Amen 03.pdf

PDF 124 KB Posted

Attached to
Bldgs HP52, HP56, HP551A, HP561A Water Heater and WC140, AS508 Boiler Replacement
Solicitation number
N4008526R9080
Issued by

About this file

This document is Amendment 0003 to Solicitation N40085-26-R-9080, issued by NAVFAC Mid-Atlantic on September 3, 2026, for water heater and boiler replacement work at Camp Lejeune, North Carolina. The solicitation concerns replacement of water heating and boiler equipment in Buildings HP52, HP56, HP551A, HP561A, and WC140, as well as AS508. The amendment responds to two contractor requests for information submitted during the proposal period and clarifies technical specifications for the equipment.

The amendment provides the following technical guidance: for boiler flues, contractors must use the same material as existing (AL29-4C) and must employ a water tube design. For water heater flues, contractors may use either the existing CPVC material or switch to AL29-4C, provided the replacement equipment is compatible with CPVC. The receipt deadline for proposals remains unchanged from the original solicitation. All other terms and conditions of the original solicitation remain in effect. Contractors must acknowledge receipt of this amendment prior to proposal submission to avoid rejection.

View the file

Other files

File Type Posted
Amen 02.pdf PDF
260404 SV.pdf PDF
Amen 01.pdf PDF
REVISED BOILER WATER HEATER SCOPE.pdf PDF
Pricing Sheet 260404.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
RFP 260404.pdf PDF
26-0404 BOILER WATER HEATER - SOW.pdf PDF
Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 2

AMENDMENT NO. 0003 09/03/26 26-0404

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-26-R-9080

8/6/26

26-0404, Bldgs HP52, HP56, HP551A, HP561A Water Heater and WC140, AS508 Boiler Replacement Amendment 0002, Requests for Information

The time and date for receipt of proposals remains unchanged.

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

See Continuation Page(s)

N40085-26-R-9080 Amendment 0003

CONTINUATION SHEET

1. QUESTION: Boilers: Existing flue is AL29-4C do we go back with that material? Please confirm a water tube design is being requested.

ANSWER: Use the same flue material. Use water tube design.

2. QUESTION: Water Heaters: Existing flue is CPVC do we go back with that material or switch to AL29-4C which has historically been used.

ANSWER: If CPVC can be used on replacement equipment, then it is fine to use it.

3. All other terms and conditions remain unchanged.