AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
MODERNIZATION OF PORTAL CRANES, SERVICE LIFE EXTENSION PROJECT (SLEP) AT NORFOLK NAVAL SHIPYARD, PORTSMOUTH, VA (NNSY) PUGET SOUND NAVAL SHIPYARD & INTERMEDIATE MAINTENANCE FACILITY (PSNSY & IMF), BREMERTON, WA
ANDPORTSMOUTH NAVAL SHIPYARD (PNSY), KITTERY, ME
This amendment provides the Pre-Proposal Meeting slides, attendance sheet, and photos.
SEE ATTACHED.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Feb-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N62470-14-R-5001
X 9B. DATED (SEE ITEM 11)
10-Jan-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Feb-2014
CODE
COMMANDER NAVFAC ATLANTIC
NAVY CRANE CENTER
NORFOLK NAVAL SHIPYARD
BLDG 491
PORTSMOUTH VA 23709-5000
N62470 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N62470-14-R-5001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0004
See attached pre-proposal meeting slides, attendance sheet, and photos.
(End of Summary of Changes)
Service Life Extension Program (SLEP) to Modernize Fourteen (14) 60 Ton Portal Cranes
NNSY, PNSY, PSNSY
Pre-Proposal Meeting and Site Visit Kickoff Briefing
RFP N62470-14-R-5001
January 28, 2014
Agenda
Welcome/Introductions
Project Overview
Solicitation Documents
Solicitation Background
Source Selection Process
Evaluation Factors
Submission of RFP/Site Visit Questions and Answers
Safety Brief
Site Tour
Project Overview
Inputs needed from Project Management and Design
Design Overview
Government Monitoring, etc.
Solicitation Documents
Solicitation, Attachments, and Amendments
Posted on the Federal Business Opportunities website: https://www.fbo.gov/
Register to receive automatic updates regarding the solicitation.
RFP posted on February 10, 2014
Amendments – Ensure you acknowledge them!
Questions
Proposals currently due on February 25, 2014
Caution- Today’s Q&As are not contractually binding
Solicitation Background
Unrestricted, Full and Open Competition
–Unsuccessful & Successful offerors
–Thorough evaluation of the proposal
–Some information on successful proposal
–The rationale for award
Indefinite Delivery, Requirements Type Contract with Firm-Fixed Prices
Single Award Contract
Basis for Award: Best Value, Tradeoff
Period of Performance: Base period of twelve months, four one-year option periods, not to exceed a total of 60 months.
Liquidated Damages (FAR 52.211-11)
Start at $450/calendar day of delay for $1,000,000 ELIN value.
Increases by $50/calendar day for each additional $100,000
Special Contract Considerations
Performance Based Payments
Must be requested and must include clear, verifiable events to substantiate payment requests
Occur no more than monthly
Limited to 90% of delivery item price
See FAR 52.232-28, FAR 52.232-32
Pass financial responsibility determination
Bonds
Bid Bond required with proposal
Performance and Payment Bonds required for task orders
Warranty
3% withheld for warranty
Liquidated Damages (FAR 52.211-11)
Starts at $450/calendar day of delay for $1,000,000 ELIN value.
Increases by $50/calendar day for each additional $100,000
Steps in the Source Selection Process
1. Define the requirement
2. Establish the team and the plan
3. Request and evaluate offers
4. Establish competitive range, negotiate, request Final Proposal Revision, re-evaluate (if necessary)
5. Select Best Value
6. Make Award
Source Selection Team
Source Selection
Authority (SSA)
Source Selection Evaluation
Board (SSEB)
Technical Evaluation
Team (TET)
Price Evaluation Team (PET)
Source Selection Team (continued)
SSA
Oversee acquisition
Determine competitive range
Select best value offeror
SSEB
Make recommendations on competitive range & best value selection to SSA based on TET & PET evaluation
TET
Evaluate non-cost/price proposals based on SSP/RFP evaluation factors
Document strengths, excesses, weaknesses, deficiencies, risks & possible discussion questions
Assign adjectival ratings
PET
Evaluate reasonableness of individual cost elements
Evaluate price reasonableness & risk
Evaluation Factors
•All technical factors when combined are of equal importance to the performance confidence assessment (past performance) rating; and all technical factors and the performance confidence assessment (past performance) rating, when combined are approximately equal to price
•Section M Non-Price Factors:
–Factor 1 – Technical Approach
–Factor 2 – Management Approach
–Factor 3 – Safety
–Factor 4 – Small Business Utilization
• Subfactor 4.A. – Past Performance in Utilization of Small Business
Concerns
• Subfactor 4.B. – Small Business Participation
–Factor 5 – Past Performance on Recent, Relevant Projects
Price Evaluation
•Ensure you complete Section B and ALL five ELIN worksheets
•Sample:
Total Price will reflect total of Exhibits A-E, which will match the total of CLINs 0001-0005.
Evaluation of Offers
Follow Procedures of FAR Part 15
Follow the Procedures of the Source Selection Plan
Utilize the Basis of Evaluation set forth in the RFP
Tradeoff Process FAR 15.101-1 - The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
Establish Competitive Range, Negotiate, Request Final Proposal Revision, Re-evaluate (if necessary)
Establish competitive range Include the “most highly rated” proposals
Evaluate based on all evaluation criteria
Preaward debriefing to those outside competitive range (if requested within the required timeframe)
Conduct negotiations Discuss all weaknesses and deficiencies
Request final proposal revisions
Re-evaluate
Select the Best Value
Source Selection Authority determines Best Value Independent decision
Comparative assessment against all evaluation criteria
Document decision
Make Award
Obtain necessary approvals Higher Level
OFCCP Pre-award Clearance
Obtain Funds
Submit CHINFO
Award
Notification to Unsuccessful Offerors
Conduct Post-Award Debriefs (if requested on time) Unsuccessful & Successful offerors
Thorough evaluation of the proposal
Some information on successful proposal
The rationale for award
Lessons Learned (prior to proposal submission)
Verify accuracy of SAM, Representations and Certifications, VETS-100 registrations
Sign and return all solicitation amendments
Ask questions if you are uncertain about something
Create a checklist to ensure you have addressed all requirements
Do not provide company brochures
Number proposal pages consecutively and stay within the page limitations provided
Make sure insurance information is up-to-date for the safety factor
Do not copy and paste from a prior proposal
Clearly label and separate/tab each factor in your proposal
Address every element within each factor
RFP/Site Visit Questions and Answers
All Site Visit Questions must be submitted in writing
This ensures all potential offerors receive accurate information at the same time.
Follow the instructions in the RFP for submission of Pre-award Inquiries and use the Government Preaward Inquiry Form (GPIF)
Site visit questions and answers will be posted to FBO. Site visit questions resulting in a change to the solicitation will be addressed in an amendment.
The list of site visit attendees and presentation will be posted on FBO.
** Do not attempt to contact the Government site visit points of contact for additional information **
Norfolk Naval Shipyard
Safety Brief
Questions?
U.S. Navy Photograph Unclassified
Luff Hoist panel
Main Contact panel
Main Contact panel
Travel panel