This is a Questions and Answers document (Notice No. 2 and 3) for solicitation N40192-25-R-5000 regarding Environmental IDIQ Services for hazardous waste management at Joint Region Marianas, Guam. The Q&As provide clarifications about facilities, equipment, and operational requirements including: confirmation that maintenance of Government-Furnished Facilities (GFF) will be at no cost to the contractor unless due to contractor negligence; availability of office space at the Conforming Storage Facility (CSF); work schedules requiring 24/7 operations for certain annexes; and contractor responsibility for waste profiling per RCRA regulations.
Key details clarified include: the Navy will provide 2 local phone lines but contractor must provide internet; contractor must furnish all equipment/materials except those specifically identified as Government-Furnished; waste pickup schedules align with regular government working hours unless specified otherwise; and guidance on non-hazardous waste disposal requirements is referenced in Section C-0200000. The document also confirms that the Project Manager and Hazardous Waste Operations Manager roles are the same position, and provides direction to relevant sections of the RFP for details on wage determinations, RCRA permit applications, and waste classification requirements.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND MARIANAS
PSC 455, BOX 195
FPO AP 96540-2937
N40192-25-R-5000 Notice No. 3
27 December 2024
NOTICE NO. 3
REQUESTS FOR INFORMATION AND RESPONSES
SOLICITATION N40192-25-R-5000
ENVIRONMENTAL IDIQ SERVICES FOR HAZARDOUS WASTE, HAZARDOUS MATERIAL,
OTHER REGULATED WASTE, AND SPILL RESPONSE AT JOINT REGION MARIANAS, GUAM
QUESTION (Q) 7: Is the contractor responsible for maintaining the CSF with regard to infrastructure sustainment and repair?
Answer (A) 7: Refer to Section C-0200000 Spec Item 2.4.2 (Government- Furnished Facilities) for details.
"Maintenance and repair of GFF shall be made at no cost to the Contractor unless if need for such repairs are otherwise caused by Contractor’s negligence."
Q8: Does the CSF have offices for use by the contractor?
A8: There is an office space available at the CSF for contractor’s use.
Q9: Is there any equipment, furniture, supplies (i.e. drum scales) at the CSF and/or 90-day storage locations that is considered GFE for contractor use?
A9: Refer to Section C-0200000 Spec Item: 2.4 (Government- Furnished Items) and Spec Item 2.5
(Contractor-Furnished Items) for details.
Q10: Is the Navy requiring hazard pay differential be applied to the wage determination rates?
A10: Refer to Attachment JH-1_SCLS Wage Determination 2015-5693_22JUL2024 of the RFP.
Q11: Please provide a copy of the Navy’s RCRA permit application for the CSF
A11: The Government will provide any available historical information/data to the selected contractor after award, upon request. However, permit application forms and requirements may be found via the following link below:
https://epa.guam.gov/applications/
Q12: Can the Navy provide a waste profile list beyond general classifications (e.g. ignitables, corrosives, etc.)
A12: The contractor is responsible for the waste profile in accordance with RCRA, Federal and local regulations.
Refer to Section 1800000 Spec Item 3.0 and 4.0 for details.
N40192-25-R-5000 Notice No. 3
Q13: Please elaborate on waste pick-up schedules at the Pier Sites.
A13: Refer to PWS Spec Items below:
2.2.1 Government Regular Working Hours
2.6.5 Work Schedules
"Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise."
Q14: Are any, of the equipment, furniture, supplies inside the TSDF and 90-day stations Government owned/furnished, that can be used by the contractor.
A14: Refer to Question & Answer 9.
Q15: How many drums does the Navy purchase on this contract annually?
A15: Refer to Section C-0200000, Spec Item: 2.5 (Contractor- Furnished Items):
"Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract."
Q16: Can the Navy please define what constitutes non-hazardous waste on this contract and whether such material has been disposed of in the Guam landfill under the current contract?
A16: Refer to "Non-RCRA Regulated Waste" for Definitions and Acronyms - Attachment Section J –
0200000 and Section C-0200000, Spec Item 2.10.2.4 for Non-Regulated Waste Disposal
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND MARIANAS
PSC 455, BOX 195
FPO AP 96540-2937
N40192-25-R-5000 Notice No. 2
20 December 2024
NOTICE NO. 2
REQUESTS FOR INFORMATION AND RESPONSES
SOLICITATION N40192-25-R-5000
ENVIRONMENTAL IDIQ SERVICES FOR HAZARDOUS WASTE, HAZARDOUS MATERIAL,
OTHER REGULATED WASTE, AND SPILL RESPONSE AT JOINT REGION MARIANAS, GUAM
QUESTION (Q) 1: Can the Attachment JL-2 be expanded to 3 pages?
Answer (A) 1: Yes.
Q2: Please confirm that the exhibits are properly labeled on line 3 of the exhibit tabs. Currently they are all labeled as Exhibit A.
A2: Exhibits A-E_Exhibit Line Item Numbers (ELINs) have been updated. See Enclosure (1). Revisions were made ONLY to the Exhibit titles in row 3 of each ELIN tab.
Q3: Given the challenges to get physical copies of the proposal d to Guam during the holiday period would the Navy consider a 2-week extension with the proposal due date on January 20, 2025.
A3: Refer to the proposal extension detailed in Amendment 0002.
Q4: Is the Project Manager the same as the Hazardous Waste Operations Manager.
A4: Yes.
Q5: Will the Navy provide the contractor with administrative office space?
A5: Yes
Q6: Who pays for communication lines? Is the contractor responsible for internet, phone, other utilities?
A6: 2 Local phone lines are provided by the Navy. The contractor is responsible for their internet connection. See Section C – 0200000Management and Administration for information re electrical and water.