60025763A.pdf
PDF 486 KB Posted
- Solicitation number
- N6247020R6012
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Contractor shall provide services to remove, store, and re-install the pulpit, eagle lectern, organ, piano, electric piano, painting, and the altar at BLDG 16 for the duration of the construction contract, photographs included for reference. The contractor shall record the condition, including photographs, of each item prior to moving them. The contractor shall remove these furnishings from the building to complete the renovation work identified in the contract. These furnishings shall be protected to ensure no damage during transportation and stored in a climate controlled storage facility to ensure preservation. The storage facility shall provide humidity and temperature control systems. Furnishings shall be returned to the facility prior to the CCD date. If damage to the furnishings occurs the contractor shall repair or replace as deemed appropriate by the government.
Protestant Chapel Furnishings - (L x W x H) measured in ft:
Pulpit: 4 x 4 x 6 Eagle lectern: 3 x 3 x 5 Piano: 7 x 5 x 3 Organ: 5 x 4 x 4 Painting: 6 x 4 Electric piano: 4 x 5 x 3 Altar: 7 x 2 x 4
2. In addition to the afore mentioned furniture storage by the contractor, please include one (1) connex container for the storage of miscellaneous furnishings. Upon contract award contractor shall provide one (1) – 40 foot connex container to allow the Marines to store furniture. Contractor shall coordinate with the project CM/ET to identify an appropriate location in the vicinity of BLDG 16 for the connex container. Once delivered, the contractor shall allow the Marines fourteen (14) days to move furniture into the connex containers. Periodic access may be needed by the Marines to this connex container, please ensure access can be maintained. Upon renovation completion, the contractor shall allow the Marines fourteen (14) days to move the furnishings from the connex container back into the building(s). Once the connex containers are emptied, they are no longer needed and shall be removed from the site.