N4008525R2520 Amendment_0004.pdf

PDF 366 KB Posted

Attached to
Pier 11 Partial Demolition
Solicitation number
N4008525R2520
Issued by

About this file

This document is an amendment to a solicitation for the partial demolition of Pier 11 at Naval Station Norfolk in Norfolk, Virginia. The amendment provides design revisions and responses to 79 pre-proposal inquiries. Key details include:

The solicitation is for an IDIQ MACC contract for waterfront construction projects in the Hampton Roads area. The project requires the partial demolition of Pier 11, including the extraction or cutting of 170-foot 24x24-inch concrete piles. Responses to pre-proposal inquiries address topics such as proposal submission requirements, hazardous material surveys, protected species monitoring, site access and laydown areas, and reinforcing steel specifications. The solicitation has a hard completion date of June 15, 2025, with an anticipated award in early December 2024. Contractors under the specified IDIQ MACC contracts are eligible to submit proposals for this project.

View the file

Other files

File Type Posted
Design Revision 02.pdf PDF
Design Revisions 01_response to 54 ppi.pdf PDF
N4008525R2520 Amendment_0003.pdf PDF
N40085-05-R-5000-RDdwg 5 of 6.pdf PDF
N40085-05-R-5000-RDdwg 4 of 6.pdf PDF
N40085-05-R-5000-RDdwg 2 of 6.pdf PDF
N40085-05-R-5000-RDdwg 1 of 6.pdf PDF
Pier 11 General_Requirements REV1.pdf PDF
N4008525R2520 Amendment_0002.pdf PDF
N40085-05-R-5000-RDdwg 6 of 6.pdf PDF
N40085-05-R-5000-RDdwg 3 of 6.pdf PDF
N4008525R2520 Amendment 0001.pdf PDF
ATTACHMENT L Site Visit Log.pdf PDF
ATTACHMENT J Provision 52.204-24.pdf PDF
ATTACHMENT I Acknowledgment of Amedments.pdf PDF
ATTACHMENT G PIEE Vendor Access Instructions.pdf PDF
ATTACHMENT M Provision 252.225-7967 Prohibitation Regarding Russian Fossil Fuel.pdf PDF
ATTACHMENT A 1772159_SPECS .pdf PDF
ATTACHMENT H Supplementry Instructions to Offerors.pdf PDF
ATTACHMENT D SECNAV 5512_1.pdf PDF
ATTACHMENT B 1772159_DWG.pdf PDF
ATTACHMENT L Provision 252.225-7059.pdf PDF
ATTACHMENT K Provision 52.204-27.pdf PDF
ATTACHMENT F Pre-Proposal Inquiry (PPI) Form.xlsx XLSX spreadsheet
ATTACHMENT E - ODP.xls XLS spreadsheet
ATTACHMENT C General Decision Number VA20240160 21Jun24.pdf PDF
Pier 11 General_Requirements.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

J 1 8

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0004 11/15/2024

6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code

NAVFACSYSCOM MID-ATLANTIC

PWD NORFOLK

FACILITIES ENGINEERING & ACQ DIV

9324 VIRGINIA AVENUE

NORFOLK, VA 23511

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N40085-25-R-2520

9B. DATED (SEE ITEM 11)

10/21/2024

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

N4008525R2520, PIER 11 PARTIAL DEMOLITION, NAVAL STATION NORFOLK, NORFOLK, VIRGINIA

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Contact POC: Natalya Kuti (757) 341-0563; natalya.kuti.civ@us.navy.mil

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

SECTION SF30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

AMENDMENT 0004

The purpose of this amendment is to:

1. Provide Design Revision 02 (Revised Responses to #10, 13, 50, 78, and 79)

2. Provide Responses to Pre-Proposal Inquiries (PPIs) #3

All other terms and conditions remain unchanged.

1. Provide Design Revision 02 (Revised Responses to #10, 13, 50, 78, and 79)

See Attachment Design Revision 02

2. Responses to PPIs #1-79 (Revised Responses to 10, 13, 50, 78, and 79)

PPI # Date Submitted

LEAVE

BLANK Reference Question Response

Page Section Paragraph

1 10/22/24 4 of 7 Proposal Delivery

Information

The referenced paragraph states, "Proposals shall be submitted electronically through the PIEE Solicitation Module in accordance with the instructions below by the proposal due date. Offerors may also [emphasis added] send proposals via Federal Express (FedEx), United Parcel Service (UPS), or hand-carried to the following address no later than three (3) calendar days after the electronic proposal due date (hard copy submission in addition to the electronic submission, not in lieu of ).

Please confirm our interpretation of, "may also" to mean that proposals are required to be submitted electroncially via PIEE, but that a hardcopy submission is OPTIONAL.

Yes, the requirement is to submit proposals electronically via PIEE, submission of a hard copy is optional and is not mandatory.

2 10/23/24 20 01 30 00 1.9.1

Spec 01 30 00, para 1.9.1 calls for facilitated formal facilitating partnering, requiring offeror's to carry costs for third-party independent Facilitator Consultant, meeting room and other incidental items. Requring a third-party facilitator will drive up project costs. Can NAVFAC waive this requirement?

Yes, This requirement can be waived.

Pre-Proposal Inquiry Submission Form Solicitation #: N4008525R2520

Project Title: NSN, Pier 11 Partial Demolition

3 10/23/24 179 01 57 19 1.5.1.1.2

Spec 01 57 19, 1.5.1.1.2 calls for hazardous material survey/inspection prior to commencement of work.

However, para 3.6 states that no hazmat anticipated for this work. Please clarify if the Contractor needs to provide the hazmat survey and/or inspection as part of its bid.

No hazmat survey as part of bid is required.

4 10/23/24 184 01 57 19 1.6.6 Please confirm that a marine mammal observer is required for this project per 01 57 19, paragraph 1.6.6.

Protected Species Observer (PSO) is required as stated per 0 57 19 1.6.6.

5 10/23/24 110 01 45 00 1.6.5

Spec 01 45 00, 1.6.5 calls for a Registered Structural Engineer to review contractor’s submittals prior to sending it to Navy. It’s not a design-built project and typical approval of all submittals is done first by the contractor's QC Manager followed by the Government.

Having the Registered PE or the Architect for this work will result in unnecessary costs that can be avoided. Will NAVFAC waive this structural engineer requirement?

Yes, this requirement will be waived.

6 10/23/24

The RFP provides a hard completion date of June 15, 2025. However, assuming the soliciation closes on 11/20/24, the government has until March 20, 2025 to award the project (120 days). This would leave less than 90 days to complete and closeout the project. What is the project's Period of Performance?

Project must be completed by 6/15/25 with an estimated award of early December.

7 10/23/24

The RFP provides a hard completion date of June 15, 2025. However, assuming the soliciation closes on 11/20/24, the government has until March 20, 2025 to award the project (120 days). This would leave less than 90 days to complete and closeout the project. By what date does the government anticipate issuing an award?

Project is estimated to be awarded early December.

8 10/23/24 Please provide information regarding the extent of any underwater inspections that are required for the project.

No underwater inspections are required.

9 10/23/24 General

Requirem ents

Time for Completio n

It is stated, "Hard contract completion date is June 15, 2025." With a proposal acceptance period of 120 days from receipt of offers, this would leave contractor with 87 days to complete the work. Can the Government confirm if this project is expected to be awarded within the first 30 days from the proposal to allow for adequate time for the subcontractor to perform the work?

See # 6.

10R 10/23/24 G-02 General Notes #22

It is a concern that pile extraction may not be possible. Is cutting the piles at the mudline or a government provided minimal depth below the mudline acceptable?

See Design Revision 02

11 10/23/24 01 50 00 3.6.1 Provide and maintain admin field office facilities within construction area at designated site. Does the Government have a designated site selected?

Please see map of suggested location and adhere to sheet G-02 loading requirements.

12 10/23/24 01 57 19 1.5.1.1.2

Structures must be surveyed for the presence of asebestos prior to demo. Section 01 57 19 3.6 states it does not expect hazard material on this project. Has the government performed a survey for this project which would eliminate the requirement in section 01 57 19 1.5.1.1.2?

See #3

13R 10/23/24 35 59 13.14

3.1.4

Section calls out to provide jetting equipment and then section 3.4.2.1 states jetting of piles is not permitted without approval of the contracting officer. Will jetting of piles be approved?

See Design Revision 02

14 10/28/24

During the site visit it was noted that there was a life ring on the west side of the area that is being demolished.

Should this be removed and turned over to the Government?

Yes. Remove it and turn over to the government.

15 10/28/24 SD-05

Can the Government please provide electrical drawings for the electrical circuit located in the demo area?

See Record Drawing Letter dated 24/Dec/08; Electrical demoliton sheets ED- 001 to ED-104; Electrical sheets E-001 to E- 605.

16 10/28/24 SD-05

Can the Government please confirm the location in which the electrical circuit will be locked and tagged out?

Refer to electrical record drawings dated 24/Dec./08

17 10/28/24 SD-05

There is a junction box located directly across from the called out junction box on SD-05 closest to the ramp.

This junction box is not called out (would be located closest to cylinder pile location A5). Can the Government confirm is this junction box shall alost follow the not called out for the other junction boxes on SD-05?

Refer to electrical record drawings dated 24/Dec./08

18 10/28/24

Will the subcontractor be able to drive construction vehicles on the pier to the demo location? If yes, are there any limitations?

Approval from contracting officer required for construction vehicles to follow designated area on the pier. No Structural limitations, but do not damage existing deck.

19 10/30/24

Following response to Question #03 posted with Amendment 001, will Navy waive a requirement for Environmental Management Plan as noted in Section 01 57 19, para 1.7?

No. Environmental Protection Plan (EPP) is required per section 01 57 19 1.7

20 10/30/24 Please provide electrical as-built drawings. See # 15 response

21 10/30/24 Will water jetting to break the piles to be extracted free be permitted on this project?

See # 13 response

22 10/30/24 What is the access situation for the work area?

e.g. Is there access down the pier? If so is it open access, semi restricted or restricted?

Restricted access down the pier and all personnel must be vetted and badged.

23 10/30/24

What is the access situation for the work area?

e.g. Is there a landing point on the navy yard that can be utilized to load materials and equipment on and off of barges?

Material can be loaded and off loaded directly from the barge to the pier as long as sheet G-02 loading requirements are followed.

24 10/30/24 Is there an area on post for a laydown yard that is going to be made available during this project?

Yes, directly on the Pier approx 8K square feet. See # 11 response

25 10/30/24 What type of water traffic around the pier can we expect?

Will there be water traffic that will restrict our operations and movement while we are working (work boats, tugs?

See Port Security Barrier (PSB) & Turbidity curtain plans -Drawing No. G-03 sheet ; section 01 11 00 1.5

26 10/31/24 Can the existing concrete piles be cutoff at the mudline? see #10 reponse

27 10/31/24 Is jetting allowed when extracting the existing concrete piles?

see #13 response

28 10/31/24 Is jetting allowed when driving the composite piles to reinstall the fenders?

see #13 response

29 10/31/24 What are the extents of the existing log camel?

85.6 ft long for existing log camel - see section A/S-08 sheet and S-671 (Record drawing dated 24/Dec/08)

30 10/31/24 What elevation is the existing log camel located at? Refer to S-08 sheet

31 10/31/24 Where should the salvaged materials be stored after removal but before re-installation?

See # 11 response (Provide Salvage Plan per 01 11 00 1.7 )

32 10/31/24 Where should the salvaged materials that do NOT get reinstalled be placed? Will NAVFAC handle moving them directly from the contractor’s barge?

Any salvage material that remains upon completion of the project will be the contractor's material to be removed from Government property.

33 10/31/24 How much does 1 composite fender pile weigh? Refer to S-08 sheet

34 10/31/24 How wide is the access ramp on Pier 11? Are we allowed to bring equipment down the pier using the access ramp?

Refere to SD-01 sheet ( S-106 record drawing dated 24/dec/08) ; Permitted to bring down equipment using the access ramp after approval from contracting officer.

35 10/31/24 Will NAVFAC supply the hardware that gets embedded in concrete to re-mount the salvaged bolster fender and pier fenders?

No, Navfac will not suppy any hardware to re-mount the salvaged bolster fender and pier fenders.

36 10/31/24 Can the contractor work 6x10 or even 7x10 (6 or 7 days per week with more than 8 hours per day) to meet the RFP deadline of June 15?

Yes, but permission from contracting officer required for work outside regular hours ( see specs section 01 14 00 1.3.2 and 01 14 00 1.3.3)

37 11/06/24 S-02 & S-

Sheet S-02 notes, "Reinstall salvaged fender and log camel in kind, see sheets S-08 & S-09 for details". The log camel plan detail on S-08 states, "(TWO REQ'D AS SHOWN)." Only 1 EA fender pile assembly is depicted on S-02, please verify that only 1 EA assembly is to support the 1 EA log camel.

Yes, 1 EA assesmbly with two composite plastic fender pile as shown in S-02 is required.

38 11/06/24 S-02 & S-

Please provide the elevation of the log camel for removal and reinstallation.

see response # 30

39 11/06/24 S-02 & S-

Please provide the length that the log camel is to be cut to for reinstallation, and clarify if the excess is to be salvaged or disposed of.

full length along grid A to C ( approx +/- 49 ft.)

40 11/06/24 2 & 3 00 01 15 1.3.1 Please provide reference drawings listed in this spec section.

See Record drawing letter dated 24/Dec/08

41 11/06/24 G-02 & S-

Some reinforcing steel details specify a galvanized finish, but the general notes do not specify a finish. Please clarify whether a galvanized finish is a requirement for all reinforcing steel.

Follow S-03 sheet; galv. for parapet reinforcement only.

42 11/06/24 297 35 59 13.14

20 2.3

Spec section calls out a "sacrificial 2 ft at pile head" for the composite fender piles. Please confirm it is permissable to cut off the top 2 ft of these piles once reinstalled, resulting in the pile tip elevation to be 2 ft less than originally installed.

Not permissible and not applicable for reinistalled pile.

43 11/05/24 p-15 01 57 19 1.6.6

Specification 01 57 19 is not adequate for pricing of the Marine Mammal Observation (MMO) activities required for the project.

Typically a Spec. 01 35 40.00 25 is provided for these activities. Without further clarification KTR will provide 1 MMO/PSO personnel (stationed at the end of Pier 11 on a 20 ft tower) for the duration of the project when Construction activities that require monitoring of impact zones are occuring. Please confirm that this MMO plan is acceptable.

1-PSO & a second PSO for breaks recommended.

44 11/05/24 Project Documen ts

01 57 19

- Based on the project’s geographical extent and construction footprint shown in the attached drawings, how many PSOs are recommended to ensure comprehensive monitoring of all impact areas?

1-PSO & a second PSO for breaks recommended.

45 11/05/24 Project Documen ts

01 57 19

- Are there specific observation points or zones that require simultaneous monitoring?

No additional zones reqd. for simultaneous monitoring

46 11/05/24 Project Documen ts

01 57 19

- Given the nature of construction activities (e.g., pile driving, demolition, heavy equipment operations), what is the expected impact radius for noise or disturbance that PSOs will need to monitor?

Training will be provided to the PSOs by the Natural Resource Manager prior to the start of work. Location of PSO & maps of area to be monitored will be provided.

47 11/05/24 Project Documen ts

01 57 19

- Do certain high-impact activities necessitate additional PSOs due to increased risk to protected species?

No additional PSOs required.

48 11/05/24 Project Documen ts

01 57 19

Can you provide recommendations on how to strategically position PSOs to ensure maximum visibility and coverage across the site, especially considering potential obstructions or limited-visibility areas?

Training will be provided to the PSOs by the Natural Resource Manager prior to the start of work. Location of PSO & maps of area to be monitored will be provided.

49 11/05/24 Project Documen ts

01 57 19

- Are there any specific vantage points identified from which PSOs can effectively monitor the protected species without interference from construction activities?

Best Vantage point will be on Pier-11 in a lift. Pier-10 & Pier-12 may also be used with a lift.

50R 11/05/24 Project Documen ts

01 57 19 Are there any site-specific environmental regulations or monitoring requirements that influence the number of PSOs needed?

See Design Revision 02

51 11/05/24 Project Documen ts

01 57 19

- What data or historical information about the frequency and behavior of protected species in the area should be considered in determining the appropriate number of observers?

See response # 43

52 11/05/24 P-2 00 01 15 1.3.1 P-1.3.1 Reference drawings listed have not been provided. Please provide or removed from contract.

See response #40

53 11/05/24 P-8 01 45 35 1.6.5

Please confirm that all division 2, 3, 35 submittals must be reviewed by a licenensed professional engineer prior to submission for government approval. Will these submittal require a PE Stamp or a signiture aknowledging review? Please confirm this is a contract requirememt.

See response #5

54 11/05/24 P-10 01 35 26 1.7.1.1.1

This Paragraph conflicts with Spec. 01 45 00 - P1.6.1.1. which states that the QCM can also perform the duties of the SSHO and Superintendent. What is the contract requirement? Can one KTR Personnel perform the three roles or are two KTR personnel required to preform the roles of Superintendent, QCM and SSHO?

Two people are required; See Design Revision 01.

55 11/05/24 N/A 1 31 16.00 2 N/A

Given this Task Orders's hard finish date. How will NAVFAC adjudicate legitimate delay claims? No weather calendar has been provided. In the field this project will be 100% impacted by inclement weather. Will the KTR be expected to make up lost days on the weekends or gov. holidays? Will NAVFAC support the project for work on weekends or gov. holidays?

See response # 36

56 11/05/24 Attach. HBid Schedule N/A

CLIN 0001AB provides for the cost of 120 Hrs (3 Weeks) of Project shutdown time directed by the government. Will the time expended against this CLIN extend the CCD day for day?

Is the KTR expected to include costs to make up for time lost against this CLIN 0001AB with no adjustment to the CCD.

Time expended against this CLIN will not extend CCD Day for Day and KTR is responsible to make up for the time lost with no adjustment to the CCD.

57 11/05/24 Attach. HBid Schedule N/A Is CLIN 0001AB also intended to be used for work stoppages due to the Marine Mammal Observation Program?

NO

58 11/05/24 S-02 & S-

Sheet S-02 notes, "Reinstall salvaged fender and log camel in kind, see sheets S-08 & S-09 for details". The log camel plan detail on S-08 states, "(TWO REQ'D AS SHOWN)." Only 1 EA fender pile assembly is depicted on S-02, please verify that only 1 EA assembly is to support the 1 EA log camel.

See response #37

59 11/05/24 S-02 & S-

Please provide the elevation of the log camel for removal and reinstallation.

See response # 30

60 11/05/24 S-02 & S-

Please provide the length that the log camel is to be cut to for reinstallation, and clarify if the excess is to be salvaged or disposed of.

See responses # 29 and # 39

61 11/05/24 G-02 & S-

Some reinforcing steel details specify a galvanized finish, but the general notes do not specify a finish. Please clarify whether a galvanized finish is a requirement for all reinforcing steel.

See response # 41

62 11/05/24 297 35 59

13.14 20

2.3

Spec section calls out a "sacrificial 2 ft at pile head" for the composite fender piles. Please confirm it is permissable to cut off the top 2 ft of these piles once reinstalled, resulting in the pile tip elevation to be 2 ft less than originally installed.

See response # 42

63 11/05/24 G-02 General

Notes #22

Note states, "Retain a geotechnical engineer licensed in the Commonwealth of Virginia to design a pile extraction plan." As a marine contractor of 75 years, it is our opinion that these piles will not be able to be extracted based on the size and length of the piles. We recommend cutting the piles at the mudline or some minimal distance below the mudline, approximately 5’. If full extraction is still required, we will not be able to bid the project.

Refer response # 10

64 11.6.24 221 02 41 00 1.2.3 Can rubbish and debris be stored on material barges with out being removed daily?

Follow per specs. 02 41 00 1.2.3

65 11.6.24 296-297

35 59 13.14 203.1 and 3.4 Section 3.1 mentions Jetting equipment, Section 3.4 call out jetting, spudding, and predrilling of piles are not permitted. How will piles be extracted and reinstalled?

See response # 13

66 11.6.24 S-08

Are the composite fender piles to be extracted filled with anything? What depth of pile can be expected to be in the ground?

See S-08 sheet (Record drawing S-671 dated 24/Dec/08)

67 11/06/24 9 of 305 01 14 00 1.2

It will be necessary to close off the end of the pier for the safety of non-essential personnel and the project. How much of the end of the pier can be closed off with fencing?

See responses # 11, 22, 23

(End of Summary of Changes)

68 11/06/24 11 of 305 01 14 00 1.3.2 Can there be an option to extend normal working hours to 10 hours per day if the contractor deems additional hours be necessary to meet project timelines.

See Response # 36

69 11/06/24

01 35 26 3.7.2 q.

FAA crane permit has an approval time of up to 45 days.

Does NAVFAC have an avenue to request an expedited review and approval?

Yes, will have expedited review for waterfront.

70 11/06/24 Will the Navy allow the Contractor to use any part of Pier 11 as a laydown area?

See response # 11

71 11/06/24 256 03 31 30 2.7.2

Drawing G-02, General Notes under the Reinforcing Section only states, "Reinforcing steel must conform to ASTM-A615 Specification for deformed and plain billet steel bars…". Specification Section 03 31 30 "Marine Concrete", Paragragh 2.7.2 Reinforcing Bars calls for various steel materials, ie galvanized, stainless, epoxy coated. Please clarify which material NAVFAC will accept for use on the project.

See responose # 41

72 11/06/24

01 35 26 01 45 00

1.7.1.1 1.6.1.1

Please clarify the following statements in the Specifications. "The SSHO may not serve as the Quality Control Manager. The SSHO may not serve as the Superintendent." "Provide a QC Manager at the work site to implement and manage the QC program, and to serve as the Site Safety and Health Officer (SSHO) as detailed in Section 01 35 26 GOVERNMENTAL SAFETY

REQUIREMENTS."

See response # 54

73 11/06/24

In the General Requirements document it states, "Time for Completion: Hard contract completion date is June 15, 2025. This date includes the initial 15 days allowed for distribution of the task order award, submission and approval of insurance, bonding and other requirements set forth in the task order/MACC.

Task order award is considered notice to proceed." It also states, "Proposal Acceptance Period: 120 days from receipt of offers."

If both of these statements hold true then the Contractor may not have enough time to complete the demolition and reconstruction, considering material submittals & procurement lead times. Please clarify.

See response # 6

74 11/06/24 Will NAVFAC consider allowing the Contractor to cut the existing concrete piles below the mudline versus complete extraction of the piles?

See response # 10

75 11/06/24 Drawing

S-08

Drawing S-08, "Fender Assembly" shows the installation of a composite plastic camel log. It is unclear whether or not the camel materials are new or salvaged materials.

Please advise.

See S-02 sheet (Reinstall salvaged fender and log camel in kind)

76 11/06/24 Drawing

S-08

Please provide additional details for which composite fender piles will receive the composite plastic camel log as shown on Drawing S-08, "Fender Assembly". Will the camel also be installed on the corner piles?

See response # 39

77 11.6.24 01 57 19 1.6.6 Please confirm Protected Species Observer must meet NMFS qualifications per spec section 01 57 19 1.6.6.

Yes, follow per spec 01 57 19 1.6.6

78 11.7.24 the marine mammal watch plan/requirements are not provided in the specifications, only the qualifications for the PSO. Please provide these specifications, detailing monitoring requirements, quantity of personnel, reporting responsibilities, etc.”

See Design Revision 02

79 11/09/24 Amend 2 PPI #10

The answer to PPI #10 ambiguous and open-ended as a "goal" and a requirement have completely different meanings. Please restate the answer to PPI #10 indicating that the extraction of the 170 ft. 24"x24" piles is a contract requirement for which all costs shall be included by all offerors.

See Design Revision 02