USS GRAVELY (DDG-107) FY22 INCREMENTAL SELECTED RESTRICTED AVAILABILITY (ISRA)
Solicitation number
N5005421R0011
Issued by

About this file

This document contains a pre-proposal information question and answer set for a solicitation seeking proposals for the USS GRAVELY (DDG-107) FY22 Incremental Selected Restricted Availability. The solicitation will result in the award of a firm-fixed price contract for ship repair and maintenance work. Proposals are due by November 17, 2021. The work includes cleaning and inspection of main reduction gears, fire safety drills, crew washroom repairs, temporary air conditioning, and fabrication of protective covers for antennas. Questions from offerors cover clarification of work locations, quantities of materials, and whether existing office space can substitute for required trailers. The Naval Sea Systems Command is seeking this work for maintenance of the USS GRAVELY.

View the file

Other files

File Type Posted
N5005421R0011 A0007.pdf PDF
Conformed N5005421R0011 A0007.pdf PDF
Conformed N5005421R0011 A0006.pdf PDF
N5005421R0011 A0006.pdf PDF
USS GRAVELY ISRA S-3 Rev 1 11-10-21.xlsx XLSX spreadsheet
USS GRAVELY ISRA S-3 Rev 1 11-8-21.xlsx XLSX spreadsheet
N5005421R0011 A0005.pdf PDF
Conformed N5005421R0011 A0005.pdf PDF
N5005421R0011 A0004.pdf PDF
Conformed N5005421R0011 A0004.pdf PDF
USS GRAVELY ISRA S-3 Rev 1 11-4-21.xlsx XLSX spreadsheet
N5005421R0011 A0003.pdf PDF
USS GRAVELY ISRA S-3 Rev 1 10-27-21.xlsx XLSX spreadsheet
Conformed N5005421R0011 A0003.pdf PDF
USS GRAVELY ISRA S-3 Rev 1 10-22-21.xlsx XLSX spreadsheet
Attachment S-10 DBIDS.pdf PDF
N5005421R0011 A0002.pdf PDF
Attachment S-11 SHIP ACCESS FORM.xlsx XLSX spreadsheet
Attachment S-7 Proposal Assessment Rev 1.xlsx XLSX spreadsheet
Conformed N5005421R0011 A0002.pdf PDF
Attachment S-7 Proposal Assessment.xlsx XLSX spreadsheet
Conformed N5005421R0011 A0001.pdf PDF
N5005421R0011 A0001.pdf PDF
N5005421R0011 USS GRAVELY (DDG-107) FY22 ISRA.pdf PDF
Attachment S-3_BQ_PPI.xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRV ISRA Q&A

USS GRAVELY (DDG-107) FY22 ISRA Pre-Proposal Information (PPI) Questions
DrawingDATE:10/19/21MARMC POC: Bethany Danyluk, bethany.danyluk1@navy.mil; Sherry Jarvis, sherry.jarvis@navy.mil
GFMSolicitation #:N5005421R0011MARMC Phone: 757-837-8752 (Bethany), 757-837-8788 (Sherry)
RLARForward all requests to: Bethany Danyluk, bethany.danyluk1@navy.mil; Sherry Jarvis, sherry.jarvis@navy.mil
CONTRACTOR:
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
To request references, drawings, RLARs, and Errata being provided under this Solicitation Question & Answer Set,

please contact the POCs.

Q #RFP Section-Page/ Work Item #Document Number/TitleQuestionGovernment Response
1991-10-001Temporary and Roller Staging for SFPara 3.1 states to install staging in each location listed in 1.2. Para 1.2 states "throughout the ship". Further para 3.2 states to install a rolling stage for ships force use, but it doesn't give a location of where this rolling staging is to be installed. - Please provide a location for the staging to be installed in 3.1 and the rolling staging to be installed in 3.2.Errata forthcoming to remove the requirements of paragraph 3.1. For paragraph 3.2 states "The exact location will be designated by the SUPERVISOR.", so we don't know where yet.
2262-40-001Main Reduction Gear (MRG) Lube Oil Cooler; clean and inspectContractor is missing reference 2.3 (S9262-B1-MMA-010). Please provide reference at your earliestFile attached
3077-11-001Fire Safety and Emergency Fire Response Plan; accomplish3.1.1 states "Each drill will be scheduled within 30 days after the start of the availability and 180 calendar days thereafter throughout the availability" The period of performance is 92 days.
Please advise.There is only 1 drill required 30 days after start of avail.
4644-11-002Crew Washroom; repair3.2 states to remove honeycomb bulkhead, coaming, shower partition and SS sheathing. Will contractor be responsible for removing all WC partitions and reinstalling after 009-26 requirements are met?Yes.
5980-10-001Naval Air Warfare Center, Aviation Facilities Assist Visit Discrepancey; correctAdditional work item that includes a man-hour & material reservation require the submittal of a report that duplicates the report required by 042-11-001 para 3.5. Request that the Government delete the duplicate weekly man-hour and material report from the following work item, this will eliminate multiple redundant reports: 3.1.2 980-10-001The requirements in paragraph and subparagraph 3.5 of work item 042-11-003 are not the same as the requirements of paragraph and suparagraphs 3.1.2 of work item 980-10-001; therefore, they will not be deleted.
6123-10-001Tank and Void Open, Pump, Clean and Gas Free; accomplish3.6.2 states "Remove existing and install new a total of 25 each missing or broken manhole cover studs for each tank opened in 3.1"
Is it the Government's intent to replace a cumulative total of 25 studs for the 15 tanks or 25 studs for each tank for a total of 375 studs?The cumulative total for all of the tanks will be 25 studs.
7992-11-008Temporary Air Conditioning; provideTypically a Temporary Air Conditioning item requires access cuts, but no 009-05 is in the item.
Will access cuts be required? If yes, contractor requests the Government to add 009-05 in the item.Response Pending
8992-11-015Barge For Multi-Function Towed Array (MFTA) Cable; provideFor estimating purposes, how much crane support will be required IAW paragraph 3.1?4 crane lifts for off load and 4 crane lifts for on load
9992-11-015Barge For Multi-Function Towed Array (MFTA) Cable; provideWill the barge directed in paragraph 3.2 be required for the entire availability? If no, how many days will the barge be required?Barge will be required for 72 hrs for off load and 72 hours for onload.
10992-11-015Barge For Multi-Function Towed Array (MFTA) Cable; provideWhat size barge is required in paragraph 3.2?Minimum 135 ft long by 35 ft wide and a minimum of 6 feet of freeboard
11251-32-002Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.4.1 States "Accomplish base metal weld buildup of a total of 50 square inches of plate defects". Is the 50 square inches per space or a cumulative total for all spaces?Response Pending
12251-32-002Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.4.2 States "Vee out and weld a total of 4 linear feet of each cracked, split, broken or damaged intake plenum/trunk weld". Is the 4-square feet, per space or a cumulative total for all spaces?Response Pending
13251-32-002Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.4.3 States "Remove existing and install new 5-square feet of bulkhead plate". Is the 5-square feet, per space or a cumulative total for all spaces, and what thickness and material type of bulkhead plate?Response Pending
14251-32-002Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.4.4 States "Remove existing and install new 5-square feet of deck plate". Is the 5-square feet, per space or a cumulative total for all spaces, and what thickness and material type of deck plate?Response Pending
15251-32-002Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.4.5 States "Remove existing and install new 10-linear feet of structural stiffener". Is the 10-linear feet, per space or a cumulative total for all spaces, and what thickness and material type of structural stiffener?Response Pending
16259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.2 States "Accomplish Power Tool clean to bare metal in each location in 1.2 to include uptake duct anchor foundation, each structural member, steel channel, deck plate and bulkhead for a total of 3,578 Square feet". Is the 3,578-square feet, per space or a cumulative total for all spaces?The square footage is to be distributed throughout as designated by the SUPERVISOR for a total of 3,578-square feet cumulative total for all spaces?
17259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.4 States "Remove existing and install new 30-square feet of deck plate located in 1.2.1". What thickness and material type of deck plate?.188 MIL-S-22698 DH-36 as noted in Ref 2.3
18259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.1 States "Accomplish base metal weld buildup of a total of 160 square inches of plate defects". Is the 160 square inches per space or a cumulative total for all spaces?Response Pending
19259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.2 States "Remove existing and install new 32-square feet of bulkhead plate". Is the 32-square feet, per space or a cumulative total for all spaces, and what thickness and material type of bulkhead plate?Response Pending
20259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.3 States "Remove existing and install new 32-square feet of deck plate". Is the 32-square feet, per space or a cumulative total for all spaces, and what thickness and material type of deck plate?Response Pending
21259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.4 States "Remove existing and install new 50-linear feet of structural stiffener". Is the 50-linear feet, per space or a cumulative total for all spaces, and what thickness and material type of structural stiffener?Response Pending
22259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.5 States "Remove existing and install new 5-square feet of eductor nozzle cap foundation". What thickness and material type of structural stiffener?Response Pending
23259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.6 States "Remove existing and install new 25-linear feet of exhaust duct stiffener". Is the 25-linear feet, per space or a cumulative total for all spaces, and what thickness and material type of exhaust duct stiffener?Response Pending
24259-10-001Number One Gas Turbine Intake Partial Repair and Preservation; accomplish3.5.7 States "Remove existing and install new longitudinal stiffener 7 starboard located in 1.2.4 at frame 186". How many linear feet, and type of material is required?One linear foot of the material designated in the drawing.
25993-31-005Antenna Radome Protective Cover; fabricate and installParagraph 1.3.2 for Radome Antenna AS-4671 appears to be incorrect based on the equipment list in reference 2.3. Contractor requests the Government to confirm if Antenna Identification Number 3-13 in 1.3.2 should be AS-4667.Correct. It should be AS-4667/WSC-9(V).
26991-10-001Temporary and Roller Staging for Ship's Force Use; provideParagraph 3.1 directs to provide staging in each location listed in 1.2, but no locations are listed.
Contractor requests the Government to provide locations requiring staging.Errata forthcoming to remove the requirements of paragraph 3.1. For paragraph 3.2 states "The exact location will be designated by the SUPERVISOR.", so we don't know where yet.
27991-10-001Temporary and Roller Staging for Ship's Force Use; provideHow many sections of rolling staging is required IAW paragraph 3.2?Paragraph 3.2 states "a rolling stage", which indicates one.
28980-90-003ShipAlt 86937K, DDG Integrated Bridge System (IBS) Tech Refresh, Alteration Installation Team (AIT) Support Service; provideParagraph 3.17 states "Provide 10 square feet of deck tile services to procure and replace Nomex tiling…".
Is the deck tile actually Nomex Panels or a type of deck tile? Please clarify.The deck tile is NOMEX panels.
29123-10-001Tank and Void Open, Pump, Clean and Gas Free; accomplishFor estimating purposes the Contractor requests the Govt. provide the quantities of fuel to be taken to the Naval Fuel Depot?Response Pending
30123-10-001Tank and Void Open, Pump, Clean and Gas Free; accomplishFor estimating purposes the Contractor requests the Govt. provide the quantities of Compensating Sea Water that will require removal and disposal?Response Pending
31123-10-001Tank and Void Open, Pump, Clean and Gas Free; accomplishFor estimating purposes the Contractor requests the Govt. provide any tanks and spaces, including adjacent tanks or spaces that require pumping, opening, cleaning for certification and maintenance that are not listed in Paragraph 1.2 for the location of work?Response Pending
32980-90-003ShipAlt 86937K, DDG Integrated Bridge System (IBS) Tech Refresh, Alteration Installation Team (AIT) Support Service; provideParagraph 3.12 requires the Contractor to provide an office trailer. Will existing office space be a suitable substitute?Response Pending
33980-90-004ShipAlt DDG51-88325K and 94418K, Hull, Mechanical and Electrical (HM&E) Core, DDG FCS Fuel Oil Lab PC (FOLPC), CPS COTS MFM Integration, Alteration Installation Team (AIT) Support Service; provideParagraph 3.10 requires the Contractor to provide an office trailer. Will existing office space be a suitable substitute?Response Pending
34991-10-001Temporary and Roller Staging for Ship's Force Use; provideParagraph 3.1 requires the Contractor to provide staging in each location listed in 1.2. Paragraph 1.2 reads, "location of work: 1.2.1 throughout the ship." For estimating purposes, can locations requiring staging be provided to the ContractorResponse Pending
35259-10-001Number One Gas Turbine Uptake; partial repair and
preservationReference 2.7 & 2.9 have the same drawing number of 7060388 (Rev E & F). Reference 2.9 was provided. Is 2.7 a typo?Response Pending
36262-40-001Main Reduction Gear (MRG) Lube Oil Cooler; clean and inspectParagraph 3.3.1.1 states "...of a report listing results of the requirements of 3.4.1…".
Contractor recommends the Government revise to 3.3.1.Response Pending