This document provides details for an Architectural and Engineering Indefinite Delivery Indefinite Quantity contract solicitation. The solicitation seeks proposals for architectural design services for various facilities located in California, Arizona, Nevada, Colorado, New Mexico, and Utah but potentially worldwide. Key work includes design of new construction, renovation, repair and sustainable features. Proposals are due no later than December 15, 2020 via DoD SAFE. The minimum contract value is $5,000 and maximum is $99 million over eight years. Evaluation criteria include experience, past performance, quality control, capacity and knowledge of the locality. The solicitation is a 100% small business set-aside for firms with average annual receipts less than $8 million. The Naval Facilities Engineering Command is the contracting agency.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 1 – Dated December 2, 2020
THE FOLLOWING CHANGES ARE INCORPORATED INTO THE NOTICE LISTED BELOW:
1. The definition of the “recent” period is revised to extend from five years to seven years prior to the
SF330 due date (December 15, 2020).
Definitions: RECENT or SEVEN-YEAR PERIOD: The prescribed timeframe for this solicitation that refers to the period of time for which projects may be submitted for consideration as relevant experience, relevant past performance, etc. The seven-year period is calculated by counting back seven years from the SF330 due date.
SF330, Part 1, Section F, Block 24: “Recent” is defined as professional A-E services completed within the past seven years prior to the SF330 due date.
2. The description of the requirements for registering in sam.gov is updated to include the following statement:
Note: all submitting contractors must be registered in sam.gov.
3. The contracting office name and address are updated:
A-E firms meeting the requirements described in this announcement are invited to submit a completed SF330 package per the submission requirements to the office shown below. The submittal package (1 electronic SF330 in .pdf format) shall be received via DoD SAFE marked with this office information: (NAVFAC Southwest Design and Construction Contracting Core -
Navy, Attn: Michael Hyatt Jr, Code RRA30.MH, 750 Pacific Highway, San Diego, CA 92132) no later than, 2:00 P.M Pacific Standard Time on Tuesday, December 15, 2020. ONLY DOD
SAFE .PDF FORMAT SF330 PACKAGES WILL BE ACCEPTED. Submittals received after this date and time will not be considered.
Criterion 4: PAST PERFORMANCE Submission Requirements: Submit an A-E Contractor
Appraisal Support System (ACASS), Contractor Performance Assessment Report System
(CPARS), or a Past Performance Questionnaire (PPQ) evaluation for each project listed under
Criterion 2. If a completed ACASS/CPARS evaluation is available, it shall be submitted with the completed SF330 package. If there is not a completed ACASS/CPARS evaluation, the PPQ included with this notice is provided for the Offeror or its team members to submit to the client for each project. AN OFFEROR SHALL NOT SUBMIT A PPQ WHEN AN ACASS/CPARS
EVALUATION IS AVAILABLE. If an ACASS/CPARS evaluation is not available, ensure correct phone numbers and email addresses are provided for the client point of contact.
Completed PPQs should be submitted with your SF330. If the A-E is unable to obtain a completed PPQ from a client for a project before the response date set forth in this notice, the A-
E should complete and submit with their response the first page of the PPQ (Attachment #1), including contract and client information for the respective projects. A-Es should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government point of contact, Naval Facilities
Engineering Systems Command Southwest, Code RRA30.MH, Attn: Michael Hyatt Jr, via email at michael.d.hyatt1@navy.mil, prior to the response date. A-Es shall not incorporate by reference mailto:michael.d.hyatt1@navy.mil into their response, ACASS/CPARS or PPQ evaluations previously submitted in response to other A-E services procurements. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Submitted
ACASS/CPARS and PPQ evaluations will not be counted as part of the 30 page limitation and shall be attached to the SF330, behind the SF330 Part II document.
4. The words “separately from all other correspondence relating to this Synopsis,” are added to the instructions for submission of SF330s using the DoD SAFE “Drop-off” feature:
Instructions for submission of SF330s using the DoD SAFE “Drop-off” feature are provided below:
1. There are no user accounts for DoD SAFE. In order to submit an SF330 in response to this
Synopsis, Offerors shall submit their point of contact (POC) name and email address via email, separately from all other correspondence relating to this Synopsis, no later than 7 days before
SF330 due date, to the Contract Specialist identified below to obtain a “Request Code” for DoD
SAFE “Drop-off” of the SF330.
5. The words: “NAVFAC SW does not intend to respond to Requests For Information (RFIs) submitted after 17:00 (5:00 PM) local time on December 7, 2020” and “Note: the Interested Vendors List is only viewable if you are logged in to beta.sam.gov and your account is associated with an entity” are added to the final paragraph of the Notice:
THIS IS NOT A REQUEST FOR PROPOSAL. ALL INFORMATION NEEDED TO SUBMIT
SF330 DOCUMENTS IS CONTAINED HEREIN. NO SOLICITATION PACKAGE,
TECHNICAL INFORMATION, OR BIDDER/PLAN HOLDER LIST WILL BE ISSUED. It is the offeror’s responsibility to check beta.sam.gov (FedBizOpps), which is the NAVFAC electronic solicitation website, for any revisions to this announcement or other notices. An
Interested Vendors List is available via the FedBizOpps website, www.beta.sam.gov, under this solicitation number. Note: the Interested Vendors List is only viewable if you are logged in to beta.sam.gov and your account is associated with an entity. Address inquiries via email:
michael.d.hyatt1@navy.mil. NAVFAC SW does not intend to respond to Requests For
Information (RFIs) submitted after 17:00 (5:00 PM) local time on December 7, 2020. *** END
OF ANNOUNCEMENT ***
N62473-21-R-1401
ALL INFORMATION NEEDED FOR INTERESTED PARTIES TO SUBMIT A STANDARD FORM
(SF) 330, ARCHITECT-ENGINEER QUALIFICATIONS, IS CONTAINED HEREIN. THERE IS NO
SEPARATE REQUEST FOR PROPOSAL (RFP) PACKAGE TO DOWNLOAD.
This is a 100% small business set-aside procurement. A Sources Sought Notice was posted, and a market research study was conducted by NAVFAC Southwest, which included an assessment of relevant qualifications and capabilities of potentially qualified firms. Upon review of the Market Research and
Sources Sought analysis, the U.S. Small Business Administration (SBA) representing NAVFAC SW in
San Diego determined that a 100% small business set-aside procurement is appropriate. The NAVFAC
SW small business office concurs with the SBA determination. Architect-Engineer (A-E) services are required for a firm-fixed-price (FFP) Indefinite-Delivery, Indefinite-Quantity (IDIQ) contract for
Architectural Design Services. Projects under this contract will occur at various military installations located in the NAVFAC Southwest Area of Responsibility (AOR): California, Arizona, Nevada, Colorado, New Mexico, and Utah; but may be available worldwide as approved by the NAVFAC SW
Procuring Contracting Officer. The preponderance of work will be at Navy and Marine Corps installations in Southern California. The offeror/contractor must demonstrate adequate in-house staffing, capable of self-performing (see definition) at least 50 percent of the cost of the contract as required by
FAR Clause 52.219-14(c)(1) Limitations on Subcontracting (Mar 2020).
Required A-E services for this project include various multi-discipline Architectural Design Service projects including, but not limited to, new construction and renovation/repair (see definitions) of a variety of facilities and sites. Types of projects may include, but are not limited to, commercial, institutional, industrial, operational and training, research and development, medical, and quality of life facilities. A-E services shall be in accordance with the scope of the contract, applicable references, and Unified Facilities
Criteria (UFC), such as, High Performance and Sustainable Building Requirements, Fire Protection
Engineering, Antiterrorism Standards, etc. The number of design task orders per fiscal year may vary and may involve surges of multiple projects with overlapping delivery dates.
Primary A-E services required:
a. Prepare Requests for Proposal (RFPs) for Design-Build projects;
b. Prepare fully-designed plans and specifications;
c. Site investigations to support new development of facilities on raw land and/or redevelopment of existing facilities on existing sites;
d. Conduct studies, reports, and evaluations related to the designs of new buildings/facilities and/or renovation/repair of existing buildings and facilities; and
e. MILCON Preliminary Design Authority (PDA) efforts, to include DD1391 preparation, 35% design, concept sketches, preliminary site plans with building footprint, geotechnical report, site civil survey information and other similar planning and programming-related documents.
Secondary A-E services required:
a. Preparation of cost estimates;
b. Provide Construction Contract Support Services (CCSS);
c. Provide Post Construction Award Services (PCAS); and
d. Conduct technical reviews of Government-prepared RFP packages for Design-Build projects and/or fully designed plans and specifications.
Support A-E services that may be required:
a. Coordination of various technical disciplines such as civil, structural, mechanical, electrical, fire protection, and geotechnical; and
b. Identification and abatement methods of existing asbestos-containing materials, lead-based paint, and other hazardous materials.
The maximum contract value may not exceed $99,000,000 aggregate in total. The minimum guarantee for the contract is $5,000. The minimum guarantee for the entire contract term (including option years) will be satisfied either by a minimum payment, or by issuance of a task order. The minimum value of individual task orders under this contract is $5,000. The maximum value of individual task orders under this contract is $2,000,000. No dollar limit will be placed per-year under this contract. Multiple task orders may be awarded with similar completion schedules and overlapping delivery dates. The contract will be for a base period of two (2) years with two (2) option periods of three (3) years each for a maximum of eight (8) years. The hourly rates will be negotiated for each performance period. The
Government may exercise the option period unilaterally. The estimated start date is June 2021. The
NAICS Code for this procurement is 541310 (Architectural Services) and the annual small business size standard is $8 Million.
The Government makes no representation as to the number of task orders or the actual amount of work to be ordered under this contract. The contractor is not guaranteed work in excess of the minimum guarantee. Firms that provide Architect-Engineer services for a task order issued under the resulting contract are prohibited from participating on the subsequent construction contract. This limitation also applies to subsidiaries/affiliates of the firm.
Selection Criteria and Submittal Requirements
The Selection of Architects and Engineers Act (formerly Brooks Architect-Engineer Act) (PL 92-582) and Federal Acquisition Regulations (FAR) Part 36.6 selection procedures apply. The evaluation and selection will be based on the following criteria:
Criterion 1: Professional Qualifications
Criterion 2: Specialized Experience and Technical Competence
Criterion 3: Capacity
Criterion 4: Past Performance
Criterion 5: Location and Knowledge of the Locality
Criterion 6: Quality Control
Criterion 7: Volume of Work
Submitted SF330s (Architect-Engineer Qualifications) and related information will be evaluated to determine the most highly-qualified firm based on the evaluation criteria. Criteria 1 and 2 are considered most important and of equal importance to each other; Criteria 3, 4, 5, and 6 are of lesser importance than
Criteria 1 and 2, and are listed in descending order of importance; Criterion 7 is of lesser importance than
Criteria 3, 4, 5, and 6, and will be used as a tiebreaker among firms considered to be technically equal.
Evaluation of past performance and experience may include information provided by the firm, customer inquiries, Government databases, and publicly available sources. Failure to provide requested data, accessible points of contact, or valid phone numbers may result in a firm being considered less favorably in the evaluation. In evaluating an offeror’s capability, the Government will consider how well the offeror complied with these instructions. All projects provided in the SF 330 shall have been completed by the office/branch/individual team member who will be actually performing the work under this contract.
Projects not performed by the office/branch/individual team member will be excluded from evaluation consideration.
Submission Requirements
The SF330 (Part 1) submission is limited to thirty (30), 8.5”x11” pages (see definition). Information submitted beyond the stated page limitation, unless otherwise excepted, will not be considered in the evaluation. Submit one (1) electronic copy of the SF 330 (Adobe Acrobat .pdf format) (Parts 1 and 2) via
DoD SAFE, addressing the selection criteria information below. Requested items not counted as part of the 30-page limitation are as noted herein.
SF330, Part 1, Sections B and C:
In Block 5, in addition to the name of the firm, provide the firm’s Data Universal Numbering System
(DUNS) number issued by Dun and Bradstreet Information Services. In Block 9, in addition to the name of the firm, provide the DUNS number of each proposed team member.
SF330, Part 1, Section D: Organization Chart:
In addition to requirements stated in the SF330 Instructions (i.e., show names and roles of all proposed key personnel and firms they are associated with), identify on the submitted organization chart the relationships and lines of authority of the proposed team members, including key subconsultants. (Note:
All individuals listed on the organization chart are not required to have a resume in Section E, such as administrative or lower level engineering positions.) This chart is not counted as part of the 30-page limitation. This chart must be affixed to the submittal to avoid separation in handling.
SF330, Part 1, Section E, Resumes of Key Personnel, CRITERION 1, PROFESSIONAL
QUALIFICATIONS
The evaluation will consider the professional qualifications of proposed key personnel (see definition) in providing relevant primary and secondary A-E services for project types required by this contract. All key personnel must be professionally registered/accredited (see definition) in their discipline. The prime A-E firm shall have a minimum of three (3) professional registered architects on staff to perform the anticipated work of this contract. The designated Program Manager (see definition) shall be a professional registered architect and be an employee of the prime A-E firm. Key personnel demonstrating experience with projects located in California may be considered more favorably in the evaluation (see evaluation
Criterion 5).
Provide brief resumes of proposed key personnel who will specifically perform the relevant primary and secondary A-E services for relevant project types listed for this contract. Non-relevant information will not be considered. Resumes of personnel performing only support services (as listed above) are not required and will not be considered. For each key personnel, indicate highest level of education achieved, number of years engaged in the discipline, and submit a copy of the applicable current professional registration/accreditation certificate (personnel with registration in multiple states need only submit a copy from one state). Resumes will be counted in the 30-page limitation; certificate copies will not be counted in the 30-page limitation.
Key personnel resumes shall include, but not be limited to, individuals who will perform the functions of
Program Manager, Design Quality Control Manager (DQCM), and Sustainable Design Manager (see definitions). The prime A-E firm shall submit a minimum of three (3) professional registered architects on staff. Resumes of these individuals shall demonstrate their depth of experience in their respective roles.
Each resume shall include a maximum of five (5) recently completed projects (see definitions) that best demonstrate the individual’s qualifications in performing the relevant primary and secondary A-E services listed for this contract. Projects not meeting these requirements will not be considered. Submit only projects in which the key personnel performed a significant role. Submit a brief description of the project within the SF330, Section E, Block 19. For each project, describe: scope and cost; role and responsibilities of the key personnel; and the specific A-E services performed that are relevant to the primary and secondary services required by this contract.
SF330, Part 1, Section F, Example Projects, CRITERION 2, SPECIALIZED EXPERIENCE AND
TECHNICAL COMPETENCE
The evaluation will consider specialized experience and technical competence of the proposed team relative to the primary and secondary A-E services and project types required by this contract. Projects completed by the prime A-E firm identified in Part I may be given more consideration in the evaluation process than projects of proposed subcontractors. Projects completed in California may be considered more favorably in the evaluation process (see evaluation Criterion 5).
Submit maximum ten (10) recently completed projects (see definitions), that best demonstrate the relevant experience of the proposed team in performing the primary and secondary A-E services for project types required by this contract. Projects shall have been performed by the office(s)/branch(es) identified in
SF330, Part 1, Section C. Projects not meeting these requirements will not be considered. For government contracts, include the full contract number and task order number, if applicable.
In SF330, Part 1, Section F, Block 24
Submit a description of the project, including:
1) Type of project and its relevance to this contract;
2) Specific relevant A-E services performed;
3) Construction cost;
4) Relevant sustainable features (see definition) incorporated in the project; and
5) A-E fee. Firms with multiple offices shall indicate which office/branch performed the A-E services.
Additional requirements:
- A minimum of one (1) project shall demonstrate recent, relevant experience with projects having professional fees between $800,000 and $1,500,000.
- A minimum of one (1) project shall demonstrate recent, relevant experience with projects having professional fees greater than $1,500,000.
- A minimum of one (1) Design-Bid-Build (Plans & Specs) project to demonstrate recent, relevant design experience with new buildings/facilities.
- A minimum of one (1) project to demonstrate recent, relevant design experience with renovation/ repair of existing buildings/facilities.
Note: A project experience shall be considered either primarily a new construction or renovation/repair, but not both. A single project may satisfy more than one of the above minimum requirements except for experience in new construction and renovation/repair. “Recent” is defined as professional A-E services completed within the past seven years prior to the SF330 due date. If the proposed team is a joint venture
(JV), submit information for relevant projects completed by the JV entity. If the JV does not have shared experience, individual projects shall be submitted for each of the JV partners. Do not exceed the ten (10) project limitation in the JV project count. In cases where the project was performed by a JV, but all JV partners are not on the team proposed for this contract, specifically describe the relevant work performed by the JV partner(s) teaming on this contract. In all cases, clearly describe the specific relevant work self-performed by the proposing firm and the firm’s roles and responsibilities on the project; do not include work that is not attributable to the proposing firm. If the project description does not clearly delineate the work performed by the entity/entities teaming on this contract, the project may not be considered.
SF330, Part 1, Section G, Key Personnel Participation in Example Projects
Submit in accordance with the SF330 Instructions. From the total projects listed in Section F, provide maximum ten (10) projects.
SF330, Part 1, Section H; Additional Information requested by Agency
Address the remaining Criteria 3 through 7; additional sheets may be used (up to the 30-page limitation), if required. See submission requirements. Clearly identify the Criterion number and title.
CRITERION 3, CAPACITY
The evaluation will consider the Offeror’s capacity to accomplish the work in the required time.
Submit a narrative that demonstrates the Offeror’s capacity to accomplish work in required time frames.
Describe: 1) Present workload and capability to integrate work under this contract with other commitments; 2) Capacity to accomplish multiple task orders simultaneously with overlapping delivery dates.
CRITERION 4, PAST PERFORMANCE: The evaluation will consider the Offeror’s past performance on relevant Government and/or commercial projects regarding quality of work, cost control, compliance with performance schedules, and customer satisfaction, with emphasis on example projects presented in
Section F. The evaluation will be based on past performance assessments and other available past performance information. Points of contact provided in the proposal may be contacted. Where there is no record of past performance, the proposal will be evaluated neither favorably nor unfavorably. Superior performance ratings on relevant projects may be considered more favorably in the evaluation.
Firms are encouraged to provide information on problems encountered and the corrective actions taken on projects submitted under Criterion 2. Firms may also address any adverse past performance issues.
Information shall not exceed two double-sided pages (or four single-sided pages) in total.
Submission Requirements: Submit a narrative to demonstrate Offeror’s past performance in effective project cost control: 1) Describe the firm’s cost estimating procedures and project cost control methods;
2) Provide budget amounts, final construction cost estimates, and actual construction contract award amounts for at least five (5) projects submitted in response to Criterion 2. Explain any differences in the amounts.
Submit an A-E Contractor Appraisal Support System (ACASS), Contractor Performance Assessment
Report System (CPARS), or a Past Performance Questionnaire (PPQ) evaluation for each project listed under Criterion 2. If a completed ACASS/CPARS evaluation is available, it shall be submitted with the completed SF330 package. If there is not a completed ACASS/CPARS evaluation, the PPQ included with this notice is provided for the Offeror or its team members to submit to the client for each project. AN
OFFEROR SHALL NOT SUBMIT A PPQ WHEN AN ACASS/CPARS EVALUATION IS
AVAILABLE. If an ACASS/CPARS evaluation is not available, ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your
SF330. If the A-E is unable to obtain a completed PPQ from a client for a project before the response date set forth in this notice, the A-E should complete and submit with their response the first page of the PPQ
(Attachment #1), including contract and client information for the respective projects. A-Es should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government point of contact, Naval Facilities
Engineering Systems Command Southwest, Code RRA30.MH, Attn: Michael Hyatt Jr, via email at michael.d.hyatt1@navy.mil, prior to the response date. A-Es shall not incorporate by reference into their response, ACASS/CPARS or PPQ evaluations previously submitted in response to other A-E services procurements. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation. Submitted ACASS/CPARS and PPQ evaluations will not be counted as part of the 30 page limitation and shall be attached to the SF330, behind the SF330 Part II document.
For projects provided as experience in Section F, list and provide copies of any applicable performance awards received (not counted in the 30-page limitation). Clearly indicate to which Section F project the award applies; otherwise, the information may not be considered.
CRITERION 5, LOCATION AND KNOWLEDGE OF THE LOCALITY: The evaluation will consider the team’s location, demonstrated knowledge of and project experience within the geographic areas where projects are anticipated for this contract. The preponderance of the work will be at Navy and Marine
Corps installations in Southern California. Prime A-E firms with a local office in California may be considered more favorably in the evaluation.
Submission Requirements: Submit a narrative that demonstrates the team’s knowledge of, and project experience within, the geographic locations for anticipated projects on this contract. Include: 1) Location of the Offeror’s main office and any branch offices and subconsultant offices that will be utilized for this contract; 2) Description of team’s knowledge of, and project experience within, the targeted geographic areas; and 3) Description of team’s availability and ability to ensure timely response to requests for onsite support.
CRITERION 6, QUALITY CONTROL: The evaluation will consider the Offeror’s Quality Control (QC) program for ensuring technical accuracy of the A-E work product. Firms are encouraged to describe the process used for checking designs for accuracy, consistency and effective cross coordination among multiple design disciplines. Firms shall identify the Quality Control Manager and any other key personnel responsible for the QC program, along with their roles and responsibilities. Firms shall describe the firm’s quality control program for management of subconsultants. For offerors who are joint ventures and/or teams with offices in a variety of locations, describe how the QC effort will be implemented across the various team offices, as well as which office(s) the QC program will be managed/coordinated from.
Describe the plans/methods to ensure effective quality control and communication between offices. Firms that demonstrate a QC process that will minimize the government’s quality assurance (QA) effort in reviewing the A-E’s work product may be considered more favorably in the evaluation.
Submission Requirement: Submit a narrative that describes: 1) Offeror’s QC program that is used to ensure technical accuracy and effective coordination of the A-E’s work product across all disciplines; 2)
Process used for checking documents for coordination errors, omissions, conflicts, and discrepancies;
tracking changes and incorporating review comments.
For offerors who are joint ventures and/or teams with offices in a variety of locations, describe how the
QC effort will be implemented across the various team offices. Describe from which office the QC program will be managed/coordinated and the plan/methods to ensure effective QC and communication between offices.
CRITERION 7, VOLUME OF WORK: The evaluation will consider the volume of DoD work awarded to the prime A-E in the past 12 months with the objective of equitably distributing contracts among A-E firms, including minority-owned firms and firms without prior DoD contracts.
Submission Requirements: Provide a list of DOD contracts/task orders (with contract dollar amount) of work awarded in the past 12 months to the firm identified as the Prime A-E on the submitted SF330. Joint venture (JV) entities should list awards to the JV and separately list awards to each JV partner for the time period. Do not include work performed as a subcontractor. Firms with multiple offices shall indicate which branch office completed each project.
SELECTION INTERVIEW REQUIREMENTS: Personal interviews may be scheduled for firms slated as most highly qualified. Firms slated for interviews may be asked to explain or expand on information contained in their SF 330 submittal. Elaborate presentations are not desired. Note that joint ventures (JV) slated for interviews will be required to provide a copy of their JV Agreement prior to the interview.
ADDITIONAL INFORMATION: All information must be included in the submitted SF 330 package
(cover letter, attachments, and excess information beyond the 30-page limit, unless otherwise excepted, will not be considered in the evaluation).
System for Award Management (SAM) Database: In accordance with FAR 52.204-7, System for Award
Management Registration (Oct 2018), ensure your firm has an active SAM entity record. SAM is a
Federal Government-owned and -operated free web site that consolidates the capabilities of CCR (Central
Contractor Registration), ORCA (Online Representations and Certifications Application), and EPLS
(Excluded Parties List System). SAM is the primary Government repository for current and prospective federal awardee information. Please complete your SAM registration for the same name and address identified as the submitting office on your SF330, with its associated CAGE code and DUNS or
DUNS+4. Registration instructions and information can be accessed from the SAM home page at:
https://www.sam.gov. Note: all submitting contractors must be registered in sam.gov.
In accordance with the Selection of Architects and Engineers (formerly the Brooks Architect-Engineer
Act), the A-E firm must be a registered/licensed architectural and/or engineering firm. Provide evidence that your firm, subcontractor or proposed team members are permitted by law to practice the profession of
Architecture and/or Engineering, i.e., State registration number, a brief explanation of the firm’s licensing in states that do not register firms, etc. Firms will be required to submit proof of required professional A-
E registration/licensure prior to the interview phase of the selection process. This documentation is not counted as part of the 30-page limitation.
A-E firms meeting the requirements described in this announcement are invited to submit a completed
SF330 package per the submission requirements to the office shown below. The submittal package (1 electronic SF330 in .pdf format) shall be received via DoD SAFE marked with this office information:
(NAVFAC Southwest Design and Construction Contracting Core - Navy, Attn: Michael Hyatt Jr, Code
RRA30.MH, 750 Pacific Highway, San Diego, CA 92132) no later than, 2:00 P.M Pacific Standard Time on Tuesday, December 15, 2020. ONLY DOD SAFE .PDF FORMAT SF330 PACKAGES WILL BE
ACCEPTED. Submittals received after this date and time will not be considered.
Instructions for submission of SF330s using the DoD SAFE “Drop-off” feature are provided below:
1. There are no user accounts for DoD SAFE. In order to submit an SF330 in response to this Synopsis, Offerors shall submit their point of contact (POC) name and email address via email, separately from all other correspondence relating to this Synopsis, no later than 7 days before SF330 due date, to the Contract
Specialist identified below to obtain a “Request Code” for DoD SAFE “Drop-off” of the SF330.
Contract Specialist: Michael Hyatt Jr Email: michael.d.hyatt1@navy.mil
Note: The Government does not intend to respond to emails for drop-off request codes submitted less than 7 calendar days before the SF330 due date shown in the solicitation.
2. No later than 4 calendar days prior to the SF330 due date, the Contract Specialist or Contracting
Officer will send a “Request Code” to the Offeror’s specified POC via the email address provided. Only https://www.sam.gov/ the Offeror’s identified POC will be able to drop off the SF330 and related revisions in DoD SAFE.
Failure to provide accurate POC information will preclude the Offeror from using DoD SAFE.
3. Offerors are instructed to submit their complete SF330 package in one (1) single file, formatted in
Portable Document Format (PDF) with a .pdf file extension.
4. To submit the SF330, the Offeror will go to the DoD SAFE website at https://safe.apps.mil, accept the user agreement, click “Drop-off,” and enter the 12-digit “Request Code” that was provided by the
Contract Specialist or Contracting Officer. The system will allow for inclusion of a short note to the
Government recipient. The Offeror will then click to add their SF330 file, or drag and drop the file. Click
“Drop-off Files” to send the file to the Government recipient. Confirm that the file does not contain classified information and click “OK.” Once the file is uploaded, an email will be sent to the Government recipient notifying them of the “drop-off.” [Additional details can be viewed in the DoD SAFE User
Guide available at https://safe.apps.mil/about.php]. The DoD SAFE system will record the date and time of SF330 submission. The date and time of SF330 submission recorded in DoD SAFE shall govern the timeliness of any submission.
The maximum allowable file size for DoD SAFE is 8GB. DoD SAFE recommends using Firefox, Chrome, or Edge browsers. Internet Explorer is not recommended. Please note that Internet Explorer limits uploads to 2GB.
Read the following information carefully.
It is an Offeror’s responsibility, when transmitting its SF330 package electronically (via DoD SAFE), to ensure timely delivery by transmitting the package sufficiently in advance of the time set for receipt of
SF330’s to allow for timely receipt by the Government no later than the date and time stated in this
Synopsis. Offerors shall allow adequate time to upload and send files, which may be slower for non-DoD users, and to avoid other technical difficulties that may be encountered. An Offeror risks the late receipt and rejection of a SF330 where it delays transmitting its SF330 until the last few minutes before the time set for receipt. SF330’s that are received after the stated date and time in Synopsis will not be considered.
Offerors are responsible for submitting their SF330 in the format specified, consistent with requirements stated elsewhere in this Synopsis. Offerors are asked to submit only the information/exhibits required.
Page limits, if stipulated, must be adhered to. Files that cannot be opened, or are otherwise missing the required content, are the responsibility of the Offeror.
No parking or offloading of SF330s is available at the Government facility.
THIS IS NOT A REQUEST FOR PROPOSAL. ALL INFORMATION NEEDED TO SUBMIT SF330
DOCUMENTS IS CONTAINED HEREIN. NO SOLICITATION PACKAGE, TECHNICAL
INFORMATION, OR BIDDER/PLAN HOLDER LIST WILL BE ISSUED. It is the offeror’s responsibility to check beta.sam.gov (FedBizOpps), which is the NAVFAC electronic solicitation website, for any revisions to this announcement or other notices. An Interested Vendors List is available via the FedBizOpps website, www.beta.sam.gov, under this solicitation number. Note: the Interested
Vendors List is only viewable if you are logged in to beta.sam.gov and your account is associated with an entity. Address inquiries via email: michael.d.hyatt1@navy.mil. NAVFAC SW does not intend to respond to Requests For Information (RFIs) submitted after 17:00 (5:00 PM) local time on December 7, 2020.*** END OF ANNOUNCEMENT ***
DEFINITIONS OF TERMS:
BRANCH OFFICE: An office of a firm located separately from a firm’s other office(s) and having a separate address.
COMBINED PROJECT(S): Projects with multiple starting and ending points, performed under separate task orders, delivery orders, or multiple contracts combined in a single description. No credit will be given for work performed under IDIQ or other multiple-award type contracts in the aggregate (multiple projects completed under more than one task/delivery order).
COMPLETE PROJECT: 100% plans and specifications signed by a professional Architect or Engineer and ready to advertise for construction with final cost estimate; or 100% complete RFP/deliverable documents. Do not include any construction phase support services such as Post Construction Award
Support (PCAS).
DESIGN-BID-BUILD: Refers to the traditional project delivery method where design and construction are sequential and contracted for two separate contracts and two contractors. One is for an A-E design contract and the other is for a construction contract.
DESIGN-BUILD: Refers to combining design and construction in a single contract with one prime contractor. Projects that require only shop drawing level effort are not design-build projects.
DESIGN QUALITY CONTROL MANAGER: The individual who is responsible for management of the design quality control program for the A-E IDIQ contract. The DCQM shall be a registered/licensed architect or engineer with minimum five (5) years of design experience.
FIRM: Any individual, firm, partnership, corporation, association, or other legal entity permitted by law to practice the professions of architecture or engineering.
JOINT VENTURE (JV): A legal business entity formed between two or more companies (parties) to undertake the performance activities of a contract together.
KEY PERSONNEL: The personnel of the offeror’s team who are the registered/licensed/ accredited professionals in their respective disciplines, directly responsible for the design and management of the relevant contract work. These are the individuals for which resumes are being submitted.
NEW CONSTRUCTION: Refers to projects where the work primarily involves building of entirely new facilities (or new additions/expansions to existing facilities where a new structure and foundation are provided as part of the new addition/expansion).
OFFEROR: Refers to the contractor submitting the proposal, including joint ventures, designated in
Section C of Standard Form (SF) 330 (Architect-Engineer Qualifications) as the prime contractor.
OFFEROR’S TEAM: Refers to the Offeror (see definition) and the other firm(s)/entity(ies) proposed to perform the work of the contract together as a team, as listed in the Offeror’s submitted SF330, Section C.
PAGE: Refers to one printed side of a piece of paper (e.g., 15 pieces of paper printed on both sides equates to 30 total pages). Minimum font size is 10 point.
PAST PERFORMANCE: Relates to how well an Offeror has performed; e.g., the quality of work accomplished, cost control, schedule compliance, customer satisfaction. Past performance is distinct from experience.
PROFESSIONAL REGISTRATION/ACCREDITATION: Professional registration/license/ accreditation in one or more of the 50 United States and its territories. For the purposes of this procurement, “Evidence-based” design accreditations/certificates are not acceptable as professional credentials.
PROGRAM MANAGER (formerly Project Lead): The individual who is responsible for overall management of the A-E IDIQ contract. This individual shall be an employee of the prime A-E firm. This position is distinct from that of individuals who are responsible for managing individual task orders/projects under the IDIQ contract or special programs (QC, Sustainable Design, etc.).
PROJECT or SPECIFIC PROJECT: A single project contract or a single task order under an IDIQ or other multiple award type contract; a design-build or a design-bid-build activity or task, with a single starting point and a single ending point. Combined projects (see definition) will not be considered.
RECENT or SEVEN-YEAR PERIOD: The prescribed timeframe for this solicitation that refers to the period of time for which projects may be submitted for consideration as relevant experience, relevant past performance, etc. The seven-year period is calculated by counting back seven years from the SF330 due date.
RELEVANT or RELEVANT EXPERIENCE: Pertains to work performed by an Offeror, within the prescribed timeframe, which is the same or similar to the work that may be ordered under this contract in terms of size, scope, and complexity. Experience is distinct from past performance (how well an Offeror has performed).
RENOVATION/REPAIR: Refers to projects where the work primarily involves modification of existing facilities by renovation, repair, and alteration (work within the existing exterior walls and existing square footage of the facility).
SELF-PERFORM: Refers to performing relevant architectural-engineering work in-house without subconsultants/subcontractors. Relevant work is that which is the same or similar to the primary or secondary services that may be ordered under this contract.
SUSTAINABLE DESIGN MANAGER: The individual who is responsible for management of the sustainable design program for the A-E IDIQ contract. The Sustainable Design Manager shall be a LEED
AP or equivalent. The LEED Green Associate (GA) credential is not considered equivalent to the LEED
Accredited Professional (AP) credential.
SUSTAINABLE FEATURES: Features in the design, construction, and operation of facilities with the goal of conserving resources and minimizing adverse effects on the environment while enhancing occupant productivity, minimizing energy use, improving quality and durability of materials, increasing recycling and use of recycled products, waste reduction, etc. Relevant sustainable features are those that are the same or similar to those recognized by the USGBC LEED rating system.