PPI LOG 01 FOR 25R0133.pdf

PDF 418 KB Posted

Attached to
EV32 CRANE SWMU 36 AND 37 SUBAREA PROJECT
Solicitation number
N4008525R0133
Issued by

About this file

This document is a Questions and Answers (Q&A) form for a federal contract opportunity. The government extended two key dates in response to bidder questions: the question submittal due date was moved to 8 September at 3:00 p.m. EDT, and the proposal due date was extended to 12 September at 2:00 p.m. EDT via the Procurement Integrated Enterprise Environment (PIEE). The government explicitly stated that no additional extensions would be granted to accommodate end-of-year award deadlines, and proposals will not be accepted through email. The Q&A form provides a standard template with columns for PPI Number, Date Submitted, Page, Section, Paragraph, Question, Government Response, and Government Responder Name/Email, though only two questions are currently populated on the first page of the document.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page Section Para.

Can the Government extend the question submittal due date to occur after the 4 Sep site visit (to 8 Sep) in order to allow bidders to seek clarifications based on site conditions observed during the site visit?

The question submittal due date will be extended to 8 Sept.

at 3:00 p.m. EDT

Given the short time between the site visit and the current proposal due date (6 calendar days), kindly request for the Government to extend the proposal due date by one week to allow bidders to adjust the LOE and/or ascertain additional costs based on site conditions observed during the site visit?

The proposal due date will be extended to 12 Sept. at 2:00 p.m. EDT via PIEE. Proposals will NOT be accepted through email. The Government cannot provide any additional extensions in order to accommodate an end of the year deadline for award.

GOVERNMENT RESPONSEQUESTION GOV'T RESPONDER

NAME, E-MAIL

REFERENCE

Date

SubmittedPPI No.

Amend No.

File details come from the government source that posted it. Updated .