Maintenance of Generators and Related Systems, Stennis Space Center, MS
Solicitation number
N6945013R3587
Issued by

About this file

Attachment J-1502000-03-Amend0001

View the file

Other files

File Type Posted
Amendment0002.pdf PDF
J-1502000-02_Site_Map.pdf PDF
J-1502000-05.xlsx XLSX spreadsheet
Amendmt0001-Bldg_1032_ATS_Info.pdf PDF
Amendmt0001-Bldg_1032_ATS_Drawings.pdf PDF
Amendment0003.pdf PDF
Amendment0001.pdf PDF
J_1502000_Dwgs_26-32.pdf PDF
N69450-13-R-3587.pdf PDF
J_1502000_Dwgs_71-73.pdf PDF
J_1502000_Dwgs_46-55.pdf PDF
J_1502000_Dwgs_16-25.pdf PDF
J_1502000_Dwgs_65-70.pdf PDF
J_1502000_Dwgs_33-36.pdf PDF
J_1502000_Dwgs_1-7.pdf PDF
J_1502000_Dwgs_37-45.pdf PDF
J_1502000_Dwgs_8-15.pdf PDF
Amendment_0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amend0004-J-B3-01_ELINS_Gen_NAVO.xlsx XLSX spreadsheet
Amendment_0004.pdf PDF
Amend0004-J-1502000-06_Minimum_PM_HVAC_and_CRUs.pdf PDF
Amend0004-J-1502000-04_Equipment_Inventory_REVISED_18_July_2013.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT J-1502000-03

MINIMUM PREVENTATIVE MAINTENANCE FOR GENERATORS

The following preventative maintenance will be provided to all systems as a minimum:

Generators

1) Periodic facility inspection. Perform physical check on the units each work day. (Minimum of 5 times each week, and before/after significant storms)

2) Monthly load testing A. Operate generator under load. Check voltage and frequency.

B. Publish a monthly report reflecting all maintenance actions performed by contractor and/or the

OEM.

3) Quarterly maintenance A. Engine lubrication system: Visual check for leaks, change lube oil and filters every 12 months or 250 operating hours, whichever occurs first.

B. Engine Air Cleaners: clean or replace filter, as needed.

C. Ignition System: check magneto, set timing, as needed.

D. Governor: check and set speed (to OEM spec), sensitivity, and oil level.

E. Engine Cooling System: Check general condition; check antifreeze and add, if needed. Check belts and hoses.

F. Engine Electric System: hydrometer test battery; clean and lubricate battery posts and cables, load test batteries, check alternator belts, check battery charger for proper operation and output.

G. Engine Fuel System: visually check for leaks, check all visible connections and flexible hoses;

change fuel strainers, replace flexible hoses, as needed, check for water in fuel tank.

H. Engine Exhaust System: Visually check for leaks or corrosion, check drain condensation trap and muffler condition, and drain condensation trap as needed.

I. AC Generator: Visually inspect generator condition, check slip rings and commentator for wear, check lubrication of rear generator bearing.

J. Miscellaneous: Check all instruments for proper operations, check timers and relays for proper operation, check all connections for tightness, check safety circuits shutdowns and alarm systems.

K. Operation: Run engine unloaded. Transfer load to make adjustments, if needed.

L. Clean up: Wipe down unit, remove used fluids and materials from NAVOCEANO location and dispose of them in accordance with EPA, state regulations at contractor facility.

4) Annual maintenance A. All items mentioned in the quarterly maintenance plus;

B. Change all fluids using OEM authorized oil and filter.

C. Perform hydrometer check to insure cooling system protections of minimum 0 degrees. Adjust as required.

D. Check all electrical connections, inspect insulation for fraying and heat damage.

E. Publish annual report for all maintenance performed for year.

UPS

1) Periodic facility inspection. Perform physical check on the units each work day (Minimum 5 times a week and before/after significant storms)

2) Monthly load testing.

(Includes physical inspection of the unit and recording of all readings) A. Publish a monthly report reflecting all maintenance actions performed by the contractor and /or the

OEM.

3) Semi annual maintenance.

A. Record Utility Voltage on each leg.

J-01502000-03 Page 1 of 2 Page 98 of 115

ATTACHMENT J-1502000-03

MINIMUM PREVENTATIVE MAINTENANCE FOR GENERATORS

B. Record current on each leg.

C. Record DC Current on rectifier and battery.

D. Record DC float voltage.

E. Record inverter output voltage.

F. Record generator voltage.

G. Record generator current.

H. Record motor power factor at above load.

I. Record all test point voltage.

J. Record logic lead.

K. Record bypass angle.

L. Check fans M. Check hot sport N. Check m/g vibrations.

O. Check air filters.

P. Check UPS room appearance.

Q. Visual check of obvious signs of over heating.

R. Record number of faults.

S. Record UPS room temperature.

T. Record unit hours.

U. Add OEM approved bearing grease, if needed.

4) Annual maintenance A. All items mentioned in quarterly maintenance, plus;

B. Load test UPS (building load, unless otherwise specified and agreed upon with customer) Batteries

1) Periodic facility inspection. Perform physical check on the units each day. (Minimum 5 times a week and before/after significant storms)

2) Monthly maintenance.

A. Record each battery voltage reading.

B. Record AC ripple C. Inspect each battery for damage D. Publish a monthly report reflecting all maintenance actions performed by contractor and/or the

OEM.

E. Load testing. Physical inspection of units and record all readings per OEM

3) Quarterly maintenance.

A. Record each battery voltage reading.

B. Record AC ripple.

C. Inspect each battery for damage.

D. Record impedance reading of each battery.

4) Annual maintenance.

A. All items mentioned in quarterly maintenance plus B. Annual load test as recommended by OEM.

C. Load test each battery D. Publish annual report covering all maintenance for year.