Amendment 03 Attachment ANNEX 1502000 DEMO 02_17_2021.pdf
PDF 325 KB Posted
- Attached to
- Indefinite Delivery/Indefinite Quantity (IDIQ) Demolition at Marine Corps Base Camp Pendleton (MCBCP) Federal contract opportunity
- Solicitation number
- N6247321R1012
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1502000 – Facility Investment Table of Content Demolition and Abatement Spec Item Title 1 General Information
2 Management and Administration
2.1 Definitions and Acronyms
2.2 Personnel
2.2.1 Certification, Training, and Licensing
2.3 Special Requirements
2.3.1 Workmanship and Material Standards
2.3.2 Historical Preservation
2.3.3 Backflow Preventer
2.3.4 Landfills and Pits on MCB Camp Pendleton
2.3.5 Salvageable Items/Recyclables
2.3.6 Hauler’s Weigh-In
2.3.6.1 Weigh-In Process and Supporting Documentation
2.4 References and Technical Documents
3 FFP Work – Not used.
4 IDIQ Work
1502000 – Facility Investment
Spec Item
Title Description
1 General Information
The Contractor shall furnish all project management, general and administrative, overhead, quality control, site safety and health management, site supervision, project labor, tools, personal protective equipment, safety equipment and devices, materials necessary for demolition and abatement, mechanized equipment, other equipment, temporary facilities, vehicles/fuel/maintenance, transportation, incidental engineering, and other items necessary to provide the demolition and abatement services described in this Contract.
Spec Item
Title Description
2 Management and Administration
2.1 Definitions and
Acronyms
Acronyms and definitions applicable to demolition and abatement are found in the applicable sections in the General Requirements and Technical Requirements which are located in Section J, Attachment’s J-1502000-02 and J-1502000-03.
2.2 Personnel The Contractor shall provide skilled workers with the skills, qualifications, technical knowledge, and all necessary training and certifications required to perform demolition and abatement.
The Contractor shall provide a certified Asbestos Building Inspector (Certified Site Surveillance Technician that works under a Certified Asbestos Consultant) to perform a complete asbestos survey of a facility or structure, to include inspecting and sampling the complete facility or structure for Presumed Asbestos Containing Materials (PACM), i.e. all interior and exterior building components and to include roof components down to the substrate. The Asbestos Building Inspector shall not be affiliated with the demolition or abatement contractor or sub-contractors.
The Contractor shall provide a certified State of California Certified Lead Inspector/Assessor (I/A) to perform a complete lead assessment of a facility or structure, to include inspecting and sampling all facility or structure building components for Lead-Based Paint. The State of California Certified I/A shall not be affiliated with the contractor or subcontractor performing the demolition or abatement, The Contractor shall provide a Certified Industrial Hygienist (CIH) to be on site at all times while work is in progress to perform air monitoring and sampling during ACM and LBP abatements. The CIH shall have no affiliation with the demolition or abatement contractors or sub-contractors.
2.2.1 Certification, Training, and Licensing
Contractor Performing Demolition:
The Contractor or subcontractor performing demolition shall have a valid C- 21 State of California Contractor’s license or have another state’s contractor’s license that is equivalent to the C-21 State of California Contractor’s license. Note: A C-21 Building Moving/Demolition Contractor is a contractor that is licensed to raise, lower, crib, underpin, demolish and move or remove structures, including their foundations. This classification does not include the alterations, additions, repairs or rehabilitation of the permanently retained portions of such structures.
Shall have a minimum of five (5) consecutive years of demolition experience in commercial type buildings and structures.
Contractor Performing Asbestos Abatement:
Contractor Requirement:
The Contractor or subcontractor performing asbestos shall have a valid C-22
State of California Contractor’s license or have another state’s contractor’s license that is equivalent to the C-22 State of California Contractor’s license.
The asbestos abatement contractor shall be fully competent in California’s regulations as they pertain to asbestos abatement. All work performed, and all documentation prepared by asbestos abatement contractors shall be done in accordance with regulations and requirements of the Department of Industrial Relations’ Division of Occupational Safety and Health (DOSH).
Note: A C-22 Asbestos Abatement Contractor is a contractor that operates as a stand-alone specialty contractor classification for asbestos abatement work, regardless of any other classification(s) that may be held by the licensed contractor, and functions within the scope of the contractor’s DOSH registration.
Shall have a minimum of five (5) consecutive years of asbestos abatement experience.
Asbestos Contractor/Supervisor:
Shall have a valid Asbestos Contractor/Supervisor (Competent Person) certification that satisfies OSHA/Cal-OSHA and EPA’s Model Accreditation Plan (AHERA) training requirements.
Shall have a valid Respiratory Protection certification that meets OSHA Respiratory Protection Standard, 29 CFR 1910.134.
Shall have a minimum of three concurrent years of experience as an Asbestos Contractor/Supervisor.
Spec Item
Title Description
Asbestos Worker:
Shall have a valid Asbestos Worker certification that satisfies OSHA/Cal-
OSHA and EPA’s Model Accreditation Plan (AHERA) training requirements.
Shall have a valid Respiratory Protection certification that meets OSHA Respiratory Protection Standard, 29 CFR 1910.134.
Asbestos Project Designer:
Shall have a valid AHERA Asbestos Project Designer certification.
Shall have a minimum of three (3) consecutive years working in Asbestos
Abatement field.
Shall be qualified to plan and design and define the necessary procedures for project specific Asbestos Abatement Plans.
Contractor Performing Lead Abatement:
Contractor Requirement:
Shall be a State of California certified lead-removal contractor.
Shall have a minimum of five (5) consecutive years of lead removal experience.
Lead Supervisor/Lead Project Monitor
Shall have a valid Lead Supervisor/Lead Project Monitor certification that satisfies California Department of Public Health (CDPH) training requirements.
Shall have passed the State Lead Certification Exam and have a valid certification.
Shall have a valid Respiratory Protection certification that meets OSHA Respiratory Protection Standard, 29 CFR 1910.134.
Shall have a minimum of three concurrent years of experience as a Lead Supervisor/Lead Project Manager.
Lead Workers:
Shall have a Lead Worker certification that satisfies California Department of Public Health (CDPH) training requirements.
Certified Industrial Hygienist (CIH):
CIH
Submit the company name, address, telephone number, State of California license, all permits and certifications of the CIH.
Shall have successfully completed training and is therefore accredited
Spec Item
Title Description under a legitimate State of California Model Accreditation Plan as described in 40 CFR 763.
Shall be accredited by the American Industrial Hygiene Association (AIHA) and National Institute of Science and Technology (NIST) under National Voluntary Laboratory Accreditation Program
(NVLAP).
CIH Technician:
Shall have a valid AHERA Asbestos Project Designer certification.
Shall have a valid Lead Supervisor/Lead Project Monitor certification that satisfies California Department of Public Health (CDPH) training requirements.
Air Conditioning and Refrigeration Technicians:
Air Conditioning and Refrigeration Technicians working on systems, equipment or components containing chlorofluorocarbons (CFCs) and/or hydro-chlorofluorocarbons (HCFCs) shall be certified under an Environmental Protection Agency (EPA) approved technical certification program per OPNAVINST 5090.1 Chapter 6 Overseas Environmental Baseline Guidance Document/Final Government Standard (OEBDG/FGS).
Contractor’s Performing Utilities Disconnects:
Contractors:
Contractor’s performing low/medium electrical utilities disconnects shall have a valid contractor’s license and shall have a minimum of five (5) consecutive years of experience in the industry.
Contractor’s performing water and sewer utilities disconnects shall have a valid contractor’s license and shall have a minimum of five (5) consecutive years of experience in the industry.
Contractor’s performing gas utilities disconnects shall have a valid contractor’s license and shall have a minimum of five (5) consecutive years of experience in the industry.
Trades Foremen:
Trades foremen shall have a minimum of three (3) years of relative experience in their respective trade.
Shall have a minimum of two (2) consecutive years supervising tradesmen in their own trade.
Tradesmen:
Tradesmen performing utilities disconnects shall have a minimum of two (2) years of experience.
Spec Item
Personnel performing work on transformers must be knowledgeable of proper procedures for handling and disposing of insulating fluid containing polychlorinated biphenyls (PCBs)
Submittal Requirements:
Submit resumes of qualifications, licenses and certifications within 15-calendar days after award of a contract task order to the Contracting Officer, Contracting Officer’s Representative, and FEAD FSC Technical Writer for review, and acceptance by the Contracting Officer. The Contractor shall submit the licenses and certifications for new subcontractors to the Contracting Officer, Contracting Officer’s Representative, and FEAD FSC Technical Writer within 15-calander days prior to performing demolition or abatement for review, and acceptance by the Contracting Officer. The Contractor nor shall any of their subcontractors mobilize onto a demolition site, whether a contract task order has been awarded or not, until the license and certification submittals have been approved.
EXCEPTION: Should the Contractor have go into agreement with a subcontractor(s) that are contracted to provide the types of services specified in this Contract on an ongoing nature, i.e. the same subcontractor will perform the service on each awarded contract task order, then the Contractor shall submit resumes of qualifications, licenses and certifications within 15-calendar days after award of a Contract to the Contracting Officer, Contracting Officer’s Representative, and FEAD FSC Technical Writer for review, and acceptance by the Contracting Officer. The Contractor shall submit the licenses and certifications for new subcontractors to the Contracting Officer, Contracting Officer’s Representative, and FEAD FSC Technical Writer within 15-calander days prior to performing demolition or abatement for review, and acceptance by the Contracting Officer. The Contractor nor shall any of their subcontractors mobilize onto a demolition site, whether a contract task order has been awarded or not, until the license and certification submittals have been approved.
Note: This requirement is applicable to the Contractor if they plan to perform the service(s) in-house.
See the General Requirements found in Section J, Attachment J-1502000-02 and the Technical Requirements found in Section J, Attachment J-1502000-03 for additional certification, training and license information and requirements.
2.3 Special
Requirements
2.3.1 Workmanship and
Material Standards
All demolition and abatement work shall comply with all applicable safety codes, and all Federal, State of California, the respective Activity and local regulatory agency regulations.
Workmanship: The Contractor's Quality Control Manager shall ensure that all aspects of demolition and abatement are in conformance with the Contract specifications and each awarded contract task order’s statement of work and Decision Memorandum.
The Contractor shall not allow debris and demolition waste to spread into adjacent areas nor accumulate in the work area. All such debris and demolition waste shall be cleaned up and removed at the completion at the end of each work shift while project is in progress and at the completion of the project and before scheduling the “Final
Spec Item
Acceptance Inspection.”.
After demolition has been completed and prior to scheduling the “Final Acceptance Inspection” the site shall be cleaned and free of debris, graded and raked, free of excess spoils and rocks and other inert materials, and all equipment and disposal units removed from the site.
2.3.2 Historical
Preservation
Adjacent buildings and facilities designated as historical sites shall be protected and the protection controls put into place be continually maintained in accordance with Federal, State, respective Activity, and local historical policies and regulations.
2.3.3 Backflow
Preventer
When using fire hydrants and standpipes for water supply to maintain dust control during demolition the Contractor shall provide and install a certified backflow preventer to the hydrant or standpipe at no additional cost to the Government.
Hoses shall never be connected to a fire hydrant or standpipe without first installing a certified backflow preventer that has been accepted by the Government.
The Contractor shall submit the product data and certifications of all backflow preventers to the Contracting Officer and Contracting Officer’s Representative for review, and acceptance by the Contracting Officer before placing them into use. No exceptions!
2.3.4 Landfills and Pits
on MCB Camp Pendleton
Landfills located on MCB Camp Pendleton are not authorized for use.
Pits located on MCB Camp Pendleton and once used to dispose of inert materials, i.e.
soil/fill materials, rocks and gravel, asphalt and concrete are not authorized for use.
The Contractor, under no circumstances, shall dispose of demolition waste, debris, rubbish, recyclables and inert materials anywhere on MCB Camp Pendleton and NWS Seal Beach Detachment Fallbrook, CA.
2.3.5 Salvageable
Items/Recyclables
All salvageable items found in a building or structure shall become the property of the Contractor.
It is expected that the Contractor will make a profit on salvageable/recyclable items, therefore the Government will not compensate the Contractor to separate salvageable items, for temporary storage containers to store recyclables in, and for hauling to an approved recycle facility. The Contractor shall not include the weight of the salvageable/recyclable items as part of the demolition waste.
2.3.6 Hauler’s Weigh-
In
The Contractor’s haulers of demolition waste (non-hazardous, commingled non-hazardous and Category I non-friable ACM, and hazardous) and recyclable asphalt and concrete shall weigh in at the Base Scales at B-2255 or at the 43 Area Landfill as follows:
Prior to proceeding to the project site to weigh and document the tare weight of the hauling vehicle and trailer if applicable.
After being loaded at the project site proceed to the scales to weigh and document the gross vehicle weight to include the trailer if applicable.
Once the hauler has performed the above process for demolition debris (non-hazardous and hazardous) only, the hauler shall weigh in with the gross vehicle weight at the off-Base landfill and shall receive the supporting documentation indicating the gross vehicle weight.
Spec Item
Title Description
Haulers of recyclable asphalt and concrete need only weigh in at the Base scales.
2.3.6.1 Weigh-In Process
and Supporting Documentation
Each Base weight receipt shall include the truck identification number, actual date of being weighed, the tare weight, combined gross vehicle weight, the task order modification number, the facility number and the Weighmaster’s signature. The Contractor is responsible for ensuring the entire Certified Scale Certificate is completed. Failure of the Contractor to complete the form may result in the Contractor not being compensated for the haul.
Each off-Base landfill weight receipt shall include the name of the landfill, the vehicle number, the actual date of being weighed, and the combined gross vehicle weight.
The Certified Scale Certificate is found in Attachment J-1502000-05.
Note to Contractor:
For each hauled load of demolition debris, the Base Certified Scale Receipt’s documented gross vehicle weight shall match the gross vehicle weight documented on the off-Base landfill weight receipt.
Failure of the Contractor to submit supporting weight receipts may result in the Contractor not being compensated for the haul.
2.4 References and
Technical Documents
The technical specifications are found in Section J, Attachment J-1502000-01 through Attachment J-1502000-07.
Spec Item
Title Performance Objective
Related Information Performance Standard
3 FFP Work NA NA NA
Spec Item
Title Performance Objective
Related Information Performance Standard
4 IDIQ Work IDIQ work may be The Contracting Officer will award Work and services on ordered utilizing DoD a contract task order to the each awarded contract EMALL or on a task Contractor which includes an IDIQ task order is performed order in accordance Work bid schedule of the ELINs to and completed in with the be used, necessary quantities, unit accordance with the PROCEDURES FOR price, and total price. The awarded Contract specifications ISSUING ORDERS contract task order’s bid schedule and in accordance with clause. The order will will also include the project’s environmental specify the exact statement of work. regulations.
locations and types of work to be The performance of work shall be All work is performed accomplished. The completed by the awarded contract on scheduled and period of performance task order’s completion due date. completed by the will be specified in each awarded contract task order. order’s completion due date.
Awarded contract task order Contractor’s Daily Production Reports and Quality Control Reports are submitted as required.
All awarded contract task order required reports and documentation is submitted as required.
File details come from the government source that posted it. Updated .