This is Amendment 0006 to a federal solicitation for a Design-Build (DB) Repair project at Naval Station Newport, Rhode Island. The amendment is issued by NAVFAC Mid Atlantic Contracting Core and is effective October 28, 2026, for solicitation N40085-26-R-0228. The primary purpose of this amendment is to incorporate three key changes: updates to General Requirements, corrected response to Proposal Preparation Instruction (PPI) #121, and an updated wage determination.

The amendment revises the liquidated damages clause from the previously stated $17,115.93 per calendar day to $14,088.62 per calendar day for failure to complete work within the specified timeframe, in accordance with FAR 52.211-12 (Deviation 2026-O0038). The response to PPI #121 clarifies that the revised liquidated damages amount reflects differences in project costs, including higher Sellers, General and Administrative (SG&A) costs for Repair and Maintenance (RM) projects compared to Military Construction (MILCON) projects, higher Project Controls and Administration Systems (PCAS) costs due to increased architect-engineer involvement, and potentially tighter schedules to avoid delays. The wage determination has been updated to Department of Labor General Decision Number RI20260001 dated October 1, 2026, covering Rhode Island counties (Bristol, Kent, Newport, Providence, and Washington) for building, heavy, and highway construction work, including marine construction projects. The wage determination includes detailed prevailing wage rates and fringe benefits for multiple trade classifications such as carpenters, electricians, ironworkers, laborers, painters, plumbers, roofers, and truck drivers, along with applicable Executive Order requirements for paid sick leave and minimum wage rates.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N4008526R0228 Design-Build (DB) Repair OTC Dorm King Hall Bldg 291, Naval Station Newport, RI

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contract POC: Catharine Keeling, catharine.a.keeling.civ@us.navy.mil

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

2. AMENDMENT/MODIFICATION NUMBER

PAGE OF PAGES

1 17

5. PROJECT NUMBER (If applicable)

6. ISSUED BY

NAVFAC MID ATLANTIC

CONTRACTING CORE

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

CODE N40085 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NUMBER

N40085-26-R-0228

9B. DATED (SEE ITEM 11)

09/01/2026

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE

(X)

4. REQUISITION/PURCHASE REQUISITION NUMBER 3. EFFECTIVE DATE

10/28/2026

1. CONTRACT ID CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The following have been added by fully text:

AMENDMENT 0006

The purpose of this amendment is to incorporate the following:

1. Updates to General Requirements (in red)

2. Corrects Response for PPI #121

3. Updates Wage Determination

N40085-26-R-0228

1. Updates to General Requirements:

The following sections have been updated:

Wage Determination: Department of Labor (DoL) General Decision Number: RI20260001 dated 10/01/2026 ( listed below) applies to this work. Should this wage determination be modified by DoL prior to award, the most current wage determination will be incorporated in the award.

Liquidated damages: In accordance with FAR 52.211-12 (DEVIATION 2026-O0038) Liquidated Damages - Construction, if the Contractor fails to complete the work within the time specified in the task order, the Contractor shall pay liquidated damages to the Government in the amount of $14,088.62 for each calendar day of delay until the work is completed or accepted.

2. Revised/corrected Response to PPI#121

Question

Page Section Paragraph Question Response

General Requirem ents

The liquidated damages for this project are listed at $17,115.93 per day. This value is significantly higher than we have seen on other projects of similar complexity and price range. Please confirm this value is correct and provide any additional details that are available to contractors on how this value was calculated so we can plan accordingly to mitigate key cost drivers for the government.

Please see updated General Requirements as the liquated damages has been revised to $14,088.62.

Main reasons for projects of similar size/complexity delta:

1. SIOH is carried as a higher amount for RM projects than MILCONs.

2. PCAS is higher than typical in past due to higher involvement and greater delegation from AE reviewers.

3. For a project of this size, schedule may be tighter than related projects to avoid schedule slip as a factor in the denominator.

3. Updates Wage Determination to RI20260001 dated 10/01/2026

"General Decision Number: RI20260001 10/01/2026

State: Rhode Island

Construction Types: Building, Heavy and Highway

Counties: Rhode Island Counties of Bristol, Kent, Newport, Providence and Washington

Includes Marine Construction Projects

Modification Number Publication Date 2 01/30/2026 3 05/18/2026 4 07/30/2026 5 10/01/2026

ASBE0006-006 09/01/2024

Rates Fringes

HAZARDOUS MATERIAL HANDLER (INCLUDES PREPARATION,

WETTING, STRIPPING, REMOVAL SCRAPPING, VACUUMING,

BAGGING & DISPOSING OF ALL INSULATION MATERIALS,

WHETHER THEY CONTAIN ASBESTOS OR NOT, FROM

MECHANICAL SYSTEMS).................................$ 49.91 36.63

ASBE0006-008 09/01/2024

Rates Fringes

ASBESTOS WORKER/INSULATOR (INCLUDES APPLICATION OF

ALL INSULATING MATERIALS, PROTECTIVE COVERINGS,

COATINGS & FINISHES TO ALL TYPES OF MECHANICAL

SYSTEMS)............................................$ 49.91 36.63

BOIL0029-001 01/01/2025

Rates Fringes

BOILERMAKER.........................................$ 50.62 28.82

BRRI0003-001 06/01/2022

Rates Fringes

BRICKLAYER, STONEMASON, POINTER, CAULKER & CLEANER..$ 46.86 29.14

BRRI0003-002 09/01/2022

Rates Fringes

MARBLE SETTER, TERRAZZO WORKER & TILE SETTER........$ 46.54 30.34

BRRI0003-003 09/01/2022

Rates Fringes

MARBLE, TILE & TERRAZZO FINISHER....................$ 38.78 29.61

CARP0330-001 06/02/2025

DIVER (WHEN NOT DIVING OR TENDING THE DIVER, THE

DIVER AND DIVER TENDER SHALL RECEIVE THE PILEDRIVER

RATE. DIVER TENDERS SHALL RECEIVE $1.00 PER HOUR

ABOVE THE PILE DRIVER RATE WHEN TENDING THE DIVER.)

...................................................$ 60.83 30.50

DIVER TENDER (WHEN NOT DIVING OR TENDING THE DIVER,

THE DIVER AND DIVER TENDER SHALL RECEIVE THE

PILEDRIVER RATE. DIVER TENDERS SHALL RECEIVE $1.00

PER HOUR ABOVE THE PILE DRIVER RATE WHEN TENDING

THE DIVER.) ......................................$ 48.68 30.50

CARPENTER: INCLUDES SOFT FLOOR LAYER (WORK ON

FREE-STANDING STACKS, CONCRETE SILOS & PUBLIC

UTILITY ELECTRICAL POWER HOUSES, WHICH ARE OVER 35

FT. IN HEIGHT WHEN CONSTRUCTED: $.50 PER HOUR

ADDITIONAL. WORK ON EXTERIOR CONCRETE SHEAR WALL

GANG FORMS, 45 FT. OR MORE ABOVE GROUND ELEVATION

OR ON SETBACK: $.50 PER HOUR ADDITIONAL.)...........$ 47.88 30.50

PILEDRIVER (WORK ON FREE-STANDING STACKS, CONCRETE

SILOS & PUBLIC UTILITY ELECTRICAL POWER HOUSES,

WHICH ARE OVER 35 FT. IN HEIGHT WHEN CONSTRUCTED:

$.50 PER HOUR ADDITIONAL. WORK ON EXTERIOR CONCRETE

SHEAR WALL GANG FORMS, 45 FT. OR MORE ABOVE GROUND

ELEVATION OR ON SETBACK: $.50 PER HOUR ADDITIONAL.

THE DESIGNATED PILEDRIVER, KNOWN AS THE ""MONKEY"":

$1.00 PER HOUR ADDITIONAL...........................$ 41.53 29.35

WELDER (WORK ON FREE-STANDING STACKS, CONCRETE

SILOS & PUBLIC UTILITY ELECTRICAL POWER HOUSES,

WHICH ARE OVER 35 FT. IN HEIGHT WHEN CONSTRUCTED:

$.50 PER HOUR ADDITIONAL. WORK ON EXTERIOR

CONCRETE SHEAR WALL GANG FORMS, 45 FT. OR MORE

ABOVE GROUND ELEVATION OR ON SETBACK: $.50 PER HOUR

ADDITIONAL.) .......................................$ 48.68 30.50

CARP1121-002 04/21/2025

Rates Fringes

MILLWRIGHT..........................................$ 45.72 31.50

ELEC0099-002 06/01/2025

Rates Fringes

ELECTRICIAN (WORK OF A HAZARDOUS NATURE, OR WHERE

THE WORK HEIGHT IS 30 FT. OR MORE FROM THE FLOOR,

EXCEPT WHEN WORKING OSHA-APPROVED LIFTS: 20% PER

HOUR ADDITIONAL. WORK IN TUNNELS BELOW GROUND LEVEL

IN COMBINED SEWER OUTFALL: 20% PER HOUR

ADDITIONAL.)........................................$ 56.11 24.74

TELEDATA SYSTEM INSTALLER (WORK OF A HAZARDOUS

NATURE, OR WHERE THE WORK HEIGHT IS 30 FT. OR MORE

FROM THE FLOOR, EXCEPT WHEN WORKING OSHA-APPROVED

LIFTS: 20% PER HOUR ADDITIONAL. WORK IN TUNNELS

BELOW GROUND LEVEL IN COMBINED SEWER OUTFALL: 20%

PER HOUR ADDITIONAL.)...............................$ 42.09 19.71

ELEV0039-001 01/01/2025

Rates Fringes

ELEVATOR MECHANIC (ADDTIONAL FRINGE TO BE PAID A.

PAID HOLIDAYS: NEW YEARS DAY; MEMORIAL DAY;

INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY;

THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING

DAY; AND CHRISTMAS DAY. B. EMPLOYER CONTRIBUTES 8%

BASIC HOURLY RATE FOR 5 YEARS OR MORE OF SERVICE OF

6% BASIC HOURLY RATE FOR 6 MONTHS TO 5 YEARS OF

SERVICE AS VACATION PAY CREDIT.)....................$ 64.52 38.44

ENGI0057-001 12/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 1: CRANES, LIGHTERS, BOOM TRUCKS AND

DERRICKS. (BOOM LENGTHS, INCLUDING JIBS: 150 FEET

AND OVER + $ 2.00; 180 FEET AND OVER + $ 3.00;

210 FEET AND OVER + $ 4.00; 240 FEET AND OVER + $

5.00; 270 FEET AND OVER + $ 7.00; 300 FEET AND

OVER + $ 8.00; 350 FEET AND OVER + $ 9.00; 400

FEET AND OVER + $10.00); (PAID HOLIDAYS: NEW

YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, JULY

FOURTH, VICTORY DAY, LABOR DAY, COLUMBUS DAY,

VETERANS DAY, THANKSGIVING DAY, CHRISTMAS DAY. ANY

EMPLOYEE WHO WORKS 3 DAYS IN THE WEEK IN WHICH A

HOLIDAY FALLS SHALL BE PAID FOR THE HOLIDAY.)

(HAZMAT WORK: $2.00 PER HOUR ADDITIONAL.

TUNNEL/SHAFT WORK: $5.00 PER HOUR ADDITIONAL.)......$ 51.30 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 2: DIGGING MACHINE, ROSS CARRIER,

LOCOMOTIVE, HOIST, ELEVATOR, BIDWELL-TYPE MACHINE,

SHOT & WATER BLASTING MACHINE, PAVER, SPREADER,

GRADERS, FRONT END LOADER (3 YDS. AND OVER),

VIBRATORY HAMMER & VACUUM TRUCK, ROADHEADERS,

FORKLIFTS, ECONOMOBILE TYPE EQUIPMENT, TUNNEL

BORING MACHINES, CONCRETE PUMP AND ON SITE CONCRETE

PLANTS. (BOOM LENGTHS, INCLUDING JIBS: 150 FEET

AND OVER + $ 2.00; 180 FEET AND OVER + $ 3.00;

210 FEET AND OVER + $ 4.00; 240 FEET AND OVER + $

5.00; 270 FEET AND OVER + $ 7.00; 300 FEET AND

OVER + $ 8.00; 350 FEET AND OVER + $ 9.00; 400

FEET AND OVER + $10.00); (PAID HOLIDAYS: NEW

YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, JULY

FOURTH, VICTORY DAY, LABOR DAY, COLUMBUS DAY,

VETERANS DAY, THANKSGIVING DAY, CHRISTMAS DAY. ANY

EMPLOYEE WHO WORKS 3 DAYS IN THE WEEK IN WHICH A

HOLIDAY FALLS SHALL BE PAID FOR THE HOLIDAY.)

(HAZMAT WORK: $2.00 PER HOUR ADDITIONAL.

TUNNEL/SHAFT WORK: $5.00 PER HOUR ADDITIONAL.)......$ 49.30 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 3: OILERS ON CRANES. (BOOM LENGTHS,

INCLUDING JIBS: 150 FEET AND OVER + $ 2.00; 180

FEET AND OVER + $ 3.00; 210 FEET AND OVER + $

4.00; 240 FEET AND OVER + $ 5.00; 270 FEET AND

OVER + $ 7.00; 300 FEET AND OVER + $ 8.00; 350

FEET AND OVER + $ 9.00; 400 FEET AND OVER +

$10.00); (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY, CHRISTMAS DAY. ANY EMPLOYEE WHO

WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS

SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK:

$5.00 PER HOUR ADDITIONAL.).........................$ 44.92 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 4: OILER ON CRAWLER BACKHOE. (BOOM

LENGTHS, INCLUDING JIBS: 150 FEET AND OVER + $

2.00; 180 FEET AND OVER + $ 3.00; 210 FEET AND

OVER + $ 4.00; 240 FEET AND OVER + $ 5.00; 270

FEET AND OVER + $ 7.00; 300 FEET AND OVER + $

8.00; 350 FEET AND OVER + $ 9.00; 400 FEET AND

OVER + $10.00); (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY, CHRISTMAS DAY. ANY EMPLOYEE WHO

WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS

SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK:

$5.00 PER HOUR ADDITIONAL.) ...$ 42.07 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 5: BULLDOZER, BOBCATS, SKID STEER

LOADER, TRACTOR, SCRAPER, COMBINATION LOADER

BACKHOE, ROLLER, FRONT END LOADER (LESS THAN 3

YDS.), STREET AND MOBILE-POWERED SWEEPER (3-YD.

CAPACITY), 8-FT. SWEEPER MINIMUM 65 HP). (BOOM

LENGTHS, INCLUDING JIBS: 150 FEET AND OVER +

$2.00; 180 FEET AND OVER + $ 3.00; 210 FEET AND

OVER + $ 4.00; 240 FEET AND OVER + $ 5.00; 270

FEET AND OVER + $ 7.00; 300 FEET AND OVER + $

8.00; 350 FEET AND OVER + $ 9.00; 400 FEET AND

OVER + $10.00); (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY, CHRISTMAS DAY. ANY EMPLOYEE WHO

WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS

SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK:

$5.00 PER HOUR ADDITIONAL.).........................$ 48.35 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 6: WELL-POINT INSTALLATION CREW. (BOOM

LENGTHS, INCLUDING JIBS: 150 FEET AND OVER + $

2.00; 180 FEET AND OVER + $ 3.00; 210 FEET AND

OVER + $ 4.00; 240 FEET AND OVER + $ 5.00; 270

FEET AND OVER + $ 7.00; 300 FEET AND OVER + $

8.00; 350 FEET AND OVER + $ 9.00; 400 FEET AND

OVER + $10.00); (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY, CHRISTMAS DAY. ANY EMPLOYEE WHO

WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS

SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK:

$5.00 PER HOUR ADDITIONAL.).........................$ 39.15 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 7: UTILITY ENGINEERS AND SIGNAL

PERSONS. (BOOM LENGTHS, INCLUDING JIBS: 150 FEET

AND OVER + $ 2.00; 180 FEET AND OVER + $ 3.00;

210 FEET AND OVER + $ 4.00; 240 FEET AND OVER + $

5.00; 270 FEET AND OVER + $ 7.00; 300 FEET AND

OVER + $ 8.00; 350 FEET AND OVER + $ 9.00; 400

FEET AND OVER + $10.00); (PAID HOLIDAYS: NEW

YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, JULY

FOURTH, VICTORY DAY, LABOR DAY, COLUMBUS DAY,

VETERANS DAY, THANKSGIVING DAY, CHRISTMAS DAY. ANY

EMPLOYEE WHO WORKS 3 DAYS IN THE WEEK IN WHICH A

HOLIDAY FALLS SHALL BE PAID FOR THE HOLIDAY.)

(HAZMAT WORK: $2.00 PER HOUR ADDITIONAL.

TUNNEL/SHAFT WORK: $5.00 PER HOUR ADDITIONAL.)......$ 33.15 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 8: HEATER, CONCRETE MIXER, STONE

CRUSHER, WELDING MACHINE, GENERATOR AND LIGHT

PLANT, GAS AND ELECTRIC DRIVEN PUMP AND AIR

COMPRESSOR. (BOOM LENGTHS, INCLUDING JIBS: 150

FEET AND OVER + $ 2.00; 180 FEET AND OVER + $

3.00; 210 FEET AND OVER + $ 4.00; 240 FEET AND

OVER + $ 5.00; 270 FEET AND OVER + $ 7.00; 300

FEET AND OVER + $ 8.00; 350 FEET AND OVER + $

9.00; 400 FEET AND OVER + $10.00); (PAID

HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY,

MEMORIAL DAY, JULY FOURTH, VICTORY DAY, LABOR DAY,

COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY,

CHRISTMAS DAY. ANY EMPLOYEE WHO WORKS 3 DAYS IN THE

WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR THE

HOLIDAY.) (HAZMAT WORK: $2.00 PER HOUR ADDITIONAL.

TUNNEL/SHAFT WORK: $5.00 PER HOUR ADDITIONAL.).....$ 45.00 29.95

POWER EQUIPMENT OPERATOR: POWER PLANTS, SEWER

TREATMENT PLANTS, PUMPING STATIONS, TUNNELS,

CAISSONS, PIERS, DOCKS, BRIDGES, WIND TURBINES,

SUBTERRANEAN & OTHER MARINE AND HEAVY CONSTRUCTION

WORK: GROUP 9: BOAT & TUG OPERATOR. (BOOM LENGTHS,

INCLUDING JIBS: 150 FEET AND OVER + $ 2.00; 180

FEET AND OVER + $ 3.00; 210 FEET AND OVER + $

4.00; 240 FEET AND OVER + $ 5.00; 270 FEET AND

OVER + $ 7.00; 300 FEET AND OVER + $ 8.00; 350

FEET AND OVER + $ 9.00; 400 FEET AND OVER +

$10.00); (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY, CHRISTMAS DAY. ANY EMPLOYEE WHO

WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS

SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK:

$5.00 PER HOUR ADDITIONAL.).........................$ 48.92 29.95

ENGI0057-003 12/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 1: CRANES, LIGHTERS, BOOM TRUCKS AND

DERRICKS. (BOOM LENTHS, INCLUDING JIBS: 150 FT.

AND OVER: + $ 2.00; 180 FT. AND OVER: + $ 3.00;

210 FT. AND OVER: + $ 4.00; 240 FT. AND OVER: + $

5.00; 270 FT. AND OVER: + $ 7.00; 300 FT. AND

OVER: + $ 8.00; 350 FT. AND OVER: + $ 9.00; 400

FT. AND OVER: + $10.00) (PAID HOLIDAYS: NEW YEAR'S

DAY, PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH,

VICTORY DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY. A: ANY EMPLOYEE

WHO WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY

FALLS SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK: $5.00

PER HOUR ADDITIONAL.)...............................$ 50.57 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 2: DIGGING MACHINE, ROSS CARRIER,

LOCOMOTIVE, HOIST, ELEVATOR, BIDWELL-TYPE MACHINE,

SHOT & WATER BLASTING MACHINE, PAVER, SPREADER,

FRONT END LOADER (3 YDS. AND OVER), VIBRATORY

HAMMER AND VACUUM TRUCK. (BOOM LENTHS, INCLUDING

JIBS: 150 FT. AND OVER: + $ 2.00; 180 FT. AND

OVER: + $ 3.00; 210 FT. AND OVER: + $ 4.00; 240

FT. AND OVER: + $ 5.00; 270 FT. AND OVER: + $

7.00; 300 FT. AND OVER: + $ 8.00; 350 FT. AND

OVER: + $ 9.00; 400 FT. AND OVER: + $10.00) (PAID

HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL

DAY, JULY FOURTH, VICTORY DAY, LABOR DAY, COLUMBUS

DAY, VETERANS DAY, THANKSGIVING DAY & CHRISTMAS

DAY. A: ANY EMPLOYEE WHO WORKS 3 DAYS IN THE WEEK

IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR THE

HOLIDAY.) (HAZMAT WORK: $2.00 PER HOUR ADDITIONAL.

TUNNEL/SHAFT WORK: $5.00 PER HOUR ADDITIONAL.

............................$ 48.57 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 3: TELEHANDLER EQUIPMENT, FORKLIFT, CONCRETE

PUMP & ON-SITE CONCRETE PLANT. (BOOM LENTHS,

INCLUDING JIBS: 150 FT. AND OVER: + $ 2.00; 180

FT. AND OVER: + $ 3.00; 210 FT. AND OVER: + $

4.00; 240 FT. AND OVER: + $ 5.00; 270 FT. AND

OVER: + $ 7.00; 300 FT. AND OVER: + $ 8.00; 350

FT. AND OVER: + $ 9.00; 400 FT. AND OVER: +

$10.00) (PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S

DAY, MEMORIAL DAY, JULY FOURTH, VICTORY DAY, LABOR

DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY &

CHRISTMAS DAY. A: ANY EMPLOYEE WHO WORKS 3 DAYS IN

THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR

THE HOLIDAY.) (HAZMAT WORK: $2.00 PER HOUR

ADDITIONAL. TUNNEL/SHAFT WORK: $5.00 PER HOUR

ADDITIONAL.)........................................$ 48.35 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 4: FIREMAN & OILER ON CRANES. (BOOM LENTHS,

INCLUDING JIBS: 150 FT. AND OVER: + $ 2.00; 180

FT. AND OVER: + $ 3.00; 210 FT. AND OVER: + $

4.00; 240 FT. AND OVER: + $ 5.00; 270 FT. AND

OVER: + $ 7.00; 300 FT. AND OVER: + $ 8.00; 350

FT. AND OVER: + $ 9.00; 400 FT. AND OVER: +

$10.00) (PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S

DAY, MEMORIAL DAY, JULY FOURTH, VICTORY DAY, LABOR

DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY &

CHRISTMAS DAY. A: ANY EMPLOYEE WHO WORKS 3 DAYS IN

THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR

THE HOLIDAY.) (HAZMAT WORK: $2.00 PER HOUR

ADDITIONAL. TUNNEL/SHAFT WORK: $5.00 PER HOUR

ADDITIONAL.)........................................$ 44.35 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 5: OILER ON CRAWLER BACKHOE. (BOOM LENTHS,

INCLUDING JIBS: 150 FT. AND OVER: + $ 2.00; 180

FT. AND OVER: + $ 3.00; 210 FT. AND OVER: + $

4.00; 240 FT. AND OVER: + $ 5.00; 270 FT. AND

OVER: + $ 7.00; 300 FT. AND OVER: + $ 8.00; 350

FT. AND OVER: + $ 9.00; 400 FT. AND OVER: +

$10.00) (PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S

DAY, MEMORIAL DAY, JULY FOURTH, VICTORY DAY, LABOR

DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY &

CHRISTMAS DAY. A: ANY EMPLOYEE WHO WORKS 3 DAYS IN

THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR

THE HOLIDAY.) (HAZMAT WORK: $2.00 PER HOUR

ADDITIONAL. TUNNEL/SHAFT WORK: $5.00 PER HOUR

ADDITIONAL.)........................................$ 41.50 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 6: BULLDOZER,SKID STEER LOADERS,BOBCATS,

TRACTOR, GRADER, SCRAPER,COMBINATION LOADER

BACKHOE, ROLLER, FRONT END LOADER (LESS THAN 3

YDS.), STREET AND MOBILE POWERED SWEEPER (3 YDS.

CAPACITY), 8-FT. SWEEPER (MINIMUM 65 HP). (BOOM

LENTHS, INCLUDING JIBS: 150 FT. AND OVER: + $

2.00; 180 FT. AND OVER: + $ 3.00; 210 FT. AND

OVER: + $ 4.00; 240 FT. AND OVER: + $ 5.00; 270

FT. AND OVER: + $ 7.00; 300 FT. AND OVER: + $

8.00; 350 FT. AND OVER: + $ 9.00; 400 FT. AND

OVER: + $10.00) (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY. A: ANY EMPLOYEE

WHO WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY

FALLS SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK: $5.00

PER HOUR ADDITIONAL.)...............................$ 47.65 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 7: WELL POINT INSTALLATION CREW. (BOOM

LENTHS, INCLUDING JIBS: 150 FT. AND OVER: + $

2.00; 180 FT. AND OVER: + $ 3.00; 210 FT. AND

OVER: + $ 4.00; 240 FT. AND OVER: + $ 5.00; 270

FT. AND OVER: + $ 7.00; 300 FT. AND OVER: + $

8.00; 350 FT. AND OVER: + $ 9.00; 400 FT. AND

OVER: + $10.00) (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY. A: ANY EMPLOYEE

WHO WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY

FALLS SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK: $5.00

PER HOUR ADDITIONAL.)...............................$ 47.22 29.95

POWER EQUIPMENT OPERATOR: BUILDING CONSTRUCTION:

GROUP 8: HEATER, CONCRETE MIXER, STONE CRUSHER,

WELDING MACHINE, GENERATOR FOR LIGHT PLANT, GAS AND

ELECTRIC DRIVEN PUMP & AIR COMPRESSOR. (BOOM

LENTHS, INCLUDING JIBS: 150 FT. AND OVER: + $

2.00; 180 FT. AND OVER: + $ 3.00; 210 FT. AND

OVER: + $ 4.00; 240 FT. AND OVER: + $ 5.00; 270

FT. AND OVER: + $ 7.00; 300 FT. AND OVER: + $

8.00; 350 FT. AND OVER: + $ 9.00; 400 FT. AND

OVER: + $10.00) (PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY. A: ANY EMPLOYEE

WHO WORKS 3 DAYS IN THE WEEK IN WHICH A HOLIDAY

FALLS SHALL BE PAID FOR THE HOLIDAY.) (HAZMAT WORK:

$2.00 PER HOUR ADDITIONAL. TUNNEL/SHAFT WORK: $5.00

PER HOUR ADDITIONAL.)...............................$ 44.54 29.95

ENGI0057-005 12/01/2025

Rates Fringes

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 1:

CRANES, PILE DRIVERS, LIGHTERS, BOOM TRUCKS,

HOISTS, DERRICKS. (ANY EMPLOYEE WHO WORKS THREE

DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE

PAID FOR THE HOLIDAY. PAID HOLIDAYS: NEW YEAR'S

DAY, PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH,

VICTORY DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.)..................$ 46.45 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 2:

DIGGING MACHINES, EXCAVATORS, LOCOMOTIVES, JOHN

HENRY'S, DIRECTIONAL DRILLING MACHINES, COLD

PLANERS, RECLAIMERS, PAVERS, SPREADERS, GRADERS,

FRONT-END LOADERS (3YDS & OVER), VACUUM TRUCK,

DRILL/BORING MACHINE OPERATORS, VERMEER SAW, WATER

BLASTER, HYDRAULIC-DEMOLITION ROBOT, ROSS CARRIERS,

CONCRETE PUMP OPERATORS, ASPHALT/MATERIAL TRANSFER

MACHINES, ROTATING TELEHANDLERS, SPMT TYPE

EQUIPMENT. (ANY EMPLOYEE WHO WORKS THREE DAYS IN

THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR

THE HOLIDAY. PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.) DAY, PRESIDENT'S

DAY, MEMORIAL DAY, JULY FOURTH, VICTORY DAY, LABOR

DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY &

CHRISTMAS DAY.......................................$ 44.45 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 3:

WELLPOINT INSTALLATION AND DRILL/BORING MACHINE

ASSISTANTS. (ANY EMPLOYEE WHO WORKS THREE DAYS IN

THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR

THE HOLIDAY. PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.)..................$ 39.15 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 4:

UTILITY ENGINEERS. (ANY EMPLOYEE WHO WORKS THREE

DAYS IN THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE

PAID FOR THE HOLIDAY. PAID HOLIDAYS: NEW YEAR'S

DAY, PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH,

VICTORY DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.)..................$ 25.75 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 5:

SIGNAL PERSONS. (ANY EMPLOYEE WHO WORKS THREE DAYS

IN THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID

FOR THE HOLIDAY. PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.)..................$ 33.15 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 6:

OILERS ON CRANES AND DECKHANDS. (ANY EMPLOYEE WHO

WORKS THREE DAYS IN THE WEEK IN WHICH A HOLIDAY

FALLS SHALL BE PAID FOR THE HOLIDAY. PAID

HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL

DAY, JULY FOURTH, VICTORY DAY, LABOR DAY, COLUMBUS

DAY, VETERANS DAY, THANKSGIVING DAY & CHRISTMAS

DAY.)...............................................$ 39.73 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 7:

COMBINATION LOADER / BACKHOES, FRONT-END LOADERS

(LESS THAN 3 YDS.), FORKLIFT, BULLDOZERS, SCRAPERS,

BOATS, ROLLERS, SKID STEER LOADERS (REGARDLESS OF

ATTACHMENTS), STREET SWEEPERS, MECHANICS, WELDERS,

OPERATORS IN MATERIALS YARDS, SHOPS AND GARAGES.

(ANY EMPLOYEE WHO WORKS THREE DAYS IN THE WEEK IN

WHICH A HOLIDAY FALLS SHALL BE PAID FOR THE

HOLIDAY. PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.)..................$ 43.43 29.95

POWER EQUIPMENT OPERATOR: HIGHWAY CONSTRUCTION

PROJECTS; WATER AND SEWERLINE PROJECTS WHICH ARE

INCIDENTAL TO HIGHWAY CONSTRUCTION PROJECTS; AND

BRIDGE PROJECTS THAT DO NOT SPAN WATER: GROUP 8:

GAS AND ELECTRIC DRIVE HEATERS, CONCRETE MIXERS,

LIGHT PLANTS, WELDING MACHINES, PUMPS AND

COMPRESSORS. (ANY EMPLOYEE WHO WORKS THREE DAYS IN

THE WEEK IN WHICH A HOLIDAY FALLS SHALL BE PAID FOR

THE HOLIDAY. PAID HOLIDAYS: NEW YEAR'S DAY,

PRESIDENT'S DAY, MEMORIAL DAY, JULY FOURTH, VICTORY

DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY,

THANKSGIVING DAY & CHRISTMAS DAY.)..................$ 38.70 29.95

IRON0037-001 09/16/2025

Rates Fringes

IRONWORKER..........................................$ 43.03 33.53

LABO0271-001 12/03/2023

Rates Fringes LABORER (BUILDING CONSTRUCTION): GROUP 1: Laborer, Carpenter Tender, Mason Tender, Cement Finisher Tender, Scaffold Erector, Wrecking Laborer, Asbestos Removal [Non-Mechanical Systems............$ 37.00 26.90 LABORER (BUILDING CONSTRUCTION): GROUP 2: Asphalt Raker, Adzemen, Pipe Trench Bracer, Demolition Burner, Chain Saw Operator, Fence & Guard Rail Erector, Setter of Metal Forms for Roadways, Mortar Mixer, Pipelayer, Riprap & Dry Stonewall Builder, Highway Stone Spreader, Pneumatic Tool Operator, Wagon Drill Operator, Tree Trimmer, Barco-Type Jumping Tamper, Mechanical Grinder Operator.........$ 37.00 26.90 LABORER (BUILDING CONSTRUCTION): GROUP 3: Pre-Cast Floor & Roof Plank Erectors.........................$ 37.00 26.90 LABORER (BUILDING CONSTRUCTION): GROUP 4: Air Track Operator, Hydraulic & Similar Self-Powered Drill, Block Paver, Rammer, Curb Setter, Powderman & Blaster.............................................$ 37.00 26.90 LABORER (BUILDING CONSTRUCTION): GROUP 5: Toxic Waste Remover.......................................$ 39.00 26.90

LABO0271-002 11/27/2022

LABORER (HEAVY AND HIGHWAY CONSTRUCTION):

COMPRESSED AIR: GROUP 1:Mucking machine operator, tunnel laborer, brake person, track person, miner, grout person, lock tender, gauge tender, miner:

motor person & all others in compressed air ........$ 55.40 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION):

COMPRESSED AIR: GROUP 2: Change house attendant, powder watchperson, top person on iron ............$ 52.93 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION):

COMPRESSED AIR: GROUP 3: Hazardous waste work within the ""HOT"" zone...............................$ 42.45 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): FREE AIR:

GROUP 1: Grout person - pumps, brake person, track person, form mover & stripper (wood & steel), shaft laborer, laborer topside, outside motorperson, miner, conveyor operator, miner welder, heading motorperson, erecting operator, mucking machine operator, nozzle person, rodperson, safety miner, shaft & tunnel, steel & rodperson, mole nipper, concrete worker, form erector (wood, steel and all accessories), cement finisher (this type of work only), top signal person, bottom person (when heading is 50' from shaft), burner, shield operator and TBM operator....................................$ 46.00 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): FREE AIR:

GROUP 2: Change house attendant, powder watchperson $ 45.00 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): FREE AIR:

GROUP 3: Hazardous waste work within the ""HOT"" zone.$ 42.45 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): GROUP 1:

Laborer; Carpenter tender; Cement finisher tender;

Wrecking laborer; Asbestos removers [non-mechanical systems]; Plant laborer; Driller in quarries........$ 33.05 24.05

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): GROUP 2:

Adzeperson; Asphalt raker; Barcotype jumping tamper; Chain saw operators; Concrete and power buggy operator; Concrete saw operator; Demolition burner; Fence and guard rail erector; Highway stone spreader; Laser beam operator; Mechanical grinder operator; Mason tender; Mortar mixer; Pneumatic tool operator; Riprap and dry stonewall builder;

Scaffold erector; Setter of metal forms for roadways; Wagon drill operator; Wood chipper operator; Pipelayer; Pipe trench bracer ...........$ 35.75 24.85

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): GROUP 3:

Air track drill operator; Hydraulic and similar powered drills; Brick paver; Block paver; Rammer and curb setter; Powderperson and blaster...........$ 36.50 24.85

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): GROUP 4:

Flagger & signaler..................................$ 29.00 24.85

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): GROUP 5:

Toxic waste remover ................................$ 37.50 24.85

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): OPEN AIR

CAISSON, UNDERPINNING WORK AND BORING CREW: BOTTOM

MAN.................................................$ 41.50 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): OPEN AIR

CAISSON, UNDERPINNING WORK AND BORING CREW: TOP MAN

& LABORER...........................................$ 35.60 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): TEST

BORING: DRILLER.....................................$ 41.95 24.15

LABORER (HEAVY AND HIGHWAY CONSTRUCTION): TEST

BORING: LABORER.....................................$ 41.95 24.15

PAIN0011-005 06/01/2025

Rates Fringes

PAINTER (BRUSH AND ROLLER)..........................$ 39.57 26.60

PAINTER (EPOXY, TANKS, TOWERS, SWING STAGE &

STRUCTURAL STEEL)...................................$ 41.57 26.60

PAINTER (SPRAY, SAND & WATER BLASTING)..............$ 42.57 26.60

PAINTER (TAPER).....................................$ 38.82 25.80

PAINTER (WALL COVERER)..............................$ 38.57 25.80

PAIN0011-006 06/01/2024

GLAZIER (SWING STAGE: $1.00 PER HOUR ADDITIONAL.

PAID HOLIDAYS: LABOR DAY & CHRISTMAS DAY.)..........$ 41.63 26.15

PAIN0011-011 06/01/2024

Rates Fringes

PAINTER (BRIDGE WORK)...............................$ 57.85 26.40

PAIN0035-008 06/01/2011

Rates Fringes

SIGN PAINTER........................................$ 24.79 13.72

PLAS0040-001 01/01/2025

Rates Fringes

CEMENT MASON/CONCRETE FINISHER (BUILDING

CONSTRUCTION) (CEMENT MASON: WORK ON FREE SWINGING

SCAFFOLDS UNDER 3 PLANKS WIDTH AND WHICH IS 20 OR

MORE FEET ABOVE GROUND AND ANY OFFSET STRUCTURE:

$.30 PER HOUR ADDITIONAL.)..........................$ 44.75 29.10

PLAS0040-002 01/01/2025

Rates Fringes

CEMENT MASON/CONCRETE FINISHER (HEAVY AND HIGHWAY

CONSTRUCTION).......................................$ 40.45 25.30

PLAS0040-003 01/01/2025

Rates Fringes

PLASTERER...........................................$ 45.52 29.43

PLUM0051-002 08/25/2025

Rates Fringes

PLUMBERS AND PIPEFITTERS............................$ 54.34 34.50

ROOF0033-004 12/01/2025

Rates Fringes

ROOFER..............................................$ 47.49 31.44

SFRI0669-001 04/01/2025

Rates Fringes

SPRINKLER FITTER....................................$ 53.76 33.44

SHEE0017-002 06/01/2025

Rates Fringes

SHEET METAL WORKER..................................$ 44.42 41.94

TEAM0251-001 05/01/2025

Rates Fringes

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

1: PICK-UP TRUCKS, STATION WAGONS, & PANEL TRUCKS

(ADDITIONAL FRINGE TO BE PAID: PAID HOLIDAYS: NEW

YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR

DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PLUS

PRESIDENTS' DAY, COLUMBUS DAY, VETERAN'S DAY & V-J

DAY, PROVIDING THE EMPLOYEE HAS WORKED AT LEAST ONE

DAY IN THE CALENDAR WEEK IN WHICH THE HOLIDAY

FALLS. EMPLOYEE WHO HAS BEEN ON THE PAYROLL FOR 1

YEAR OR MORE BUT LESS THAN 5 YEARS AND HAS WORKED

150 DAYS DURING THE LAST YEAR OF EMPLOYMENT SHALL

RECEIVE 1 WEEK'S PAID VACATION; 5 TO 10 YEARS - 2

WEEKS' PAID VACATION; 10 OR MORE YEARS - 3 WEEK'S

PAID VACATION.) (EMPLOYEES ON THE SENIORITY LIST

SHALL BE PAID A ONE HUNDRED DOLLAR ($100.00) BONUS

FOR EVERY FOUR HUNDRED (400) HOURS WORKED, UP TO A

MAXIMUM OF FIVE HUNDRED DOLLARS ($500.00)) (ALL

DRIVERS WORKING ON A DEFINED HAZARD MATERIAL JOB

SITE SHALL BE PAID A PREMIUM OF $2.00 PER HOUR OVER

APPLICABLE RATE.) ...................$ 31.86 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

2: TWO-AXLE ON LOW BEDS (ADDITIONAL FRINGE TO BE

PAID: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND

CHRISTMAS DAY, PLUS PRESIDENTS' DAY, COLUMBUS DAY,

VETERAN'S DAY & V-J DAY, PROVIDING THE EMPLOYEE HAS

WORKED AT LEAST ONE DAY IN THE CALENDAR WEEK IN

WHICH THE HOLIDAY FALLS. EMPLOYEE WHO HAS BEEN ON

THE PAYROLL FOR 1 YEAR OR MORE BUT LESS THAN 5

YEARS AND HAS WORKED 150 DAYS DURING THE LAST YEAR

OF EMPLOYMENT SHALL RECEIVE 1 WEEK'S PAID VACATION;

5 TO 10 YEARS - 2 WEEKS' PAID VACATION; 10 OR MORE

YEARS - 3 WEEK'S PAID VACATION.) (EMPLOYEES ON THE

SENIORITY LIST SHALL BE PAID A ONE HUNDRED DOLLAR

($100.00) BONUS FOR EVERY FOUR HUNDRED (400) HOURS

WORKED, UP TO A MAXIMUM OF FIVE HUNDRED DOLLARS

($500.00)) (ALL DRIVERS WORKING ON A DEFINED HAZARD

MATERIAL JOB SITE SHALL BE PAID A PREMIUM OF $2.00

PER HOUR OVER APPLICABLE RATE.) .....$ 32.01 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

3: TWO-AXLE DUMP TRUCK (ADDITIONAL FRINGE TO BE

PAID: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND

CHRISTMAS DAY, PLUS PRESIDENTS' DAY, COLUMBUS DAY,

VETERAN'S DAY & V-J DAY, PROVIDING THE EMPLOYEE HAS

WORKED AT LEAST ONE DAY IN THE CALENDAR WEEK IN

WHICH THE HOLIDAY FALLS. EMPLOYEE WHO HAS BEEN ON

THE PAYROLL FOR 1 YEAR OR MORE BUT LESS THAN 5

YEARS AND HAS WORKED 150 DAYS DURING THE LAST YEAR

OF EMPLOYMENT SHALL RECEIVE 1 WEEK'S PAID VACATION;

5 TO 10 YEARS - 2 WEEKS' PAID VACATION; 10 OR MORE

YEARS - 3 WEEK'S PAID VACATION.) (EMPLOYEES ON THE

SENIORITY LIST SHALL BE PAID A ONE HUNDRED DOLLAR

($100.00) BONUS FOR EVERY FOUR HUNDRED (400) HOURS

WORKED, UP TO A MAXIMUM OF FIVE HUNDRED DOLLARS

($500.00)) (ALL DRIVERS WORKING ON A DEFINED HAZARD

MATERIAL JOB SITE SHALL BE PAID A PREMIUM OF $2.00

PER HOUR OVER APPLICABLE RATE.) .....$ 32.06 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

4: THREE-AXLE DUMP TRUCK (ADDITIONAL FRINGE TO BE

PAID: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND

CHRISTMAS DAY, PLUS PRESIDENTS' DAY, COLUMBUS DAY,

VETERAN'S DAY & V-J DAY, PROVIDING THE EMPLOYEE HAS

WORKED AT LEAST ONE DAY IN THE CALENDAR WEEK IN

WHICH THE HOLIDAY FALLS. EMPLOYEE WHO HAS BEEN ON

THE PAYROLL FOR 1 YEAR OR MORE BUT LESS THAN 5

YEARS AND HAS WORKED 150 DAYS DURING THE LAST YEAR

OF EMPLOYMENT SHALL RECEIVE 1 WEEK'S PAID VACATION;

5 TO 10 YEARS - 2 WEEKS' PAID VACATION; 10 OR MORE

YEARS - 3 WEEK'S PAID VACATION.) (EMPLOYEES ON THE

SENIORITY LIST SHALL BE PAID A ONE HUNDRED DOLLAR

($100.00) BONUS FOR EVERY FOUR HUNDRED (400) HOURS

WORKED, UP TO A MAXIMUM OF FIVE HUNDRED DOLLARS

($500.00)) (ALL DRIVERS WORKING ON A DEFINED HAZARD

MATERIAL JOB SITE SHALL BE PAID A PREMIUM OF $2.00

PER HOUR OVER APPLICABLE RATE.) .....$ 32.11 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

5: FOUR- AND FIVE-AXLE EQUIPMENT. (ADDITIONAL

FRINGE TO BE PAID: PAID HOLIDAYS: NEW YEAR'S DAY,

MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY,

THANKSGIVING DAY AND CHRISTMAS DAY, PLUS

PRESIDENTS' DAY, COLUMBUS DAY, VETERAN'S DAY & V-J

DAY, PROVIDING THE EMPLOYEE HAS WORKED AT LEAST ONE

DAY IN THE CALENDAR WEEK IN WHICH THE HOLIDAY

FALLS. EMPLOYEE WHO HAS BEEN ON THE PAYROLL FOR 1

YEAR OR MORE BUT LESS THAN 5 YEARS AND HAS WORKED

150 DAYS DURING THE LAST YEAR OF EMPLOYMENT SHALL

RECEIVE 1 WEEK'S PAID VACATION; 5 TO 10 YEARS - 2

WEEKS' PAID VACATION; 10 OR MORE YEARS - 3 WEEK'S

PAID VACATION.) (EMPLOYEES ON THE SENIORITY LIST

SHALL BE PAID A ONE HUNDRED DOLLAR ($100.00) BONUS

FOR EVERY FOUR HUNDRED (400) HOURS WORKED, UP TO A

MAXIMUM OF FIVE HUNDRED DOLLARS ($500.00)) (ALL

DRIVERS WORKING ON A DEFINED HAZARD MATERIAL JOB

SITE SHALL BE PAID A PREMIUM OF $2.00 PER HOUR OVER

APPLICABLE RATE.) ...................$ 32.21 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

6: LOW-BED OR BOOM TRAILER. (ADDITIONAL FRINGE TO

BE PAID: PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL

DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY

AND CHRISTMAS DAY, PLUS PRESIDENTS' DAY, COLUMBUS

DAY, VETERAN'S DAY & V-J DAY, PROVIDING THE

EMPLOYEE HAS WORKED AT LEAST ONE DAY IN THE

CALENDAR WEEK IN WHICH THE HOLIDAY FALLS. EMPLOYEE

WHO HAS BEEN ON THE PAYROLL FOR 1 YEAR OR MORE BUT

LESS THAN 5 YEARS AND HAS WORKED 150 DAYS DURING

THE LAST YEAR OF EMPLOYMENT SHALL RECEIVE 1 WEEK'S

PAID VACATION; 5 TO 10 YEARS - 2 WEEKS' PAID

VACATION; 10 OR MORE YEARS - 3 WEEK'S PAID

VACATION.) (EMPLOYEES ON THE SENIORITY LIST SHALL

BE PAID A ONE HUNDRED DOLLAR ($100.00) BONUS FOR

EVERY FOUR HUNDRED (400) HOURS WORKED, UP TO A

MAXIMUM OF FIVE HUNDRED DOLLARS ($500.00)) (ALL

DRIVERS WORKING ON A DEFINED HAZARD MATERIAL JOB

SITE SHALL BE PAID A PREMIUM OF $2.00 PER HOUR OVER

APPLICABLE RATE.) ...................$ 32.61 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

7: TRAILERS WHEN USED ON A DOUBLE HOOK UP (PULLING

2 TRAILERS). (ADDITIONAL FRINGE TO BE PAID: PAID

HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND

CHRISTMAS DAY, PLUS PRESIDENTS' DAY, COLUMBUS DAY,

VETERAN'S DAY & V-J DAY, PROVIDING THE EMPLOYEE HAS

WORKED AT LEAST ONE DAY IN THE CALENDAR WEEK IN

WHICH THE HOLIDAY FALLS. EMPLOYEE WHO HAS BEEN ON

THE PAYROLL FOR 1 YEAR OR MORE BUT LESS THAN 5

YEARS AND HAS WORKED 150 DAYS DURING THE LAST YEAR

OF EMPLOYMENT SHALL RECEIVE 1 WEEK'S PAID VACATION;

5 TO 10 YEARS - 2 WEEKS' PAID VACATION; 10 OR MORE

YEARS - 3 WEEK'S PAID VACATION.) (EMPLOYEES ON THE

SENIORITY LIST SHALL BE PAID A ONE HUNDRED DOLLAR

($100.00) BONUS FOR EVERY FOUR HUNDRED (400) HOURS

WORKED, UP TO A MAXIMUM OF FIVE HUNDRED DOLLARS

($500.00)) (ALL DRIVERS WORKING ON A DEFINED HAZARD

MATERIAL JOB SITE SHALL BE PAID A PREMIUM OF $2.00

PER HOUR OVER APPLICABLE RATE.)

.................................................$ 32.81 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

8: SPECIAL EARTH-MOVING EQUIPMENT, UNDER 35

TONS.(ADDITIONAL FRINGE TO BE PAID: PAID HOLIDAYS:

NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY,

LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PLUS

PRESIDENTS' DAY, COLUMBUS DAY, VETERAN'S DAY & V-J

DAY, PROVIDING THE EMPLOYEE HAS WORKED AT LEAST ONE

DAY IN THE CALENDAR WEEK IN WHICH THE HOLIDAY

FALLS. EMPLOYEE WHO HAS BEEN ON THE PAYROLL FOR 1

YEAR OR MORE BUT LESS THAN 5 YEARS AND HAS WORKED

150 DAYS DURING THE LAST YEAR OF EMPLOYMENT SHALL

RECEIVE 1 WEEK'S PAID VACATION; 5 TO 10 YEARS - 2

WEEKS' PAID VACATION; 10 OR MORE YEARS - 3 WEEK'S

PAID VACATION.) (EMPLOYEES ON THE SENIORITY LIST

SHALL BE PAID A ONE HUNDRED DOLLAR ($100.00) BONUS

FOR EVERY FOUR HUNDRED (400) HOURS WORKED, UP TO A

MAXIMUM OF FIVE HUNDRED DOLLARS ($500.00)) (ALL

DRIVERS WORKING ON A DEFINED HAZARD MATERIAL JOB

SITE SHALL BE PAID A PREMIUM OF $2.00 PER HOUR OVER

APPLICABLE RATE.) ...................$ 32.31 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

9: SPECIAL EARTH-MOVING EQUIPMENT, 35 TONS OR

OVER. (ADDITIONAL FRINGE TO BE PAID: PAID HOLIDAYS:

NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY,

LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY, PLUS

PRESIDENTS' DAY, COLUMBUS DAY, VETERAN'S DAY & V-J

DAY, PROVIDING THE EMPLOYEE HAS WORKED AT LEAST ONE

DAY IN THE CALENDAR WEEK IN WHICH THE HOLIDAY

FALLS. EMPLOYEE WHO HAS BEEN ON THE PAYROLL FOR 1

YEAR OR MORE BUT LESS THAN 5 YEARS AND HAS WORKED

150 DAYS DURING THE LAST YEAR OF EMPLOYMENT SHALL

RECEIVE 1 WEEK'S PAID VACATION; 5 TO 10 YEARS - 2

WEEKS' PAID VACATION; 10 OR MORE YEARS - 3 WEEK'S

PAID VACATION.) (EMPLOYEES ON THE SENIORITY LIST

SHALL BE PAID A ONE HUNDRED DOLLAR ($100.00) BONUS

FOR EVERY FOUR HUNDRED (400) HOURS WORKED, UP TO A

MAXIMUM OF FIVE HUNDRED DOLLARS ($500.00)) (ALL

DRIVERS WORKING ON A DEFINED HAZARD MATERIAL JOB

SITE SHALL BE PAID A PREMIUM OF $2.00 PER HOUR OVER

APPLICABLE RATE.) ...................$ 32.56 34.51

TRUCK DRIVER: HEAVY AND HIGHWAY CONSTRUCTION: GROUP

10: TRACTOR TRAILER. (ADDITIONAL FRINGE TO BE PAID:

PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY,

INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND

CHRISTMAS DAY, PLUS PRESIDENTS' DAY, COLUMBUS DAY,

VETERAN'S DAY & V-J DAY, PROVIDING THE EMPLOYEE HAS

WORKED AT LEAST ONE DAY IN THE CALENDAR WEEK IN

WHICH THE HOLIDAY FALLS. EMPLOYEE WHO HAS BEEN ON

THE PAYROLL FOR 1 YEAR OR MORE BUT LESS THAN 5

YEARS AND HAS WORKED 150 DAYS DURING THE LAST YEAR

OF EMPLOYMENT SHALL RECEIVE 1 WEEK'S PAID VACATION;

5 TO 10 YEARS - 2 WEEKS' PAID VACATION; 10 OR MORE

YEARS - 3 WEEK'S PAID VACATION.) (EMPLOYEES ON THE

SENIORITY LIST SHALL BE PAID A ONE HUNDRED DOLLAR

($100.00) BONUS FOR EVERY FOUR HUNDRED (400) HOURS

WORKED, UP TO A MAXIMUM OF FIVE HUNDRED DOLLARS

($500.00)) (ALL DRIVERS WORKING ON A DEFINED HAZARD

MATERIAL JOB SITE SHALL BE PAID A PREMIUM OF $2.00

PER HOUR OVER APPLICABLE RATE.) ...$ 32.36 34.51

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than SU, UAVG, SA, or SC denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The SU identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .