J_9_QnA_SGA_VR_12Nov2026.xlsx
XLSX spreadsheet 23 KB Posted
- Attached to
- USNS SACAGAWEA (T-AKE 2) VRA KR
- Solicitation number
- N6264927RK001
About this file
This file is a Questions and Answers (Q&A) document from Amendment 1 of a federal solicitation for voyage repair availability services on USNS SACAGAWEA (T-AKE 2).
The Q&A sheet contains 21 substantive question-and-answer entries submitted by contractors (Hanwha Ocean Co., Ltd., Unithai Shipyard and Engineering Ltd., Seatrium Repair & Upgrades Pte. Ltd., and Mitsubishi Heavy Industries, Ltd.) regarding Work Item specifications and requirements. Key clarifications provided include: WI 583 and WI 407 are cancelled; WI 0651B (Lifeboat Davit Inspection) is not required as davits were certified in September; two overhauling kits are required for two High Pressure Air Compressors under WI 0521; the contractor must procure updated CAT laptop and software for training under WI 0506; all six tanks (not four) must be serviced under WI 0154; performance dates cannot be changed (15 December 2026 to 6 January 2027); contractors should bid on WI 563B and WI 565B only; hydrostatic testing and internal visual examination of all cylinders is mandatory under WI 0565B; WI 0525 revised to include only compressor replacement without overhaul; and surface preparation under WI 0173 must meet SSPC-SP1 guidance if using power tooling. Multiple work items requiring inspection reports, calibration lists, and technical documentation were addressed, with some responses indicating that supporting materials were provided or would be obtained from previous service providers and original equipment manufacturers.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question No. | Contractor | WI No. | Para. No. | Question | Answer | Amendment | |
| 1 | Hanwha Ocean co., Ltd. | 0583 | N/A | The work specification assigns the removal, transportation, reinstallation, and operational testing of the Detector Units to the Requesting Activity, while the filter changeout is assigned to the Performing Activity. | |||
| Please clarify the contractor's specific scope of work under this Work Item, as no contractor responsibilities are explicitly identified in the specification. | WI 583 is cancelled. | 0001 | |||||
| 2 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0407 | 2.2.1 | Can the Government provide the complete GPETE equipment list referenced in Enclosure 2.2.1, including equipment description, manufacturer, model, serial number, and location, as the current enclosure only contains placeholders? | WI 407 is cancelled. | 0001 | |
| 3 | UNITHAI SHIPYARD AND ENGINEERING LTD. | N/A | N/A | Based on the previous experience, WI 0651B – TAKE-CCSI-Annual Lifeboat Davit Inspection is typically performed in conjunction with WI 0651A – TAKE-CCSI-Annual Lifeboat Inspection (T-AKE 1-12). | |||
| Could you please confirm whether WI 0651B has been intentionally excluded from the current scope of work and is not required for this maintenance period? | Lifeboat davits were certified in September. | 0001 | |||||
| 4 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0521 | 3.1.2&3.3 | Section 3.1.2 specifies a quantity of two (2) High Pressure Air Compressors, whereas Section 3.3 (Bill of Materials) lists only one (1) Overhauling Kit. | |||
| Could you please clarify whether the required quantity of Overhauling Kits should be two (2), one for each compressor? | THIS WILL require a second rebuild kit as well | 0001 | |||||
| 5 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0506 | 7.6 | Section 7.6 requires eight (8) hours of onsite technical training using the vessel's CAT laptop and software. |
Based on our subcontractor's experience during previous maintenance, the CAT laptop and software currently available onboard are outdated, making it difficult to conduct effective training using the latest CAT Electronic Technician (ET) software.
Could you please confirm whether the vessel currently has an updated CAT laptop and ET software available for training?
| If not, please advise whether the vessel intends to procure the updated equipment and software prior to the commencement of the maintenance period. | Request to have Contractor to procure the updated laptop and software. | 0001 | ||
| 6 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0154 | Please clarify the location of tanks: |
para 3.1: Four (4) Salt water ballast tanks 6-45-1,6-45-2,6-54-1,6-54-2
| Enclosure 2.2.2: Cargo Potable Water Tank 3-79-2, Cargo Potable Water Tank 3-80.5-2 | We are doing all six (6) tanks. | 0001 | ||
| 7 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0503 | Please see the response from Appleton OEM: |
I will need to review our schedule but it is unlikely we can support this short POP (15.Dec.2026 - 06.Jan.2027).
Please provide alternate range of dates for our consideration / planning.
Thank you.
Regards,
| Appleton Marine, Inc. | We cannot change the dates. | 0001 | ||||
| 8 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0563A & 0563B | Please clarify what Work Item we should bid for between 563A or 563B. | Perform WI 563B | 0001 | |
| 9 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0565A & 0565B | Please clarify what Work Item we should bid for between 565A or 565B. | Perform WI 563B | 0001 | |
| 10 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0565B | From the last SGA V/R package in August, the work item requested to perform a hydro test and internal visual examination of all cylinders. |
However, Para 7.5 requests to conduct a hydrostatic test of 10% of the cylinders again.
| Would it be acceptable to conduct a hydro test through CFR? | Perform the requirement as stated in the WI. Inspection and Hydro test is a must. | 0001 | |||||
| 11 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0655 | Please provide a previous inspection/service report. | Report provided | 0001 | ||
| 12 | UNITHAI SHIPYARD AND ENGINEERING LTD. | 0656 | Please provide a previous inspection/service report. | Survetic Korea completed the last certification. If they reach out to them at the same time, waiting response from the ship. | 0001 | ||
| 13 | Seatrium Repair & Upgrades Pte. Ltd. | 0561A | Please provide a list on para 2.3 and 2.4, and the quantity of Para 3.3. | Calibration list attached. | 0001 | ||
| 14 | Seatrium Repair & Upgrades Pte. Ltd. | 0633 | For bidding purposes, please provide pictures of separator plates in a bad condition. | See attached. | 0001 | ||
| 15 | Seatrium Repair & Upgrades Pte. Ltd. | 0525 | 7.4 | Please get some clarification on the compressor that needs to be worked on for the WI525 – In the beginning the York Marine AB VSB 151 L is called out. However, in section 7 (note after 7.4) a HP air compressor is being called out. |
And what is the required scope: replacement only, or replacement and overhaul?
| The same note states that MSC will arrange for refurbishment, so please confirm whether the overhaul/refurbishment is outside the contractor's scope. | WI was revised, HP air was deleted. | 0001 | |||||
| 16 | Seatrium Repair & Upgrades Pte. Ltd. | 0173 | Due to environmental concerns, we would like to propose to do power tooling only for surface preparation. Please confirm if this is acceptable. | As long as it meets the SSPC-SP1 guidance. | 0001 | ||
| 17 | Mitsubishi Heavy Industries, Ltd. | 0301 | 2.1.3 | Reqiured PARA 2.1.3 ECDIS POWER MODIFICATION Drawing – 420-8938678 | |||
| 18 | Mitsubishi Heavy Industries, Ltd. | 0525 | Will this work item in the current VR cover only the compressor replacement, or should the compressor overhaul also be included in the scope of work? | Only compressor replacement. | 0001 | ||
| 19 | Mitsubishi Heavy Industries, Ltd. | ||||||
| 20 | Mitsubishi Heavy Industries, Ltd. | ||||||
| 21 | Mitsubishi Heavy Industries, Ltd. | ||||||
| 22 | UNITHAI SHIPYARD AND ENGINEERING LTD. | ||||||
| 23 | UNITHAI SHIPYARD AND ENGINEERING LTD. | ||||||
| 24 | |||||||
| 25 | |||||||
| 26 | |||||||
| 27 | |||||||
| 28 | |||||||
| 29 | |||||||
| 30 | |||||||
| 31 | |||||||
| 32 | |||||||
| 33 | |||||||
| 34 | |||||||
| 35 | |||||||
| 36 | |||||||
| 37 | |||||||
| 38 | |||||||
| 39 | |||||||
| 40 |
File details come from the government source that posted it. Updated .