Amendment 0003_ LMEPP.doc
DOC document 46 KB Posted
- Attached to
- Landbased Mobile Electric Power Plant Federal contract opportunity
- Solicitation number
- N6833519R0105
About this file
This document provides details on Amendment 0003 to a solicitation for a Landbased Mobile Electric Power Plant. The amendment includes answers to six questions received from offerors. Key changes include clarifying that the unit must power E2D aircraft and pass testing at Lockheed Martin, and updating cross-reference tables and attached specifications. The related federal contract opportunity seeks a Landbased Mobile Electric Power Plant to provide 120kVA 115V 400Hz/270VDC/28VDC power at land-based naval aircraft sites. The Naval Air Warfare Center intends to award a fixed-price IDIQ contract with a minimum of four pilot production units in the first delivery order. The solicitation includes CLINs for data rights, testing, logistics, and production units over four years with a maximum of 575 total units. Proposals will be evaluated on technical, past performance, and price factors for best value, with award to the responsible offeror offering best value. The deadline to respond is not provided.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0006_ LMEPP.doc | DOC document | |
| Amendment 0005_ LMEPP.doc | DOC document | |
| Amendment 0004_ LMEPP.doc | DOC document | |
| Amendment 0002 - LMEPP.doc | DOC document | |
| N6833519R0105 LMEPP SECTION B.doc | DOC document | |
| Amendment 0001 - LMEPP.doc | DOC document | |
| N6833519R0105 LMEPP.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0003
1. The following are questions that were received by this Agency and our answers:
Question #1: Does this unit need to power the E2D aircraft? The E2D has a leading power factor which a rotating generator with have problems doing.
Answer #1: Yes, the unit will have to power E2D for ground maintenance power. The question pertaining to the rotating generator was answered in Amendment 0002 Answer #1.
Question #2: Does this unit need to be certified at the Lockheed Martin test facility in Ft. Worth TX?
Answer #2: Yes, the unit will have to pass the SIL F-35 test at Lockheed Martin. This unit will support all Navy and Marine Corp F-35 aircraft.
Question #3: Reference is made to the Table on Page 7 of the “Statement of Work for the Land-Based Mobile Electric Power Plant (LMEPP)” (SOW).
Question #3a: In column “Required Performance (Calendar days After Contract Award)”, are the days fixed or can the days be “within” what is listed?
Answer #3a: The days in the chart on page seven of the SOW are No Later Than (NLT) dates. However, offerors can propose a more aggressive schedule.
Question #3b: Can the IPR’s be combined?
Answer #3b: IPR’s are entrance criteria for Critical Design Review (CDR), Contractor Test Readiness Review (CTRR), Government Test Readiness Review (GTRR) and System Verification Review (SVR)/Production Readiness Review (PRR). Therefore, the IPR’s cannot be combined.
Question #4: Reference is made to the Appendix A of the PMA-260C22/9386 “System Specification.”
Question #4a: Row 3.2.3.22 “Lifting/Tiedown Rings” shows test 4.3.87 should be performed. What verification Stage should the 4.3.87 test be performed in?
Answer #4a: The lifting/Tiedown Ring test is specified in System Specification paragraph 4.3.87 and in MIL-STD-209.
Question #4b: Row 3.2.5.8 “Ice/Freezing Rain” Lists Test paragraph 4.3.97. Test paragraph 4.3.97 page 77 is listed as Operation and Resistance to Humidity.
Answer #4b: Ice/freezing rain is not a required test. The cross verification matrix has been updated to reflect the correct requirement paragraph to the correct test paragraph.
Question #4c: Please check the sequencing between the “Requirement” column and the “Verification para” column. For rows 3.2.5.1 thru 3.2.5.10.
Answer #4c: Cross verification matrix has been updated to reflect the correct requirement paragraph to the correct test paragraph.
Question #5: Paragraph 3.2.6.1.2 of the System specification refers to NAVAIR Drawings 1905AS300 and 1353AS156. Please provide.
Answer #5: NAVAIR Drawings 1905AS300 and 1353AS156 are available. In order to receive copies of the drawings, interested offerors shall request a copy from the office point of contact listed in the RFP. Interested offerors must be U. S. DoD Contractors and must provide the office point of contact with a copy of their current form DD2345, 'MILITARILY CRITICAL TECHNICAL DATA AGREEMENT, if they haven’t already done so. Once received and current JCP certification verified by NAVAIR, the document listed above will be transmitted to you from NAVAIR via the DoD SAFE system, to the data custodian you have identified on the DD Form 2345.
Question #6: Paragraph 3.2.6.4.4 “Modification Plate” refers to NAVAIR Drawing 5SE00363-3. Please provide.
Answer #6: NAVAIR Drawing 5SE00363-3 is available. In order to receive a copy of the drawing, interested offerors shall request a copy from the office point of contact listed in the RFP. Interested offerors must be U. S. DoD Contractors and must provide the office point of contact with a copy of their current form DD2345, 'MILITARILY CRITICAL TECHNICAL DATA AGREEMENT, if they haven’t already done so. Once received and current JCP certification verified by NAVAIR, the document listed above will be transmitted to you from NAVAIR via the DoD SAFE system, to the data custodian you have identified on the DD Form 2345.
2. As a result of the changes above, the System Specification has been revised. The updated version has been attached in Section J. In order to receive a copy of the revised System Specification, interested offerors shall request a copy from the office point of contact listed in the RFP. Interested offerors must be U. S. DoD Contractors and must provide the office point of contact with a copy of their current form DD2345, 'MILITARILY CRITICAL TECHNICAL DATA AGREEMENT, if they haven’t already done so. Once received and current JCP certification verified by NAVAIR, the document listed above will be transmitted to you from NAVAIR via the DoD SAFE system, to the data custodian you have identified on the DD Form 2345.
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
The following have been modified:
EXHIBITS/ATTACHMENTS
DOCUMENT TYPE
DESCRIPTION
PAGES
DATE
Exhibit A, B & L Contract Data Requirements List
09 January 2020 Attachment 1
Statement of Work (SOW)
28 January 2020 Attachment 2
System Specification
10 February 2020 (End of Summary of Changes)