This is Amendment 0002 to a solicitation for water heater and boiler replacement work at Camp Lejeune, North Carolina. The amendment is issued by NAVFAC Mid-Atlantic (Contract ID N40085-26-R-9080) with an effective date of August 25, 2026, and does not extend the proposal submission deadline. Offerors must acknowledge receipt of this amendment prior to proposal submission or face potential rejection.
The amendment addresses a Request for Information regarding the use of Fulton Kestava condensing water heaters as an alternative to the specified equipment. The proposed configuration would include KTV-1000 and KTV-750 models at various buildings (HP52, HP56, HP551A, HP561A) with a total of eight Kestava units versus fourteen PVI Turbopower units. The offeror highlighted advantages including redundancy, reduced footprint, improved design configuration, and Duplex Stainless Steel heat exchangers resistant to chloride corrosion. The Government's response explicitly states that it does not prefer this configuration and requires offerors to bid according to the original specifications. The amendment also notes that a site visit roster has been provided and confirms all other terms and conditions remain unchanged.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 11)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPIRATION DATA (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
1 2
AMENDMENT NO. 0002 08/25/26 26-0404
N40085
NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521
See Item 6
✘ N40085-26-R-9080
8/6/26
26-0404, Bldgs HP52, HP56, HP551A, HP561A Water Heater and WC140, AS508 Boiler Replacement Amendment 0002, Requests for Information
The time and date for receipt of proposals remains unchanged.
This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.
See Continuation Page(s)
N40085-26-R-9080 Amendment 0002
CONTINUATION SHEET
1. QUESTION: Could the Fulton Kestava condensing water heater be used. If so would the following configurations be approved:
Design load is 587 GPH @ 100F delta T:
HP52 two (2) KTV-1000 @ 1,140 GPH per heater HP56 same as HP52 HP551A Two (2) KTV-750 @ 876 GPH per heater HP561A same as HP551A
PVI Turbopower 96 total 14, Fulton Kestava total eight (8).
The Kestava design gives redundancy but uses about half the heaters verses the PVI.
Kestava has a smaller footprint as well as they are down fired with the burner on top so there is no side vessel hot spot or side mount burner weld leak as with the PVI.
Both Fulton and PVI use Duplex Stainless Steel heat exchangers that are highly resistant to chlorides unlike 316 stainless.
ANSWER: The Government does not prefer this configuration. Please bid per specs.
2. A site visit roster has been provided.
3. All other terms and conditions remain unchanged.