Atch (1)_APPENDIX E Risk Assessment Example Format - 06 Dec 2019.pptx

PPTX presentation 86 KB Posted

Attached to
Pre-Solicitation Conference Event for FY21 Content Conversion
Solicitation number
N61340-20-R-0037_PreSolicitationConference
Issued by

About this file

This document contains a risk assessment example format and risk summary worksheet for a Navy program. It details a risk of insufficient access to fleet and schoolhouse subject matter experts during analysis, design, development, and testing phases. The risk is rated high with a likelihood of likely and a consequence of moderate. Planned mitigation actions include coordinating with experts before and during acquisition, holding a risk working group meeting, and continuing coordination efforts. The risk status is listed as open and the risk type involves technical, schedule, and cost factors.

The related federal contract opportunity notice announces a pre-solicitation conference for a fiscal year 2021 content conversion opportunity with the Department of the Navy Naval Air Systems Command. Details on the conference event are provided in the attachments.

View the file

Other files

File Type Posted
Atch L-9 Draft RFP GFI Request Form-rev1.docx DOCX document
Atch (1)_APPENDIX C Terms and Definitions - 16 Jan 2020.docx DOCX document
Exhibit B_FY21 RRL CONTENT CONVERSION (B00X) Admin CDRLS - Draft 10 Feb 2020.docx DOCX document
Atch (1)_APPENDIX K S2025 xAPI Requirements - 04 Mar 2020.docx DOCX document
Atch (1)_APPENDIX H Sailor 2025 RRL Use of Blooms Taxonomy Action Verbs - 06 Dec 20199.odt ODT document
Exhibit A_FY21 RRL CONTENT CONVERSION (A00X) Engineering CDRLs - Draft 16 Mar 2020.docx DOCX document
FY21 RRL CC PreSol_QuestionsAnswers.xlsx XLSX spreadsheet
Atch (1)_APPENDIX J Mobile Learning Roadmap - 06 Dec 2019.docx DOCX document
Atch (1)_APPENDIX L NETC RRL Single User Gaming and Simulation Guidance - 06 Dec 2019.odt ODT document
Atch (1)_APPENDIX B Acronym List - 03 Feb 2020.docx DOCX document
Atch (1)_APPENDIX I Sailor 2025 RRL Content Conversion Media Type Characteristics - 18 Feb 2020.odt ODT document
Atch L-9 Draft RFP GFI Request Form.docx DOCX document
N61340-20-R-0037 - Section B.docx DOCX document
Atch (1)_APPENDIX M NETC RRL Video Streaming Guidance - 06 Dec 2019.odt ODT document
Atch (1)_APPENDIX G Sailor 2025 RRL Operational Engaging Instructional Strategies - 06 Dec 2019.docx DOCX document
Atch (1)_APPENDIX D CDRL List - 26 Feb 2020.docx DOCX document
Exhibit F_FY21 RRL CONTENT CONVERSION (F00X) Training CDRLs -16 Mar 2020.docx DOCX document
Atch (1)_APPENDIX F Sailor 2025 RRL Content Delivery Modes - 06 Dec 2019.odt ODT document
Atch (1)_FY21CC IDIQ SOW - RFP Draftv2 - 18Mar 2020.docx DOCX document
FY21 CC Industry Day Attendee List.docx DOCX document
RRL FY21 CC PreSol Conf - Final.pptx PPTX presentation
N6134020R0037_Pre-Solicitation_Conference_Announcement.doc DOC document
P2-3ParkingMap_2018.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION A. Approved for public release. Distribution is unlimited.

APPENDIX E: Risk Assessment Example Format 06 Dec 2019

Sailor 2025 – Ready Relevant Learning (RRL) Risk Assessment

Likelihood [5] Near Certainty (~90%)

[4] Highly Likely (~70%)

1
[3] Likely

(~50%)

[2] Low Likelihood (~30%)

[1] Not Likely (~10%)

Consequence[1]
Minimal[2]
Minor[3]
Moderate[4]
Major[5]

Unaccept-able

O

- Original X

- Current Low Moderate High

Consequence Likelihood

Action/Event Date Schd.

ECD

Act.

Current Status Risk Level if Successful C L Suc.

Comments Plan:

T

- Target New Plan - Current Plan Current Original Risk Level N/A N/A

1. Coordinate with schoolhouse staff and TYCOMs for SMEs.

10/1/16 1/26/17 1/26/17 Coordinating with schoolhouse and TYCOMs for SMEs.

Y

2. Coordinate with fleet SMEs prior to and during the acquisition phases.

1/2/17 05/10/17 5/10/17 Continuing coordination with schoolhouse and SMEs.

Y

8/14/17 8/14/17 8/14/17 Continue to coordinate with schoolhouse staff and fleet SMEs prior to and during the acquisition phases.

Y

Risk Status:

Open

Risk Type (Check one in each area Technical Schedule Cost Risk Summary Worksheet Team: Sailor 2025 Risk Owner: NAWCTSD Date Opened: 01 Oct 2016 Updated: 14 Aug 2017 Risk Title: Sufficient Access to Fleet and Schoolhouse SMEs Risk #: 1 Description of Risk: If sufficient access to fleet and schoolhouse Subject Matter Experts (SMEs) is not available during analysis, design, development, and testing, for each wave, then contractor deliverables, the analysis output, and content conversion may be late.

Root Cause: Fleet and schoolhouse SMEs are busy working and teaching classes and have limited availability for RRL visits.

Consequence: Contractor deliverables, the analysis output, and content conversion may be late.

X O X

3. Risk working group meeting

Action/Event Date Schd.

ECD

Act.

Success Criteria L C Suc.

Comments Risk Level if Successful

Plan:

New Plan - Current Plan Current

Team: Sailor 2025 Risk Owner: NAWCTSD Date Opened: 01 Oct 2016 Updated: 14 Aug 2017 Risk Title: Sufficient Access to Fleet and Schoolhouse SMEs Risk #: 1 Risk Summary Worksheet

Backup Information

Program Risk Assessment

Not Likely:

Low Likelihood:

Likely:

Highly Likely:

Near Certainty:

...Will effectively avoid or mitigate this risk based on standard practices ~10% ...Have usually mitigated this type of risk with minimal oversight in similar cases ~30% ...May mitigate this risk, but workarounds will be required ~50% ...Cannot mitigate this risk, but a different approach might ~70% ...Cannot mitigate this type of risk; no known processes or workarounds are available ~90%

Determination of consequence for Schedule and Cost are program Specific.

Consequence

HIGH

MEDIUM

LOW

LevelTechnical PerformanceScheduleCost
1Minimal or no consequence to technical performanceMinimal or no impactMinimal or no impact
2Minor reduction in technical performance or supportability, can be tolerated with little or no impact on program; same approach retainedAdditional activities required, able to meet key dates.
Slip <___Month(s)Cost increase or unit production cost increases

< 1_% of budget

3Moderate reduction in technical performance or supportability with limited impact on program objectives; workarounds availableMinor schedule slip, no impact to key milestones
Slip < __ month(s) plus available float of critical path. Sub-system slip > __ month(s) plus available float. Slip <__Month(s)Cost increase or unit production cost increase

<___ 5% of budget

4Significant degradation in technical performance or major shortfall in supportability; may jeopardize program success; workarounds may not be available or may have negative consequencesPrgm critical path affected, all sched float assoc. w/key MS exhausted
Slip <__ MonthsCost increase or unit production cost increase

<____ 10% of budget

5Severe degradation in technical performance; Cannot meet KPP or Key technical/supportabilility threshold; will jeopardize program success; no workarounds availableCannot meet key program milestones
Slip >___ MonthsExceeds APBA threshold

> ____ 10% of budget

Consequence Level Probability of Occurrence image1.bin image2.emf

File details come from the government source that posted it. Updated .