirements. Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC MAXIMO.
https://maximo.navfac.navy.mil/
Solicitation N6945020Q2809 Page 14 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description
2.6.7 Quality
Management System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:
• Accurate documentation of work processes, procedures, and output measures.
• A systematic procedure for assessing compliance with performance objectives and standards.
• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.
• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.
2.6.7.1 Quality
Management (QM) Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. As part of the acceptance process, the QC Manager shall provide the Government a presentation of the Contractors QM Plan and jointly complete the Government’s QMS Pre-Performance Review Checklist. If any changes are made during the period of performance, the Contractor shall submit a revised QM Plan for acceptance per Section F.
The Contractor’s QM Plan shall include, at a minimum, the following:
• Policy and objectives of Quality Management (QM)
• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications
• Approach to assuring quality of services provided and conformance with performance objectives and standards
• Methods and procedures for effective planning, operation and control of processes and performance of work
• Procedures for inspection and surveillance of services for each spec item.
o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work
• Documentation and records management
• Communication with government (customers)
2.6.7.2 Quality Inspection
and Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file (“QC Inspection File”) shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the KO per Section F within five calendar days of termination of the contract.
2.6.7.3 Quality Inspection
and Surveillance Report
The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events; a tabulated summary and results of the quality inspection and surveillance events performed; and
Solicitation N6945020Q2809 Page 15 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description inspection-driven corrective actions taken and the results attained during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.
2.7 Personnel
Requirements
The Contractor shall comply with the personnel requirements stated below.
2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO necessary to certify their qualifications.
The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract.
The key personnel shall be revised as applicable for the contract.
2.7.1.1 Project Manager
(PM)
The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be available on-site within one hour after the Government's request.
The PM shall have satisfactory relevant experience at a comparable level of responsibility on contracts of similar size, scope and complexity.
2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate that shall be available on-site within one hour after the Government’s request.
The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:
The Quality Manager shall have satisfactory experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity.
The Quality Manager may be the same person as the SSHO.
The Quality Manager cannot be the same person as the Project Manager.
The Quality Manager can be the same person as the SSHO provided that this person does not report to the PM in either capacity.
2.7.1.3 Site Safety and
Health Officer
(SSHO)
The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO).
The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.
A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being
Solicitation N6945020Q2809 Page 16 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for acceptance in consultation with the Safety Office.
The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract.
The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:
The SSHO shall have satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past, and have completed the OSHA 30-hour construction safety class or equivalent.
The SSHO shall maintain competency through 24 hours of formal safety and health related coursework every four years.
The SSHO may be the same person as the project manager but shall have fulfilled the pre-requisite qualification and experience.
The SSHO can be the same person as the Quality Manager provided that this person does not report to the PM in either capacity.
2.7.2 Employee
Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.
2.7.2.1 Employee
Certification and Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.
2.7.2.2 Employee
Appearance
The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
2.7.2.4 Identification as
Contractor Employee
Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
2.7.2.5 Removal of
Employees
The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.
2.7.2.6 Proof of Legal
Residency
No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is submitted per Section F.
2.7.3 Enterprise-wide
Contractor
The Contractor shall report all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract
Solicitation N6945020Q2809 Page 17 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description
Manpower Reporting Application (eCMRA) via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address:
https://www.ecmra.mil
Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk , linked at https://doncmra.nmci.navy.mil.
2.8 Security
Requirements
The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The Contractor shall ensure that all security/entrance clearances are obtained.
2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section F. The list shall include employee’s name, supervisor, company, and level of security clearance.
2.8.2 Vehicles The company name shall be displayed on each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid state license plate that complies with State Vehicle Code. Vehicles shall meet all other requirement of the State Vehicle Code, such as safety standards, and shall carry proof of insurance and state registration, if applicable.
2.8.3 Passes and Badges Contractor employees shall obtain an employee Common Access Card (CAC) or access badge and as required per Section F and installation security policy.
Any required vehicles passes shall be obtained per installation security policy.
Each employee shall wear the Government issued CAC or badge over the front of the outer clothing. When an employee leaves the Contractor's service, all government issued employee CACs, passes or badges shall be returned within 10 calendar days.
2.8.4 Access to
Installation
All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System
(DBIDS).
The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.
2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit.
There are no fees associated with obtaining a DBIDS credential.
The Government performs background screening and credentialing.
Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
https://doncmra.nmci.navy.mil/
Solicitation N6945020Q2809 Page 18 of 45
Performance Work Statement
0200000 - Management and Administration Spec Item Title Description
2.8.4.2 DBIDS Credentials Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.
The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification. The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.
The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:
(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.
2.8.5 Access to
Buildings
The Contractor shall monitor and control access into restricted areas under their responsibility, allowing only those individuals who have been properly cleared into restricted areas or other controlled access areas. The Contractor shall comply with security requirements, plus those imposed by the installation Commander at all times. Personnel with access to special areas will have the appropriate screening and/or security clearance, and personnel requiring routine access to restricted areas will wear special badges authorizing access for those areas. Contractor personnel shall not enter restricted or controlled areas or installation facilities unless specifically authorized in performance of their duties. The Contractor shall secure all buildings and facilities entered during non-duty hours and will secure all building and facilities under the Contractor’s cognizance at the end of each work day or shift period.
2.8.6 Access
Arrangements
The Contractor shall make all arrangements through the appropriate office necessary to obtain access to buildings, facilities and other work areas, and when necessary, arrange for them to be opened and closed by the controlling authority. The Government may issue keys to the Contractor.