RELEASED AMD0005_N627424R6717.pdf
PDF 245 KB Posted
- Attached to
- DBB Multiple Facility & Infrastructure Project, Lombrum Naval Base, Los Negros Island, Papua New Guinea
- Solicitation number
- N6274224R6717
About this file
This document is an amendment (AMD 0005) to a solicitation (N6274224R6717) for a Design-Build (DBB) Multiple Facility & Infrastructure Project at the Lombrum Naval Base on Los Negros Island, Papua New Guinea.
The key details are:
- The proposal due date has been changed from September 9, 2024 to October 28, 2024, 11:00 AM Thailand time.
- Attachment 1 provides the government's responses to additional questions received.
- Section 2.3 on Evaluation Factors and Proposal Submission Requirements has been revised, including changes to Non-Cost Factor 4 - Technical Solution.
- The evaluation method is Lowest Price Technically Acceptable (LPTA).
- Proposal requirements include price, technical experience, past performance, safety, and technical solution.
- The government intends to award a contract without discussions, but reserves the right to conduct discussions if necessary.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR6065742
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N6274224R6717 DBB Multiple Facility & Infrastructure Project, Lombrum Naval Base, Los Negros Island, Papua New Guinea.
The amendment begins on the next page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 10
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Oct-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6274224R6717
X 9B. DATED (SEE ITEM 11)
26-Jul-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
15-Oct-2024
CODE
NAVFAC ROICC THAILAND (US EMBASSY)
7 SATHORN TAI ROAD
BANGKOK 10120
N62742 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6274224R6717
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMD 5 REVISED NCF 4 AND PPIS
a. The proposal due date is hereby changed from September 9, 2024, to October 28, 2024, no later than 11:00 a.m.
Thailand time.
b. Attachment (1) provides the government’s response to the additional questions received.
c. Section 2.3 Evaluation Factors and Proposal Submission Requirements, Item a., Volume 2, Non-Cost Factor 4 – Technical Solution, (a) Submittal Requirements are revised per the following:
Non-Cost Factor 4 – Technical Solution
Changed from:
(a) Submittal Requirements:
i. Provide a narrative describing the technical solution to the project that meets the requirements of the RFP.
Include the following:
1. Describe the processes and strategies that you will implement in order for this project to be constructed on budget, on schedule, and quality meeting the requirements of the solicitation.
2. Describe the Quality Control (QC) program that you will implement for this project including QC applicability to subcontractors.
3. Describe your supply chain methods, agreements, and/or logistics plan for materials and equipment including long lead items.
Narrative shall not exceed two (2) double-sided pages (or four (4) single-sided pages).
(b) Basis of Evaluation: The Government will evaluate the narrative considering the extent to which the Offeror demonstrates a clear understanding of the architectural and engineering requirements of the project. The Government will evaluate the Offeror's technical solution to determine adherence to the technical requirements of the RFP.
i. Acceptable. Narrative is submitted; the narrative accurately describes the requirements under this factor. The Offeror illustrates an understanding of the statement of the requirements.
ii. Unacceptable. The Offeror did not submit a narrative and/or narrative is incomplete and did not address the requirements under this factor. The Offeror did not illustrate an understanding of the statement of the requirements.
To:
(a) Submittal Requirements:
i. Provide a narrative describing the technical solution to the project that meets the requirements of the RFP.
Include the following:
1. Describe in detail the proposed process and strategies that you will implement in order for this project to be constructed on budget, on schedule, and with the specified quality for a logistically unique location that has constructability challenges (i.e. weather, workforce, local fuel issues).
2. Describe the Quality Control (QC) program that you will implement for this project including QC applicability to subcontractors.
3. Describe in detail your supply chain methods, agreement, and/or logistics plan for shipment of materials and equipment which will mitigate delays experienced by limited supply chain shipping options.
Narrative shall not exceed two (2) double-sided pages (or four (4) single-sided pages).
(b) Basis of Evaluation: The Government will evaluate the narrative considering the extent to which the Offeror demonstrates a clear understanding of the technical solution requirements of the project. The Government will evaluate the Offeror's technical solution to determine adherence to the technical requirements of the RFP.
i. Acceptable. Narrative is submitted; the narrative accurately describes the requirements under this factor. The Offeror illustrates an understanding of the statement of the requirements.
ii. Unacceptable. The Offeror did not submit a narrative and/or narrative is incomplete and did not address the requirements under this factor. The Offeror did not illustrate an understanding of the
The date set for receipt of proposals is changed to October 28, 2024 at 1100am, Thailand Time.
All other paragraphs, provisions, and conditions remain unchanged.
The offeror must acknowledge receipt of this amendment.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 09-Sep-2024 11:00 AM to 28-Oct-2024 11:00 AM.
SECTION 00 22 00 - SUPPLEMENTARY INSTRUCTIONS
The following have been modified:
EVALUATION FACTORS FOR AWARD
Section 002200 – Supplementary Instructions
PART I - GENERAL
1.1 SOURCE SELECTION
This competitive procurement uses source selection procedures to select the responsible Offeror whose proposal conforms to the requirements of the solicitation and is determined to provide the best value to the Government, price and other factors considered. The Government will use the Lowest Price Technically Acceptable (LPTA) method to evaluate proposals submitted in response to this solicitation. The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with Offerors in the competitive range; and to award the contract to the Offeror submitting the lowest priced, technically acceptable (LPTA) proposal.
Per NPGI 15.101-2 (DFARS) Lowest price technically acceptable (LPTA) source selection process. (Business Rule), the number of proposals to be evaluated for technical acceptability may be limited to the lowest priced offers at the discretion of the Contracting Officer. If the number of proposals to be evaluated is limited, the technical proposal shall be provided to the evaluator(s) without any identification of price. If the lowest priced proposal is not found to be technically acceptable then the next lowest price proposal shall be evaluated. If that proposal is also not found to be technically acceptable, then the process described will be conducted again as many times as necessary, until such time as the Government identifies a technically acceptable proposal. The source selection method must be included in the request for proposal. If the Contracting Officer later determines that discussions are necessary, the procedures in FAR 15.306 shall be followed.
1.2 INTENT TO AWARD WITHOUT CONDUCTING DISCUSSIONS
The Government intends to evaluate proposals and award a contract without discussions with Offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
1.3 BASIS OF AWARD
An overall non-price factor rating must be at least “ACCEPTABLE” in order to be eligible for award. An “UNACCEPTABLE” rating in any factor results in the overall non-price factor proposal being rated “UNACCEPTABLE” unless corrected through discussions. An overall non-price factor rating of “UNACCEPTABLE” make a proposal ineligible for award.
Definitions:
Technical Acceptable/Unacceptable Ratings:
Acceptable: Proposal clearly meets the minimum requirements of the solicitation.
Unacceptable: Proposal does not clearly meet the minimum requirements of the solicitation.
Past Performance Acceptable/Unacceptable Ratings:
Acceptable: Based on the Offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the Offeror’s performance record is unknown. Note: In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on pastperformance (see FAR 15.305(a)(2)(iv)). Therefore, the Offeror shall be determined to have unknown past performance.
In the context of acceptability/unacceptability “unknown” shall be considered “acceptable.”.
Unacceptable: Based on the Offeror’s performance record, the Government has no reasonable expectation that the Offeror will be able to successfully perform the required effort.
PART II - EVALUATION FACTORS FOR AWARD
2.1 EVALUATION CRITIERIA
a. The contract resulting from this solicitation will be awarded to the responsible Offeror whose offer, conforming to the solicitation, is determined to be the lowest price technically acceptable (LPTA) proposal based on the evaluation factors set forth in the solicitation.
b. “Relevant” means similar to the acquisition in terms of size, scope, and complexity and nature of the work being solicited. The Government will only consider projects for construction services of the type described in non-cost factor 1 – Offeror Experience, below.
c. Past performance information on “relevant projects” meeting the definition in paragraph (b) will constitute the primary consideration in the Government’s evaluation under non-cost factor 2 – Past Performance. The Government may, however, review and consider past performance information on other projects as made available to the Government from other sources such as the Contractor Performance Assessment Reporting
System (CPARS) and inquiries with previous clients / owners. The Government will determine the relevance of the past performance information received on other projects, as well as consider the source, context and currency of such information in its evaluation.
d. Offerors who submit past performance and experience information of a parent, sister, predecessor or other affiliated company must describe what involvement such company will have on the acquisition. The proposal should clearly indicate how the resources of the parent, sister, predecessor or other affiliated company – its workforce, management, facilities, or other resources – will be provided or relied upon for contract performance.
e. The Contracting Officer may discount favorable past performance and experience of a subcontractor unless the prime contractor clearly provides, in its proposal, evidence of a binding teaming agreement or other contractual agreement which creates legal responsibility on the part of the subcontractors.
f. In the case of an Offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)). Therefore, the Offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability “unknown” shall be considered “acceptable.”
g. The Government, in compliance with FAR 15.305(a)(2)(ii), Offerors are authorized to provide information on problems encountered on the identified contracts and the Offeror’s corrective actions. The Government shall consider this information, as well as information obtained from any other sources, when evaluating the Offeror’s past performance.
2.2 PRICE EVALUATION
The price proposal will be evaluated to determine the reasonableness and completeness of the Offeror’s proposal.
The Contracting Officer may conduct price realism if the Contracting Officer determined that it is necessary.
Unrealistically low (or high) proposed price or unbalanced prices, may be grounds for eliminating a proposal from competition either on the basis that the Offeror does not understand the requirement or has made an unrealistic or unreasonable proposal.
2.3 EVALUATION FACTORS AND PROPOSAL SUBMISSION REQUIREMENTS
a. The Offeror’s proposal shall contain a response to each of the following evaluation factors and shall be in the form prescribed by this solicitation. The solicitation requires the evaluation of price and non-cost factors in two volumes listed below:
Volume 1: Price Factor Volume 2: Non-Cost Factor 1 – Offeror Experience
Non-Cost Factor 2 – Past Performance Non-Cost Factor 3 – Safety Non-Cost Factor 4 – Techinal Solution
b. The distinction between past performance and Offeror experience is experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past performance relates to how well a contractor has performed.
c. The following describes each evaluation factor, submittal requirements and basis for assigning ratings:
Volume 1:
(1.1) Price Factor
(a) Solicitation Submittal Requirements:
i. The Standard Form 1442 with Blocks 14 through 20c completed, signed, and dated;
ii. Acknowledge any and all amendments issued under this solicitation either by annotating it in Block 19 of the SF 1442 or signing each SF 30
iii. A completed Price Schedule for all CLINs;
iv. A completed Bill of Quantities (BOQ, Exhibit D) showing price breakdown for CLINs.
Provide in both PDF and Excel formats;
v. Completed Representations and Certifications, to include a copy of the electronic annual representations and certifications thru System for Awards Management (SAM) at www.sam.gov;
vi. Responsibility Determination and Financial Capability, as specified in Paragraph 4;
vii. Evidence of active SAM.gov registration at www.sam.gov.
(b) Basis of Evaluation: The Government will evaluate price based on the total price of all priced
CLINS. Analysis will be performed by one or more of the following techniques to ensure a fair, reasonable and realistic price:
i. Comparison of proposed prices received in response to this RFP;
ii. Comparison of proposed prices with the Independent Government Estimate (IGE);
iii. Comparison of proposed prices with available historical information.
Volume 2:
(2.1) Non-Cost Factor 1 - Offeror Experience:
(a) Submittal Requirements: Submit a minimum of three (3) and a maximum of five (5) construction projects for the Offeror that best demonstrates Offeror experience on relevant projects that are similar size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as similar construction with the following relevant characteristics:
a. Similar in Size: Construction Projects between $500,000 and $5,000,000 in final construction cost.
b. Similar in Scope: Construction of a single story (or more) reinforced concrete structure building with a minimum size of 800 SM.
c. Similar in Complexity: Construction projects involving multiple trades performed in Southeast Asia, Nepal, Maldives, Timor-Leste, Australia, Oceania, or Papua New Guinea.
Projects submitted for the Offeror shall be completed within the past (8) years of the date of issuance of this RFP. If submitting an ongoing construction project, the project should be at least 80% complete at the time of proposal submission. A project is defined as a construction project performed under a single contract.
The Offeror Experience Project Data Sheet in the form of Exhibit B is MANDATORY and SHALL be used to submit project information. Except as specifically requested, the Government will not consider information submitted in addition to this form. Individual blocks on the form may be expanded; however, total length for each Offeror Experience Project Data Sheet shall not exceed one (1) double-sided page (or two (2) single-sided pages) claimed for past performance. Data sheets for each project should not exceed two (2) pages.
For all submitted projects, the description of the project shall clearly describe the scope of work performed and the relevancy to the project requirements of this RFP (i.e., unique features, area, construction methods).
If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity or the Joint Venture partners. Offerors are still limited to a total of five (5) projects combined.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement in the performance of the contract in order for the past performance information of the affiliate/subsidiary/parent/LLC/LTD member companies to be considered. The proposal shall state specific commitments of technical resources (e.g., personnel, equipment) that the affiliate/subsidiary/parent/LLC/LTD member companies commit to the performance of this contract. In particular, the proposal will clearly state the specific commitments of resources of the affiliate/subsidiary/parent/LLC/LTD member that will be located at the worksites and company offices in the city/area of the project. The proposal shall also describe specific roles of the affiliate/subsidiary/ parent/LLC/LTD member companies in terms of the work it will either self-perform or manage on behalf of the Offeror in performance of the contract. Any projects submitted in excess of the five (5) will not be considered.
(b) Basis of Evaluation: The basis of evaluation will include the Offeror’s demonstrated experience and depth of experience in performing similar construction projects with the relevant characteristics defined in the solicitation submittal requirements for this non-cost factor above. The assessment of the Offeror’s relevant experience will be used as a means of evaluating the capability of the Offeror to successfully meet the requirements of the RFP.
The Government will only review five (5) projects. Any projects submitted in excess of the five (5) for Offeror experience will not be considered. The Government will not evaluate information exceeding the first two (2) pages for each Project Data Sheet.
i. Acceptable. The contractor has demonstrated construction experience in performing similar construction projects with the relevant characteristics defined in the solicitation submittal requirements for this non-cost factor.
ii. Unacceptable. The contractor did not submit Offeror Experience Project Data Sheets, the submitted data sheets did not demonstrate relevant construction experience performing similar construction projects with the relevant characteristics defined in the solicitation submittal requirements for this non-cost factor, or the Offeror submitted less than three
(3) relevant projects.
(2.2) Non-Cost Factor 2 - Past Performance:
(a) If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 1 Offeror Experience. If there is not a completed CPARS evaluation, then submit Past Performance Questionnaires (Exhibit C) for each project included in Factor 1. The Offeror should provide completed Past Performance Questionnaires (PPQ) in the proposal. Offerors shall not incorporate by reference into their proposal PPQs previously submitted for other RFPs.
However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project(s). The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government’s point of contact, Contract Specialist.
Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 – Offeror Experience. Offerors may also address any adverse past performance issues. Explanations shall not exceed two (2) double-sided pages (or four (4) single-sided pages) in total.
The Government reserves the right to contact references for verification or additional information. The Government’s inability to contact any of the Offeror’s references or the references unwillingness to provide the information requested may affect the Government’s evaluation of this factor.
Performance award or additional information submitted will not be considered.
(b) Basis of Evaluation: This evaluation will consider how well the Offeror’s team performed on relevant projects submitted under Factor 1 – Offeror Experience and may also consider past performance on other projects currently documented in known sources. In addition to the above, the Government reserves the right to obtain information for use in the evaluation of past performance from any and all sources including sources outside of the Government.
Other sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval Systems (PPIRS) using all CAGE/UEI numbers of Contractors who are part of a partnership or joint venture identified in the offeror’s proposal, inquiries of owner representative(s), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the offeror.
The Government will consider the recency and relevance of the information, the source of the information, context of the data, and general trends in the Contractor’s performance. This evaluation is separate and distinct from the Contracting Officer’s responsibility determination.
The assessment of the Offeror’s team’s past performance will be used as a means of evaluating the Offeror’s team’s probability to successfully meet the requirements of the RFP.
i. Acceptable. The Offeror has satisfactory or better ratings in the Contractor Performance
Assessment Reporting System (CPARS) or on Past Performance Questionnaires (PPQ) (Exhibit C) for at least three (3) projects rated acceptable in Factor 1. In the case of an Offeror without a record of recent and relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the Offeror may not be evaluated favorably or unfavorably on past performance. Therefore, the Offeror shall be determined to have “unknown” past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”
ii. Unacceptable. The Offeror was not rated satisfactory or better in the Contractor Performance Assessment Reporting System (CPARS) or on Past Performance Questionnaires (PPQ) (Exhibit C) for at least three (3) of the projects determined to be relevant and acceptable under Factor 1 – Offeror Experience, or the Government has found less than satisfactory documentation for the contractor’s performance using Government databases. Additionally, Offerors will be rated unacceptable if they do not provide a CPARS if it exists for any project submitted under Factor 1 – Offeror Experience. Submitting a PPQ in place of a CPARS when a CPARS exists will result in unacceptable rating.
(2.3) Non-Cost Factor 3 - Safety:
(a) Submittal Requirements: The Offeror shall submit a safety narrative that fully describes the safety management system that they will use to oversee the safety compliance and performance of self-performed and subcontractor (if utilized) performed work. The narrative should describe any innovative methods that will be employed to ensure and monitor safe work practices at self-performed and all subcontractor (if utilized) performed work. Additionally, the narrative should describe the methods Offeror will use to execute an effective safety program including mishap prevention techniques and processes, encouraging employee reporting of unsafe conditions, and preventing unsafe work activities that could lead to near-miss or injury mishaps. The technical approach to safety narrative shall be limited to five (5) pages.
(b) Basis of Evaluation: The Government will evaluate the narrative to determine how the Offeror will implement and oversee its safety program for protection of the prime contractor and subcontractor (if utilized) personnel. The Government will evaluate the Offeror’s plan to monitor safety performance of the prime contractor and all subcontractors (if utilized) during contract performance, with a focus on specific management practices that will be utilized for providing deliberate safety program management and mishap prevention. The Government will only evaluate up to the first five (5) pages submitted.
i. Acceptable. The Offeror demonstrates an understanding of the requirement to provide for the safety of prime and subcontractor (if utilized) personnel, the narrative describes the methods Offeror will use to execute an effective program that includes mishap prevention techniques and processes, encouraging employee reporting of unsafe conditions, and prevents unsafe work activities that could lead to near-miss or injury mishaps.
ii. Unacceptable. The Offeror’s narrative does not demonstrate an understanding of the requirement to provide for the safety of prime and subcontractor (if utilized) personnel, the narrative does not describe the methods Offeror will use to execute an effective program that includes mishap prevention techniques and processes, encouraging employee reporting of unsafe conditions, and does not prevent unsafe work activities that could lead to near-miss or injury mishaps, or the Offeror did not submit a sufficient narrative within the first five (5) pages.
(2.4) Non-Cost Factor 4 - Technical Solution:
(a) Submittal Requirements:
i. Provide a narrative describing the technical solution to the project that meets the requirements of the RFP. Include the following:
1. Describe the processes and strategies that you will implement in order for this project to be constructed on budget, on schedule, and quality meeting the requirements of the solicitation. Describe in detail the proposed process and strategies that you will implement in order for this project to be constructed on budget, on schedule, and with the specified quality for a logistically unique location that has constructability challenges (i.e. weather, workforce, local fuel issues).
2. Describe the Quality Control (QC) program that you will implement for this project including QC applicability to subcontractors.
3. Describe your supply chain methods, agreements, and/or logistics plan for materials and equipment including long lead items. Describe in detail your supply chain methods, agreement, and/or logistics plan for shipment of materials and equipment which will mitigate delays experienced by limited supply chain shipping options.
Narrative shall not exceed two (2) double-sided pages (or four (4) single-sided pages).
(b) Basis of Evaluation: The Government will evaluate the narrative considering the extent to which the Offeror demonstrates a clear understanding of the architectural and engineering technical solution requirements of the project. The Government will evaluate the Offeror's technical solution to determine adherence to the technical requirements of the RFP.
i. Acceptable. Narrative is submitted; the narrative accurately describes the requirements under this factor. The Offeror illustrates an understanding of the
ii. Unacceptable. The Offeror did not submit a narrative and/or narrative is incomplete and did not address the requirements under this factor. The Offeror did not illustrate an understanding of the statement of the requirements.
2.4 FINAL SELECTION
All Offerors will be evaluated for each of the technical (non-cost) Factors and the responsible Offeror submitting the lowest priced technically acceptable offer will be selected for contract award. A responsibility determination shall be made for each presumed awardee. A presumed awardee may be determined to be non-responsible if it has an excessive amount of current awards or ongoing projects, is currently behind or has excessive rework issues on existing contracts, or is otherwise deemed an increased risk to the US Government for unsuccessful performance.
(End of Summary of Changes)
DBB Multiple Facility Infrastructure Project, Lombrum Naval Base, Papua New Guinea
Amendment 0005 Attachment 01 - Answers to the PPIs
No. Reference Question Government Response 1 PART B, Technical
Specifications,
10.3.10 Batching
and Mixing Plants.
Can the concrete batch plant on Lombrum NB be used/contracted by the selected NAVFAC Contractor?
The current concrete batch plant will start demobilizing operations on 16 Oct 2024. The Contractor awarded this contract will be responsible to for all concrete supply requirements.
2 PART B, Division 01 Specifications, 01 14 00 Work Restrictions.
Are there any Department of Home Affairs, PNG DF, and local community expectations on political monitoring and utilization of the skills and capability of the local community?
Hiring local national personnel is encouraged, but not required, per the Defense Cooperation Agreement, Article 13, Paragraph 1 (Solicitation Amendment 0003). There is community expectation that contractor's working at Lombrum Naval Base to utilize local personnel. The current contractor on Lombrum NB has hired local personnel which has led to an increased range of local community trade skills for future work. This engagement with the local community has fostered favorable community relationship with the Papua New Guinea Defence Force (PNGDF) and mitigated local demonstration/protests.
3 PART B, Division 01 Specifications, item 19
TEMPORARY
UTILITIES and item 01 50 00 Temporary Construction Facilities and Controls.
Are there any permits required to use the Base Barge Landing Facility? Will the Gov't fund a barging contract if its needed to mitigate shipping logistics risk?
No permits required at Lombrum NB for barging operations. The Contractor awarded this contract will need to communicate with the PNGDF on use of the barge landing facility. All barging contracts required for this contract will be the responsibility of the Contractor.
4 Part B, Division 01, Para 28 Safety and Occupational Health Requirements, sub-para 6 Temporary Facilities and item 01 50 00 Temporary Construction Facilities and Controls
Can the current workers housing/camp be used by the selected NAVFAC Contractor? If yes, does the Gov't have an available room/bed information?
The Lombrum Construction Camp will be available for the awarded Contractor to use. The camp currently has 68 single rooms and 186 other beds in 2, 3, and 4 bed combinations. The Camp kitchen has capacity to feed 250 personnel. The awarded Contractor will be responsible for all payments to utilize the camp facilities.
DBB Multiple Facility Infrastructure Project, Lombrum Naval Base, Papua New Guinea
Amendment 0005 Attachment 01 - Answers to the PPIs
5 PART B, Division 01 Specifications, item 19
TEMPORARY
UTILITIES and item 01 50 00 Temporary Construction Faclities and Controls.
Are there available cranes and heavy equipment agreements that can be used/contracted by the selected NAVFAC Contractor?
There is no heavy lifting equipment at Lombrum NB.
The awarded Contractor will be responsible for all equipment requirements to complete this contract.
| N627424R6717-0005_sf30 released |
| Attachment 1 of AMD 0005_Answers to PPIs_Final |