26-0404 BOILER WATER HEATER - SOW.pdf

PDF 123 KB Posted

Attached to
Bldgs HP52, HP56, HP551A, HP561A Water Heater and WC140, AS508 Boiler Replacement
Solicitation number
N4008526R9080
Issued by

About this file

This is a Performance Work Statement (PWS) for the removal and replacement of boilers and domestic water heaters at military facilities. Project 26-0404 involves three replacement boilers with net output of 93 MBH each (2 units at Camp Lejeune facility WC140 and 1 unit at New River Air Station facility AS508) and 14 replacement water heaters distributed across four Camp Lejeune buildings (4 units each at HP52 and HP56; 3 units each at HP551A and HP561A). The existing equipment consists of KC1000 boilers and PVI Power VT Plus Model CHN1261 water heaters, with replacement units required to match existing specifications.

The contractor shall provide all labor, supervision, equipment, materials, tools, permits, and related services to complete removal, installation, testing, and commissioning of replacement systems. Scope includes preconstruction field verification of existing conditions and utilities; demolition and removal of existing equipment; installation of new boilers and water heaters with required anchorage and clearances; reconfiguration of water and gas piping with isolation valves, relief valves, strainers, and dielectric protection; installation of combustion air intake and exhaust venting systems with condensate management; electrical modifications including dedicated disconnects and panel updates; controls and building automation system integration; startup documentation; and comprehensive testing including pressure/leak integrity, combustion analysis, and temperature balancing. Closeout requirements include manufacturer startup reports for all equipment, gas and combustion test documentation, warranty registrations, as-built drawings, and owner training. The project POC is Leonard Neal at (910) 451-9560, with boiler inspector contacts Alex Vance (450-7153) and Rannie Rayes (450-7114). Temporary hot-water service, hazardous material abatement, and major structural modifications are excluded unless specifically included in the contractor's proposal.

View the file

Other files

File Type Posted
Amen 03.pdf PDF
260404 SV.pdf PDF
Amen 02.pdf PDF
Amen 01.pdf PDF
REVISED BOILER WATER HEATER SCOPE.pdf PDF
Combined DIV 01 specs small projects.pdf PDF
RFP 260404.pdf PDF
Contractor Environmental Guide Updated Format_20231009 with ESOP.pdf PDF
Pricing Sheet 260404.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DISTRIBUTION: DoW COMMUNITY ONLY

Project: 26-0404 Bldg.’s HP52, HP56, HP551A, HP561A Water Heater / WC140 and AS508 Boiler Replacements

Project Information

Project #: 26-0404

MACC #: 26M010CN

Date: 07/28/2026 Project POC: Leonard Neal | Phone#: (910) 451-9560 Locations: Camp Lejeune (WC140, HP52, HP56, HP551A, HP561A) and New

River Air Station (AS508)

1. Project Overview

The contractor shall provide all labor, supervision, equipment, materials, tools, rigging, permits, and incidental services required to complete the removal and replacement of existing boilers and domestic water heaters at designated facilities. The completed systems shall be fully operational, tested, commissioned, and compliant with applicable codes, Division 1 Specifications, and manufacturer requirements.

2. Equipment Schedule

2.1 Boiler Replacements

Location

Facility

Existing Equipment

Replacement Requirement

Quantity

WC140

Camp Lejeune

KC1000 Boilers

Net output @ full input is

93MBH

AS508

New River Air Station

KC1000 Boiler

Net output @ full input is

93MBH

2.2 Water Heater Replacements

Location Existing Quantity

Replacement Quantity

HP52 4 4

HP56 4 4

HP551A 3 3

HP561A 3 3

Total 14 14

Boiler Equipment Information:

Existing Equipment: KC1000 Boilers Replacement Equipment: New boilers shall match the specs of the existing equipment.

Water Heater Equipment Information:

Existing Equipment: PVI Power VT Plus, Model CHN1261 (Existing Serial provided: 0615140172)

Replacement Equipment: New water heaters shall match the specs of the existing equipment.

Note: Equipment quantities, model numbers, serial numbers, capacities, dimensions, connection sizes, voltage requirements, and control requirements shall be field-verified before procurement and installation. Where a serial number applies only to one unit, the contractor shall document the individual serial number for every replacement unit.

3. General Requirements

Safety & Compliance: Contractor is responsible for ensuring all base safety requirements are followed. Workers must wear all required PPE while on the jobsite. All work to be done in accordance with Division 1 Specifications.

Energy Conservation: Contractor shall comply with the Base Energy Conservation Program. Use of high energy-consuming tools or equipment shall be approved by the Government.

Housekeeping & Disposal: Contractor is responsible for ensuring the work area remains clean. Debris from the jobsite must be removed and disposed of at an off-base disposal site.

Hazardous Materials: None identified.

Environmental Requirements: None identified.

4. Detailed Scope of Work

4.1 Preconstruction and Field Verification

Coordinate the work schedule, access, shutdowns, and service interruptions with the POC or facility representative.

Survey each mechanical room and verify:

Existing equipment quantities, conditions, dimensions, and service clearances.

Access routes, door openings, clearances, and rigging requirements.

Domestic cold-water, hot-water, and recirculation piping sizes and routing.

Natural-gas service capacity, pressure, pipe sizes, and routing.

Combustion-air intake and exhaust vent sizes, materials, routing, and termination locations.

Electrical voltage, phase, circuit capacity, disconnects, grounding, and control wiring.

Floor-drain locations, equipment pads, housekeeping pads, and condensate-disposal requirements.

Verify replacement equipment is compatible with existing building systems and available utilities.

Submit equipment data, piping and venting layouts, electrical requirements, control sequences, and proposed shutdown plans for review before beginning work.

4.2 Shutdown, Protection, Demolition, and Removal

Provide advance notice before each planned shutdown. Isolate, lock out, and tag out affected electrical, gas, water, and control systems.

Drain and make safe all equipment and piping scheduled for removal.

Protect adjacent equipment, finishes, occupied spaces, and building systems from damage, dust, water, and construction debris. Maintain domestic hot-water service where required.

Boiler Demolition: Remove old KC1000 boilers (2 at WC140 & 1 at AS508).

Water Heater Demolition: Disconnect and remove 14 existing PVI Power VT

Plus water heaters and associated connections.

Cap or plug abandoned piping and wiring at the nearest active point. Repair openings and minor damage resulting from demolition to match adjacent construction.

4.3 New Equipment Installation

Boilers: Install updated boilers compatible with the outputs of the old design (Net output @ full input is 93MBH).

Water Heaters: Furnish and install water heaters that match the specs of the existing equipment.

Provide required anchorage, supports, housekeeping-pad modifications, and equipment clearances. Install equipment level and plumb.

Provide all manufacturer-required accessories, sensors, controls, adapters, fittings, and startup components necessary for a complete installation.

4.4 Piping Requirements (Water and Gas)

Water Piping: Reconfigure and repipe systems as required. Provide isolation valves at each unit to permit individual service. Provide check valves, balancing valves, unions, strainers, thermometers, pressure gauges, drain valves, and dielectric protection.

Relief Valves: Install temperature-and-pressure relief valves of the required capacity. Pipe relief-valve discharge independently to an approved termination point.

Insulation: Insulate new domestic hot-water and recirculation piping to match existing systems and code requirements.

Gas Piping: Verify total connected input and confirm existing gas infrastructure has adequate capacity. Reconfigure and repipe natural-gas lines, providing code-compliant shutoff valves, sediment traps, regulators, and supports. Perform leak testing and document results before startup.

4.5 Venting, Exhaust, and Electrical

Combustion/Exhaust Venting: Provide complete combustion-air intake and exhaust vent systems sized/installed per manufacturer requirements. Provide condensate drains, neutralization kits, traps, and freeze protection where required. Seal all joints using manufacturer-approved methods.

Electrical: Modify or replace electrical feeders, branch circuits, disconnects, breakers, conduit, wiring, grounding, and bonding as required. Provide a dedicated code-compliant disconnect for each unit. Update panel schedules to reflect new equipment.

4.6 Controls and System Integration

Provide and install all factory and field controls required for coordinated operation.

Configure operating stages, lead-lag rotation, setpoints, temperature limits, alarms, and safeties.

Integrate equipment with the existing building automation or monitoring system where an interface currently exists or is required.

5. Startup, Testing, and Commissioning

Boilers: Startup of new boilers is to be included and properly documented.

Contractor is responsible for contacting boiler inspectors two weeks from start up date to be on site for initial inspection. Alex Vance 450-7153, or Rannie Rayes 450-7114.

Water Heaters: Arrange for startup by a PVI-authorized representative when required to maintain the equipment warranty.

Testing: Test and document water/gas piping pressure and leak integrity, combustion-air intake/exhaust operation, combustion analysis, supply/return temperatures, safety controls, electrical voltage/current, and condensate drainage.

Adjust systems to provide stable temperatures and balanced operation.

Correct any identified deficiencies and demonstrate full system operation to the Owner's representatives.

6. Closeout Requirements

Provide the following before final acceptance:

Approved permits and final inspection records.

Manufacturer startup reports for all equipment (including all 14 water heaters).

Gas-pressure and leak-test reports.

Combustion-analysis reports for each unit.

Water-piping test and disinfection records.

Equipment warranties and warranty-registration documentation.

Operation and maintenance manuals.

Final equipment schedule listing model and serial number by location.

As-built piping, venting, electrical, and control drawings.

Updated electrical panel schedules and control-point lists.

Recommended preventive-maintenance schedule.

Owner training covering normal operation, shutdown, emergency procedures, alarm response, and routine maintenance.

7. Clarifications and Assumptions

This scope is based on 3 total replacement boilers and 14 total replacement water heaters.

Final gas-pipe sizing, vent sizing, electrical requirements, and domestic-water piping arrangements are subject to field verification and approved manufacturer data.

Any deficiencies in the existing utility infrastructure that prevent operation of the new equipment shall be identified and reported before proceeding.

Hazardous material testing and abatement, structural modifications, major utility-service upgrades, and extensive architectural restoration are excluded unless specifically added by written amendment.

Temporary domestic hot-water service is excluded unless specifically included in the contractor's proposal.

Pricing shall clearly identify all assumptions, exclusions, alternates, allowances, proposed shutdown durations, and lead times.