This document outlines a Quality Assurance Surveillance Plan (QASP) and matrix for a Navy contract to provide Hull, Mechanical and Electrical (HM&E) pierside assists for the Mid-Atlantic Regional Maintenance Center. The contractor will perform depot-level repairs, maintenance, installation and removal of equipment for Navy and military vessels within 50 miles of Norfolk, Virginia or worldwide. The incumbent contracts are N50054-14-D-1401/1402/1403/1404 and 1405. Solicitation N50054-19-R-0003 will be set aside 100% for small business as a multiple-award IDIQ contract with a one-year base and four one-year options. The QASP defines surveillance methods for monitoring contractor performance against requirements for combating trafficking in persons, submitting contract data deliverables, and overall contract performance.

J20 - Quality Assurance Surveillance Plan (QASP) and Matrix

View the file

Other files

File Type Posted
BIDDER'S_QUESTIONS_001-037-AMEND_0005.pdf PDF
AMENDMENT_0005_SF-30_RFP_N50054-19-R-0003.pdf PDF
BIDDER'S_QUESTIONS_001-035-AMEND_0004.pdf PDF
AMENDMENT_0004_SF-30_RFP_N50054-19-R-0003.pdf PDF
BIDDER'S_QUESTIONS_001-034-AMEND_0003.pdf PDF
AMENDMENT_0003_SF-30_RFP_N50054-19-R-0003.pdf PDF
AMENDMENT_0002_SF-30_RFP_N50054-19-R-0003.pdf PDF
J17_-_Past_Performance_Information_Form_REV-AMEND_0002.docx DOCX document
J18_-_Past_Performance_Questionnaire_REV-AMEND_0002.docx DOCX document
BIDDERS_QUESTIONS_&_ANSWERS_001-030_AMEND_0002.pdf PDF
AMENDMENT_0001_SF-30_RFP_N50054-19-R-0003.pdf PDF
RFP_REV_N5005419R0003_AMEND_0001.pdf PDF
BIDDER'S_QUESTION_&_ANSWER_003_01-02-2019.pdf PDF
RFP_N50054-19-R-0003.pdf PDF
BIDDER'S_QUESTIONS_&_ANSWERS_001-002.pdf PDF
RFP_N50054-19-R-0003.pdf PDF
J16_-_Capacity_Evaluation_Form.xlsx XLSX spreadsheet
J18_-_Past_Performance_Questionnaire.docx DOCX document
CDRL_EXHIBITS_A-E.zip ZIP file
J15_-_992-031,_Cleaning_and_Pumping;_accomplish.pdf PDF
J13_-_042-001,_Accountability_of_Manhour_and_Material_Reservation;.pdf PDF
J10_-_042-038,_General_Requirements_for_Work_Within_Naval_Station_Norfolk_and_Joint.pdf PDF
J17_-_Past_Performance_Information_Form.docx DOCX document
J6_-_042-006,_General_Occupational_Safety,_Health_and_Environment_(OSHE).pdf PDF
J12_-_992-001,_Heavy_Weather_Plan_(Demobilization);_accomplish.pdf PDF
J19_-_Request_for_Specification_Clarification.xlsx XLSX spreadsheet
J2_-_042-001,_Work_Completion_Certification_Data_for_CNO.pdf PDF
J4_-_042-005,_General_Requirements_for_Work_on_Submarines;_accomplish.pdf PDF
J7_-_042-007,_Security_Requirements_for_Work_Within_Norfolk_Naval_Shipyard;.pdf PDF
J14_-_077-001,_Hazardous_Waste_Produced_on_Naval_Vessels;_control.pdf PDF
J11_-_992-001,_Heavy_Weather_Plan_(Remobilization);_accomplish.pdf PDF
J1_-_042-001,_Work_Completion_Certification_Data_for_CMAV-EM.pdf PDF
J9_-_042-009,_General_Requirements_for_Work_Within_Norfolk_Naval_Shipyard.pdf PDF
J8_-_042-008,_General_Requirements_for_Work_on_Aircraft_Carriers;_accomplish.pdf PDF
J3_-_042-005,_Requirements_for_Work_Within_Norfolk_Naval_Shipyard_(NNSY);.pdf PDF
J5_-_042-005,_Norfolk_Naval_Shipyard_(NNSY)_Work_Authorization_Form_(WAF).pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUALITY ASSURANCE SURVEILLANCE PLAN

HULL, MECHANICAL & ELECTRICAL (HM&E) PIERSIDE ASSISTS FOR

MID-ATLANTIC REGIONAL MAINTENANCE CENTER (MARMC)

Ref: (a) NAVSEAINST 4200.19A

Enc: (1) QASP Matrix

1. PURPOSE

This Quality Assurance Surveillance Plan (QASP) is a Government developed and applied document used to ensure NAVSEA requirements identified in Ref. (a) are met in the planning, acquiring and managing of

Delivery Orders under contract N50054-19-R-0003. Systematic quality assurance methods are used in the administration of NAVSEA contracts to allow greater visibility and conscious decisions by higher levels of management regarding combatting trafficking in persons, CDRLs, and overall contract performance. This plan sets forth the procedures and guidelines the government will use in ensuring the required performance standards are achieved by the contractor. Adherence to standards is applicable to the contract and subsequent delivery orders issued hereunder.

2. AUTHORITY

Authority for issuance of this QASP is provided under Section E – Inspection and Acceptance, which provides for inspections and acceptance of the articles, services, and documentation called for in this contract, to be accomplished by the Procuring Contracting Officer (PCO) or their duly authorized representative.

3. SCOPE

The QASP is put in place to provide Government surveillance oversight of the Contractor’s quality control efforts to assure that they are timely, effective and are delivering the results specified in the contract or delivery orders. The QASP defines the methodologies used to monitor and evaluate the contractor’s performance, describes quality assurance documentation requirements, and describes the analysis of quality assurance monitoring results.

This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.

4. GOVERNMENT RESOURCES

The following definitions for Government resources are applicable to this plan:

Contracting Officer - A person duly appointed with the authority to enter into, administer, or terminate contracts and make related determinations and findings on behalf of the Government.

Contracting Officer’s Representative (COR) - An individual designated in writing by the Contracting

Officer to act as his authorized representative to assist in administering a contract. The source and authority for a COR is the Contracting Officer. COR limitations are contained in the written letter of appointment.

5. RESPONSIBILITIES

The following Government resources shall have responsibility for the implementation of this QASP:

Contracting Officer – The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United

States in the contractual relationship. It is the Contracting Officer that assures the Contractor receives impartial, fair, and equitable treatment under the contract. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the Contractor’s performance.

Contracting Officer’s Representative (COR) - The COR is responsible for technical administration of the project and assures proper Government surveillance of the Contractor’s adherence to policies and requirements regarding combatting trafficking in persons, CDRLs, and overall contract performance, and forwards all surveillance findings as required by this QASP. The COR is not empowered to make any contractual commitments or to authorize any contractual changes on the Government’s behalf. Any changes that the Contractor deems may affect contract, price, terms, or conditions shall be referred to the

Contracting Officer for action.

6. METHODS OF QA SURVEILLANCE

The below listed methods of surveillance shall be used in the administration of this QASP.

Customer Feedback – Customer feedback may be obtained from Technical Advisors and/or random customer complaints. Customer complaints, to be considered valid, must set forth clearly, and in writing, the detailed nature of the complaint. It must also be signed and forwarded to the COR. The COR shall maintain a summary log of all formally received customer complaints as well as a copy of each complaint in a documentation file.

Regular/Periodic/Random Inspections– The COR will conduct regular, periodic, and/or random inspections commensurate with contract performance and submission of CDRLs and invoices.

Reviewing Records– The COR will review Contractor meeting, training, and/or signature records to determine proof of required employee notification of Combatting Trafficking in Persons information.

7. IDENTIFIED QA SURVEILLANCE ITEMS

Attachment J20, QASP Matrix, sets forth individual descriptions, performance requirements, thresholds, surveillance methods and remedies for the contractor.

8. DOCUMENTATION

The COR will, in addition to providing documentation to the Contracting Officer, maintain a Quality

Assurance file that will include all applicable documentation and correspondence as a result of regular surveillance. All such records will be retained for the life of this contract. Information in the Quality

Assurance file will be considered when completing the annual CPARS report.

Enclosure 1

Description Performance Requirement Performance Threshold Surveillance Method Remedy

Contract Clauses; 52.222-

50, Combatting

Trafficking in Persons

IAW FAR 52.222-50; the Contractor shall:

(1) Notify its employees and agents of—

(i) The United States Government's policy prohibiting trafficking in persons, and

(ii) The actions that will be taken against employees or agents for violations of this policy; and

(2) Take appropriate action, up to and including termination, against employees, agents, or subcontractors that violate the policy in paragraph (b) of this clause.

(d) Notification.

(1) The Contractor shall inform the Contracting Officer and the agency Inspector General immediately of—

(i) Any credible information it receives from any source

(including host country law enforcement) that alleges a

Contractor employee, subcontractor, subcontractor employee, or their agent has engaged in conduct that violates the policy; and

(ii) Any actions taken against a Contractor employee, subcontractor, subcontractor employee, or their agent pursuant to this clause.

(2) If the allegation may be associated with more than one contract, the Contractor shall inform the contracting officer for the contract with the highest dollar value.

100% compliance required due to Zero

Tolerance policy.

COR to conduct periodic inspection IAW surveillance schedule.

(1) Review meeting/training/signature records as proof of contractor to employee notification.

(2) Vary routine inspections by time and day; be aware of how contractors treat their employees, watch for signs of abuse, restraints visible, etc.

(3) Review violations and document contractor actions.

The contractor's failure to comply with this FAR clause may result in:

(1) Requiring the contractor to remove an employee from the performance of this contract.

(2) Requiring the contractor to terminate a subcontract.

(3) Suspension of contract payments.

(4) Termination of contract for default.

Contract Data

Requirements List

(CDRL)

Submit reports in accordance with requirements prescribed in the SOW and CDRLs.

95% of deliverables submitted timely and without rework required.

Periodic inspection by COR

The contractor's failure to comply with this requirement may result in:

(1) CAR

(2) If CAR remains unresolved, less than

Satisfactory rating in CPARS

Overall Contract

Performance

Overall contract performance of sufficient quality to earn a

Satisfactory (or higher) rating in the COR's annual report on

Contractor Performance.

All performance elements rated satisfactory rating (or higher) Customer feedback and regular inspection by COR

The contractor's failure to comply with this requirement may result in:

(1) CAR

(2) If CAR remains unresolved, less than

Satisfactory rating in CPARS

QASP Matrix