DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC
258 MAKALAPA DR STE 100
PEARL HARBOR HI 96860-3134
RFP N62742-23-R-1302
Notice No. 2
5 July 2023
PRE-PROPOSAL QUESTIONS & ANSWERS
WON 1663847, FY24 MCAF PROJECT PAF180500, BOMBER APRON,
ROYAL AUSTRALIAN AIR FORCE (RAAF) BASE TINDAL,
AUSTRALIA
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
1. In the Specifications Section 02 61 13, Paragraph 1.3, third sentence, there is reference to an
Appendix Site Engineering Investigation SEI report. Please provide us with a copy of this report.
ANSWER: See Summary on drawing C-002.
2. In the Specifications Section 02 61 13, Paragraph 1.3, third sentence from the bottom, it states: “The excess 60,000 cubic meters of PFAS contaminated soil will be stockpiled long term on the base in an agreed designated location.” Please provide us with a location for this stockpile so we may adequately price the placement of these materials.
ANSWER: Please refer to drawing G-105 Stockpile notes and spoil location site plan insert.
3. In the Specifications Section 02 61 13, Paragraph 1.3, first sentence, it states: “The work consists of excavation and temporary storage of approximately 72,000 cubic meters of PFAS contaminated soil.” If 60,000 cm of the PFAS is to be hauled to a long-term stockpile location, would we need to place it in a temporary storage area? It would be much better to haul to a long-term storage area only.
ANSWER: Please refer to drawing G-105 Stockpile notes. As per the notes, site-won material must be tested and assigned a PFAS contamination category prior to reuse or stockpile of material. The contractor is responsible for the design and management of stockpiles, including coordination with KC-30 project. Temporary storge may or may not be required, depending on during required to confirm testing and PFAS contamination category, as well as coordination with KC-30 project.
4. To assist in developing better quantities for the civil construction, would it be possible to get the CAD drawings for this project?
ANSWER: CAD files will not be provided.
5. If a soil report was developed for this project, could we get a copy of it?
ANSWER: Boring log details are provided in Drawing sheets B-001 through B-605.
6. In the RFP, Section 00 21 16 Instructions to Proposers, 1.1d, it is stated that “an electronic copy of the price and technical proposals shall be submitted in .pdf format on a CD-ROM with the paper copy of the subcontracting plan.” Since we do not see mention of a subcontracting plan elsewhere in the RFP, can we assume that this was unintentionally included and not a part of the RFP requirements?
ANSWER: Confirmed. Submission of a subcontracting plan is not required. See Amendment
No. 0001, which revised Section 00 21 16 of the RFP to indicate that a CD-ROM shall be submitted with the paper copy of the price and technical proposals.
7. Drawing MP011 shows three (3) each Double HPV Pits (Unpaved Areas) and one (1) each
HPV Pit (Paved Areas) for the new DN250-SS Hydrant Loop Piping, while drawings CX101, CX104, CX107, and CX108 show two (2) each Double HPV Pits (Unpaved Areas) and three (3) each HPV Pits (Paved Areas). Please confirm the correct quantities for the Double HPV Pits (Unpaved Areas) and HPV Pits (Paved Areas) required for the new DN250-SS Hydrant Loop Piping.
ANSWER: Response deferred.
8. In Detail C4/MP502, there are two (2) “Note 9” shown at the new DN250 flanged connection inside the crossover valve pit. Please clarify “Note 9.” Note #9 currently does not exist in the Sheet Notes for Drawing MP502.
9. Specification Section 33 52 43.13, Paragraph 2.1.3.3, is calling out insulating gaskets with fluoroelastomer (FKM), commonly referred to as Viton, O-ring sealing surfaces, mylar insulating sleeves, and phenolic insulating washers. The Insulating Flange Kit Detail on C3/EK502 shows G10 insulating gasket, G10 insulating sleeves, and G10 insulating washers, which is different than Specification Section 33 52 43.13, Paragraph 2.1.5.4. Please clarify and confirm if the contractor is to provide insulating flange kits per Specification Section 33 52 43.13, Paragraph 2.1.3.3, or per Detail C3/EK502 with all G10 material.
10. On Drawings CD107 and CD108 it shows a section called a “Buffer Zone for Temporary
Ramp to Tie in with Existing Levels prior to KC30 Project Construction.” Please confirm that this area is not included in this contract and this work will be done by others.
ANSWER: Temporary ramp is included within scope of works, refer to drawing G-301, as demonstrated in the Phase 1 -2024 detail, it is required to enable grading of natural surface to existing swale. It is the contractor’s responsibility to propose their preferred construction methodology.
11. On Drawing CD501 in the demolition sections shown on Detail A1 there is a note on each of the details that states “salvage existing subbase for reuse.” Are we required to remove all of this material if not required in the replacement of the new sections? One of the details shows 400 to 600 mm of this material; what are we to assume?
ANSWER: Salvage existing base layer material and reuse as aggregate subbase in accordance with 32 11 20 on the USAF aircraft strength rigid apron pavement.
Salvage existing subbase material and reuse as select fill in accordance with 31 23
00.00 20 on the USAF aircraft strength rigid apron pavement, USAF tug-strength rigid pavement and USAF shoulder strength flexible pavement.
It is recommended that the selected tenderer over excavates to salvage the existing subbase material for reuse and to enable subgrade and fill preparation in accordance with the design requirements.
Per note 2 on drawing CD501 detail A1, depth presented is based on boring data, boring data is presented in drawings B-001 through B-605.
12. On Drawing C-167 there is a note that states, “KC-30 Project will provide flexible pavement between Taxiway A edge and P500 Apron Rigid Pavement.’ Can you provide us with a schedule as to when the KC-30 contractor will be grading and paving this buffer zone area?
ANSWER: Proposals should be based on the phases of works provided on drawing G-301.
Also see Note 1 on drawing G-301. Following contract award, coordination with the KC-30 project and Base stakeholders will be required.
13. General, Will the client be supplying a design model and natural surface model to the offerors during the solicitation period? The model will assist in calculating excavation and fill quantities required to be priced.
ANSWER: CAD file will not be provided.
14. Volume 2 Drawings - For the Fuel Hydrant Works, is an earth stake required for all pits?
Refer to Note 2 on drawing CX502
ANSWER: Yes, an earth stake is required for all pits.
15. P500 Final Design Specifications, Section 3.1.3.3, RFP Page 204 of 1278 and Section
1.6.10.2 PFAS Contamination, RFP Page 365 of 1278
The RFP specification references the PFAS Construction Risk Assessment (GHD 2022) and the Preliminary Construction Environmental Management Plan. Can you please provide a copy of these two plans?
16. Drawing CP501 - For Pavement Type 3, can you please confirm the AMC1 cutback bitumen prime application rate?
ANSWER: Final application rate to be approved by Contracting Officer on site in the range between 0.23 L and 0.54 L/square meter of residual bitumen, as per specification 32 12 13 section 3.3.2.
17. Drawing CP501 - For Pavement Type 5, can you please confirm the prime type and application rate?
ANSWER: Prime may be emulsified or cutback bitumen as per UFGS 32 12 13. Final application rate to be approved by Contracting Officer on site in the range between
0.23 L and 0.54 L/square meter of residual bitumen, as per specification 32 12 13 section 3.3.2.
18. Drawing CP501 - For Pavement Type 3 & 5, can you please confirm the binder type for
AC14 Asphalt?
ANSWER: C320 binder per specification 32 12 15.13 section 2.3.
19. Drawing CP108 - Referring to the Pavement Type 5 extent, it appears that the Access Road extends further north, can sheet 5 be provided?
ANSWER: The full extent of the sealed access road is shown on C-410.
20. Drawing CD502 - Can NAVFAC please provide additional information on the two buildings that are to be demolished? The Information provided in drawing CD502 is currently insufficient to scope the work. Will bidders be able to take photos of the structures and share these with potential demolition contractors? Is it possible to receive the building photos prior to the site visit to allow time for the demolition contractor to review?
ANSWER: As per drawing CD502, the buildings to be demolished are 725 (Starch Hangar) &
830 (Air Movements Terminal). In accordance with Document 00 21 16, paragraph 1.18, Site Visit, “Visitors may ONLY take photos of the project site and are prohibited from taking photos and videos of the nearby runway/taxiway/hangars/etc. during the site visit.”
21. Drawings S-501 & C-510 & C-511 - Please confirm dimensions of Penstock Pits shown on drawings S-501 & C-510 & C-511 as the drawings reference each other and no drawings detail the pit size except for S-501, which details a pit of 5.2m max by 1.8m max by 2.05m deep.
ANSWER: The dimensions of the penstock pits will be dependent on the penstock gates that the awardee provides. Drawing S-501 specifies a maximum internal width and length to cater for the penstock system the awardee elects to install.
22. Drawing CM107 and CM108 - Please provide additional detail for the dashed line marking on the apron as detailed in drawing CM107 and CM108. Please supply line details for the black dash lines (point A20 to A24) and grey dash lines (point A21 to A23).
23. Specification Section 03 30 00, Page 7, 1.15 - The Defense Base Act Waiver for Australia expires on 22 July 2023. Will the waiver be renewed? Please confirm that we should proceed with the understanding that this will be renewed for the duration of this project.
ANSWER: The U.S. Office of Defense Pricing and Contracting is processing a Defense Base
Act (DBA) Waiver Request package for Australia. Please monitor the U.S.
Department of Labor DBA website.
24. Drawing CS504 Section B4 - An inground Base Slab for SQID1&2 shows a nominal 200mm thick slab on drawing CS504 Section B4. Typically, the contractor is responsible for installing as per the manufacturer's specification to ensure the warranty is not voided. The manufacturer's specification does not typically include a concrete base slab. If a base slab is required by the Client's Design, please confirm slab details including concrete mix type and reinforcing details.
ANSWER: Please refer to Drawing CR522 for cover slab requirements.
25. Drawing CR516 Section A1 & Drawing MP503 - Drawing CR516 section A1 for the Fuel
Hydrant Pipe Surround Concrete refers to MP503 for details of the pipe surround concrete.
Drawing MP503 doesn't contain the concrete detail. Please provide the fuel hydrant pipe surround concrete detail?
ANSWER: Concrete surrounding the pipe is the Lean Mix Concrete shown on detail C1 on sheet CX501.
26. Drawing CR506, sealing detail C2 - Drawing CR506 for the Concrete Pavement Joints: For the sealing detail C2, please confirm that the joint sealing depth is 10mm rather than 100mm
ANSWER: Response deferred.
27. Drawing CP501 - Please provide geotextile strength and class for Pavement Type 6
(Unsealed Access Tracks) on drawing CP501?
28. Drawing CR506, Note 1 - Drawing CR506 for the Concrete Pavement Joints. Note 1, states that saw cutting is required for the Lean mix base. Can the location of the saw cuts be detailed in a drawing?
ANSWER: The note refers to the saw-cut depth in the concrete pavement when supported by a lean mix concrete base. The lean mix concrete base is not required to be saw-cut.
29. General - We understand there are two worker camps on RAAF Tindal for the Australian
Dept. of Defense construction forces which operate 24/7. Has NAVFAC made arrangements for a worker camp for the bomber apron workforce and other US-funded work?
ANSWER: Please refer to accommodation notes on drawing G-105. Offerors are to price as per the drawings, with man camp located off site.
30. Standard Form 1442 - Form 1442, states “D. Offers providing less than 180 calendar days for
Government acceptance after the date offers are due will not be considered and will be rejected.” Since the evaluation criteria is acceptable/ unacceptable for Factors 1-4 and then low price. Given the extraordinary long bid validity of 180 days and the escalating inflation on labor, materials and equipment in Australia, contractors have to factor additional costs into the bid, which unnecessarily increases the total cost. Can the government simply adjust the evaluation criteria to open the price envelope first and select the low bidder and then evaluate that bidders’ technical factors? This could accelerate the evaluation time schedule with a bid validity of 90 days, thereby reducing the contractors and sub-suppliers risk dollars.
ANSWER: Block 13. ADDITIONAL SOLICITATION REQUIREMENTS, Item D, remains unchanged.
31. a. Price Proposal (RFP Page 8 of 82) - The price proposal requirements list the following requirements: SF1442, Bid Guarantee, Reps and Certs, Pre-Award Survey, and Partnerships, however there is no specific call out for the Price Proposal Schedule (RFP page 5 of 82). Will the Government please advise where it would like us to include the Price Proposal Schedule in our final submittal?
ANSWER: There are four (4) pages to the Standard Form (SF) 1442, Solicitation, Offer, and
Award. As indicated on the top of the Price Proposal Schedule, it is a continuation of the SF1442 (pages 3 of 4 and 4 of 4).