This document is an amendment to a solicitation for the DBB Multiple Facility & Infrastructure Project at the Lombrum Naval Base in Papua New Guinea, solicitation number N6274224R6717. The key changes are:

  1. The proposal due date has been extended from September 3 to September 9, 2024 at 11:00 AM Thailand time.

  2. The submittal requirements for Non-Cost Factor 1 - Offeror Experience have been revised. The range of acceptable construction project sizes has been expanded from $1,000,000 - $4,000,000 to $500,000 - $5,000,000, with at least one project required to be at least $2,000,000. The scope and complexity requirements have also been expanded to include a wider geographic region.

All other terms and conditions of the solicitation remain unchanged. Offerors must acknowledge receipt of this amendment.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR6065742

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N6274224R6717 DBB Multiple Facility & Infrastructure Project, Lombrum Naval Base, Los Negros Island, Papua New Guinea.

The amendment begins on the next page.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Sep-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6274224R6717

X 9B. DATED (SEE ITEM 11)

26-Jul-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Sep-2024

CODE

NAVFAC ROICC THAILAND (US EMBASSY)

7 SATHORN TAI ROAD

BANGKOK 10120

N62742 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6274224R6717

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMD 4 REVISED NCF 1

a. The proposal due date is hereby changed from September 3 to September 9, 2024 no later than 11:00 a.m.

Thailand time.

b. Part 1, Section 2.3 Evaluation Factors and Proposal Submission Requirements, Item a., Volume 2, Non-Cost Factor 1 – Offeror Experience, (a) Submittal Requirements are revised per the following:

Summary of Changes

Amendment 0004

On Page 17 of 41 under items (a) Submittal Requirements, (2.1) Non-Cost Factor 1 – Offeror Experience

Change from

a. Similar in Size: Construction Projects between $1,000,000 and $4,000,000 in final construction cost. One project must be at least $2,000,000. Any project outside this range may not be considered.

b. Similar in Scope: Construction of a single story reinforced concrete structure building with a minimum size of 800 SM.

c. Similar in Complexity: Construction projects involving multiple trades performed in Southeast Asia, Australia, Oceania, or Papua New Guinea.

To

a. Similar in Size: Construction Projects between $500,000 and $5,000,000 in final construction cost. One project must be at least $2,000,000. Any project outside this range may not be considered.

b. Similar in Scope: Construction of a single story (or more) reinforced concrete structure building with a minimum size of 800 SM.

c. Similar in Complexity: Construction projects involving multiple trades performed in Southeast Asia, Nepal, Maldives, Timor-Leste, Australia, Oceania, or Papua New Guinea.

All other paragraphs, provisions, and conditions remain unchanged.

The offeror must acknowledge receipt of this amendment.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 03-Sep-2024 11:00 AM to 09-Sep-2024 11:00 AM.

(End of Summary of Changes)

N6274224R6717