Amend 0002 06022020.pdf
PDF 27 KB Posted
- Attached to
- P812 Provide Ship to Shore Electrical Substations at Pier #1, Naval Station, Rota, Spain
- Solicitation number
- N6247020R4005
About this file
This amendment modifies a solicitation for a construction project at Naval Station Rota in Spain. The project involves installing and commissioning shore power distribution substations operating at 15kV/450-480V voltage. The amendment provides point of contact information for questions and revises the evaluation criteria for corporate experience. Offerors must now demonstrate experience with at least one of the following: installing shore power substations; constructing medium voltage underground distribution systems between 1,000V to 35kV; or installing medium voltage metal clad switchgear. Relevant experience within the past seven years is required. The proposal due date of June 29, 2020 is unchanged. The solicitation and amendment were issued by the Naval Facilities Engineering Command Atlantic on behalf of the Department of the Navy for Solicitation Number N6247020R4005.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
P-812 PROVIDE SHIP TO SHORE ELECTRICAL SUBSTATIONS AT PIER #1 NAVAL STATION, ROTA, SPAIN
The Proposal due date is unchanged and remains Monday June 29, 2020 @ 2:00 PM (EDT).
PLEASE SEE SF-30 BLOCK 14 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 02-Jun-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247020R4005
X 9B. DATED (SEE ITEM 11)
14-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
02-Jun-2020
CODE
COMMANDER NAVFAC ATLANTIC
6506 HAMPTON BLVD
NORFOLK VA 23508-1278
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6247020R4005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMEND 02
P-812 PROVIDE SHIP TO SHORE ELECTRICAL SUBSTATIONS AT PIER #1 NAVAL STATION,
ROTA, SPAIN
The purpose of this amendment is to provide the following:
1. PPI POC requirements
2. Solicitation Revisions
1. Effective immediately, all RFIs must be sent to the following two (2) emails:
Kimberly.y.king@navy.mil anna.bellinger@navy.mil
2. Solicitation Revisions:
CURRENT:
Factor 1 – Corporate Experience:
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information. Submit a minimum of (2) and maximum of five (5) relevant construction projects for the Offeror that best demonstrates experience on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as demonstrating at least two (2) of the following elements:
- Construction of medium voltage underground distribution (1,000 V – 35 kV)
- Installing and commissioning of medium voltage metal clad switchgear
- Installing and commissioning of shore power distribution substations (15kV/450-480V)
Projects submitted for the Offeror must have been completed within the past seven (7) years from the date of issuance of this request for proposal (RFP). To ensure a project is considered “complete”, the documentation should demonstrate final delivery to the client. Each project submitted by the Offeror must include two of the three construction elements listed above to be considered relevant.
REVISED TO:
N6247020R4005
Factor 1 – Corporate Experience:
(a) Solicitation Submittal Requirements:
The Offeror shall submit the following information:
Submit a minimum of two (2) and up to a maximum of five (5) relevant construction projects for the Offeror that best demonstrates experience on relevant projects that are similar in size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as demonstrating at least one (1) of the following elements:
- Installing and commissioning of shore power distribution substations (15kV/450-480V)
- Construction of medium voltage underground distribution (1,000 V – 35 kV)
- Installing and commissioning of medium voltage metal clad switchgear
Offerors that demonstrate experience in multiple elements listed above may be considered more favorably.
Offerors that demonstrate experience in installation and commission of shore power distribution substations may be considered more favorably than those offerors who do not demonstrate this experience.
Projects submitted for the Offeror must have been completed within the past seven (7) years from the date of issuance of this request for proposal (RFP). To ensure a project is considered “complete”, the documentation should demonstrate final delivery to the client.
-- End of Amendment --