Amend 0006.pdf

PDF 434 KB Posted

Attached to
IR DEMO PROJECTS FY24 Marine Corps Base Camp Lejeune
Solicitation number
N4008525B2500
Issued by

About this file

This is Amendment 0006 to Solicitation N40085-25-B-2500 for the demolition of 53 facility buildings at Marine Corps Base Camp Lejeune, issued by NAVFAC Mid-Atlantic. The amendment removes three buildings (SSB159, SHP455A, and SRR3B) from the bid sheet and provides answers to contractor questions about site visits, asbestos/lead paint disposal, and other project details.

Key details include: bids are due by 10:00 AM EST on March 19, 2025; a bid conference will be held March 19, 2025 at 10:00 AM at Public Works Department; this is a 100% small business set-aside under NAICS 238910 with a $19M size standard; period of performance is 365 days after award; contractors can dispose of hazardous materials at the Camp Lejeune landfill; a bid guarantee is required; and award will be made on lowest price based on the total sum of ELINs 0001-0053. The contractor must provide all labor, supervision, management, tools, materials, equipment, facilities, and incidental engineering necessary for the demolition work. Electronic or facsimile bids will not be accepted, and questions were due by March 6, 2025.

View the file

Other files

File Type Posted
Amend 0007.pdf PDF
MCIEAST-MCB 11350.1B Amend 0006.pdf PDF
Amend 0005.pdf PDF
Building locations.pdf PDF
Amend 0004.pdf PDF
Amend 0003.pdf PDF
Amend 0002.pdf PDF
Amend 0001.pdf PDF
252500SOW and Specification.pdf PDF
252500Asbestos Survey.pdf PDF
252500Lead SurveyReport.pdf PDF
252500Drawings.pdf PDF
SOLN4008525B2500.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACQR6087820

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Solicitation #N40085-25-B-2500 IR DEMO Project FY24 This amendment should be acknow ledge w hen your proposal is submitted. Failure to acknow ledge may consitute grounds for rejection of proposal.

Reason for Amendment 0006: For RFI Answ ers and Corrections.

SSB159, SHP455A and SRR3B has been removed from bid sheet.

1. CONTRACT ID CODE PAGE OF PAGES

1 15

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 04-Mar-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008525B2500

X 9B. DATED (SEE ITEM 11)

14-Feb-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

04-Mar-2025

CODE

NAVFACSYSCOM MID-ATLANTIC

ROICC CAMP LEJEUNE

1107A BIRCH STREET

CAMP LEJEUNE NC 28547-2521

N40085 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4008525B2500

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been added by full text:

AMENDMENT 0006

BID Conference will be location at

Public Works Department 1005 Michael Road Camp Lejeune, NC 28547 Date: March 19,2025 Time: 10:00 AM

1. Question Are you handling the bidding on this project? If so, I am looking to obtain a plan holders list / Pre-bid meeting list if possible. If not, could you point me in the right direction?

Answer No, that information will not be available

2. Question Do you have the site visit sign in sheet for these projects?

Answer:

The sign in sheet will be on site

3. Question Are demolition company's required to have a General Contractors license?

Answer Bonding as required in your division (1) specifications

4. Question Can we setup a site visit for next week? We don’t currently have access to Camp Lejeune.

Answer No other site visit will be schedule or reschedule. At site visit was conducted 26 February 2025 contractor can visit the sites at their own time.

5. Question Amendment 0004 questions 2 and 3 answers say the Government does not anticipate asbestos removal. The reports indicate asbestos in some of the structures, is the asbestos being removed by others prior to this demo project?

Answer

2. Question: Please clarify if a phased proposed project schedule is required with the proposal response.

Answer:

This project does not require construction phasing.

3. Question:

Does the site have a preferred order in which the structures are to be removed?

Answer:

No

6. Question Can lead based paint on building materials be brought to the Camp Lejeune Landfill?

Answer Yes, see attached base order

7. Question Can asbestos containing materials be brought to the Camp Lejeune Landfill?

Answer Yes, see attached base order

8. Question If the Camp Lejeune Landfill can be used for hazardous materials, what are the restrictions?

Answer See attached base order

9. Question Are there plan pages for structure SRR3B?

Answer This structure is not in the project (See attached Amendment 0006) has been removed

10. Question Are there plan pages for structure SHP455A? This structure is not in the project Answer This structure is not in the project (See attached Amendment 0006) has been removed

11. Question Are there plan pages for structure SBB159? This structure is not in the project Answer This structure is not in the project (See attached Amendment 0006) has been removed

12. Question 36 out of 53 structures have a lead -based paint report, can the government provide the missing 17 structures?

Answer Everything the government has access to has been provided. Some structures may be wood frame structures with no paint on them, so there wouldn’t be a report on those.

13. Question 34 out of 53 structures have an asbestos report, can the government provide the missing 19 structures? Everything the government has access to has been provided.

Answer Some structures may be wood frame structures with no asbestos to report on.

Revised Questions Answers from Amendment 0004

15. Question:

Will the contractor need to establish a Deaco area for labor / equipment?

If friable asbestos is encountered, there will need to be a decon area.

16. Question:

Will all labor need to have HAZWOPER training prior to starting work?

Answer:

No.

20. Question:

What are the recycling requirements for this project?

Refer to specifications in Division 01 for recycling requirements

21. Question:

Is the contractor responsible for removing universal waste from the structures (ballast, lights, etc...), if so, will the site provide containers?

Answer:

Yes, they are required to remove anything that is left on site. Containers will not be provided by the government.

22. Question:

Is air sampling required during the lifecycle of the project?

Answer:

Yes

23. Question:

Will blood testing be required before and after the remediation of lead materials?

No.

The following have been modified:

AMENDMENT 0001

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge may constitute grounds for rejection of your proposal.

Question 1:

RFI due dates are listed on page 3 and page 47 of the Solicitation. Never wanting to assume anything. Please clarify that the RFIs are due no later than 2/27 as listed on page 3 and not 4/10 as listed on page 47 of the solicitation.

Thanks.

Answer 1:

Corrected date on page 47.

REQUEST FOR INFORMATION

All questions regarding this solicitation shall be addressed to the contract specialist via email at sharon.e.humphrey.civ@us.navy.mil and Contracting Officer regenia.d.guest.civ@us.navy.mil no later than February 27, 2025. Inquiries submitted after this deadline will not be answered. Pre-bid inquiries shall include an email subject line formatted as follows:

Question 2:

Since the solicitation was just posted on Sam.Gov on 2/18/25, we feel the bid date of 3/19/25 is aggressive and does not allow adequate time to properly evaluate 53 different sites, generate questions for each site, gather pricing, and submit a proposal. Can the bid date be extended?

Answer 2:

Bid cannot be extended due to the timeframe needed and best interest to the government. It was posted on 2/14/2025 under the pre-solicitation and was correct on 2/18/2025. The solicitation will be out for over 30 days.

Question 3 Solicitation says no formal site visit is scheduled. Military & Federal Construction respectfully requests a formal site visit be scheduled so we can access both the interior and exterior of each of the locations to properly evaluate the scope of work.

Answer 3:

A site visit is scheduled for February 26th at 10 AM meeting location will be at Building 1107 Birch Street, Camp Lejeune NC.

Those who do not have prior access to the base the following information is required:

Each individual is required to have their driver license, proof of insurance, Vehicle Registration, and if driving a rental vehicle (have rental agreement).

In your email your name must be exactly as it appears on the driver’s license.

If you need access to the base, please email me no later than 25 February 2025 by 2:00 pm. Email address sharon.e.humphrey.civ@us.navy.mil

Question 4 Can the government provide a map of the building locations?

Answer 4:

All sites’ locations and maps are available in SAM.gov.

Question 5 I was curious if you are going to have a site visit for the demolition project out to bid? We are interested in the job and would like to come see it if possible.

Answer 5:

Refer to answer question three (3).

Queston 6 I would like to schedule a site visit for Solicitation #N4008525B2500, Demolishing 53 Facility Buildings. I would like to schedule it no later than February 26th, so that I have time to get questions in before the deadline of 2/27. I do not currently have access to Camp Lejeune. What information do you need from me in order to arrange this site visit?

Answer 6

Question 7 The RFP states offerors should follow guidance under FAR Clause 52.236-27 Site Visit (Construction) Alternate I.

Please provide directive for offerors to formally request a site visit.

Answer 7 Refer to question and answer three (3).

Question 8 Please clarify if there are clearance requirements for staff onsite for the site visit and during normal operation.

Answer 8

Question 9 Would the Government consider granting an extension to Q&A from 02/27/2025 to 03/06/2025? If so, would the Government consider an extension of the proposal deadline from 03/19/2025 to 04/03/2025 to permit ample time to schedule, attend, submit post-site visit questions, receive responses from the Government, disseminate answers and incorporate into the proposal?

Answer 9 Q&A will be extended to 03/06/2025 to give ample time for questions after site visit 2/26/2025. Due to the governments need the proposal deadline cannot be extended.

Question 10

Please clarify if there will be concurrent on-site work that would challenge the offeror's ability to execute the contract.

Answer 10 This is a demo project, there should not be any concurrent on-site work.

Question 11 Please provide information regarding how offerors will receive answers to questions and if we will have the opportunity to review the Q&A submitted by other potential offerors.

Answer 11 All questions and answers will be posted via amendments, which are required to acknowledged with proposals.

Question 12 Please provide the method of evaluation and the Government's evaluation criteria for this opportunity.

Answer 12 Lowest Price

Question 13 The SF 33 indicates the proposal needs to be submitted as a hardcopy including an original and 1 copy for a total of two copies. Would the Government consider revising the requirement to permit electronic submittals?

Answer 13 No electric submission, this is an IFB.

Question 14 We would like to schedule a site visit for a party of five on Friday the 27th of February at 0900 if possible.

Answer 14

OFFERORS INFORMATION

RESIDENT OFFICER IN CHARGE OF CONSTRUCTION (ROICC)

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND (NAVFAC)

1107A BIRCH STREET

CAMP LELEUNE, NC 28547

NAVFAC Solicitation Number N40085-25-B-2500

DEMOLISHING FIFTY-THREE (53) FACILITY BUILDINGS

NOTICE: BIDS ARE DUE BY: 10:00 AM (EST) ON Date: 03-19-2025

Bids are to be addressed to the Contract Specialist listed below and place in the bid mailbox at 1107A Birch Street:

ROICC, NAVFAC MID ATLANTIC

SOLICITATION # N40085-25-B-2500

ATTN: SHARON E. HUMPHREY

1107A BIRCH STREET

CAMP LEJEUNE, NC 28547-2521

All inquiries concerning any phase of the specification shall be made, in writing to Sharon E. Humphrey by email at sharon.e.humphrey.civ@us.navy.mil and Regenia D. Guest via email at Regenia.d.guest.civ@us.navy.mil. Bids must be received by the established due date and time to be considered for award. No email and no facsimile bids will be accepted.

A.1 Contract Title: Demolition for 53 Buildings at Marine Corps Base, Camp Lejeune (MCBCL), North Carolina.

A.2 Contract Type: Firm-Fixed Price (FFP) solicitation.

A.3 Delivery: The Contractor shall provide all labor, supervision, management, tools, materials, equipment, facilities, incidental engineering, and other items necessary to provide demolition of 53 buildings at MCBCL, North Carolina and MCBCL areas of responsibility. The Contractor shall be capable of providing transportation to and from each location and shall dispose of hazardous materials at the MCBCL landfill.

A.4 Set-Aside Information: This acquisition is a total 100% small business set-aside, and the offeror must be a Small Business in SAM.gov at the time of the bidding under the required NAICS listed in A.5 below.

A.5 The NAICS Code assigned to this procurement is 238910, Site Preparation Contracts, with a small business size standard of $19 Million. Offerors shall ensure current registration in the System for Award Management at https://sam.gov, including Annual Representations and Certifications are complete and updated for this procurement.

If a Representation and Certification required by Section K of the RFP is not provided in SAM, include the Representation and Certification in your price bid.

A.6 Bid Guarantee: A bid guarantee is required. See, FAR Clause 52.228-1 Bid Guarantee.

A.7 Wage Determination: The Service Contract Act by Direction of the Secretary of Labor are included in this solicitation. Refer to Section G Contract Administration.

A.8 Contract Term/Period of Performance: This procurement contains provisions for 365 days after award date.

A.9 Offerors shall provide their Unique Entity Number (UEI), CAGE code, and Federal Tax ID number with bid.

A.10 Offerors are advised that Funding may not become Available: If funds are not available, no award will be made as a result of this solicitation. Offerors will not be reimbursed for any effort or bid costs resulting from this solicitation. See FAR Clause 52.232-18 Availability of Funds. All bid prices must remain vital as proposed for at least 120 days after bidding due date.

A.11 Site Visit: See FAR Clause 52.236-27 Site Visit (Construction) Alternate I.

A.12 For Additional Information: Submit all questions in writing no later than February-27-2025 by 12:00 noon. The Government does not intend to respond to inquiries/questions submitted after this date. When submitting questions, please include the solicitation number: N40085-25-B-2500, to Sharon E. Humphrey by email at sharon.e.humphrey.civ@us.navy.mil and Regenia D. Guest by email only at Regenia.d.guest.civ@us.navy.mil.

SECTION B - SUPPLIES OR SERVICES AND PRICES

NOTES

A. Under the line items furnished, the offers shall state prices for each Exhibit Line-Item Number (ELIN) given hereinafter:

ELIN 0001

Price includes completing all work associated with building 114 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0002

Price includes completing all work associated with building 528 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0003

Price includes completing all work associated with building 1014 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0004

Price includes completing all work associated with building 1742A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0005

Price includes completing all work associated with building 1742B in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0006

Price includes completing all work associated with building 1742C in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0007

Price includes completing all work associated with building SBB159 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0008

Price includes completing all work associated with building ST13 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0009

Price includes completing all work associated with building VL60 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0010

Price includes completing all work associated with building VL61 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0011

Price includes completing all work associated with building VL325 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0012

Price includes completing all work associated with building 1306 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0013

Price includes completing all work associated with building RR27 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0014

Price includes completing all work associated with building RR28 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0015

Price includes completing all work associated with building RR108 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0016

Price includes completing all work associated with building S185 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0017

Price includes completing all work associated with building SAS4215 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0018

Price includes completing all work associated with building AS3990 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0019

Price includes completing all work associated with building AST27B in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0020

Price includes completing all work associated with building SRR65 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0021

Price includes completing all work associated with building SRR66 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0022

Price includes completing all work associated with building TC1003 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0023

Price includes completing all work associated with building SFC408 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0024

Price includes completing all work associated with building SFC499 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0025

Price includes completing all work associated with building SFC581 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0026

Price includes completing all work associated with building 203 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0027

Price includes completing all work associated with building 203A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0028

Price includes completing all work associated with building 401 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0029

Price includes completing all work associated with building 401A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0030

Price includes completing all work associated with building 728 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0031

Price includes completing all work associated with building 1005A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0032

Price includes completing all work associated with building H206 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0033

Price includes completing all work associated with building H207 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0034

Price includes completing all work associated with building H208 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0035

Price includes completing all work associated with building H209 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0036

Price includes completing all work associated with building LCH4034 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0037

Price includes completing all work associated with building SHP306A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0038

Price includes completing all work associated with building SHP308A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0039

Price includes completing all work associated with building SSR93 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0040

Price includes completing all work associated with building SRR105 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0041

Price includes completing all work associated with building AS849 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0042

Price includes completing all work associated with building AS903A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0043

Price includes completing all work associated with building AS903B in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0044

Price includes completing all work associated with building AS3906 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0045

Price includes completing all work associated with building AS3450 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0046

Price includes completing all work associated with building AS3540 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0047

Price includes completing all work associated with building AS852 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0048

Price includes completing all work associated with building AS251 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0049

Price includes completing all work associated with building AST27 in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0050

Price includes completing all work associated with building AST27A in accordance with the provided drawings and specifications. The price for this line item should include all applicable costs, overhead and profit for this work.

B. Offers must be submitted on all line items. Failure to provide pricing on all line items may result in the offer being rejected as non-responsive.

C. ELIN’s shall include all markups (overhead, labor burden, and profit) for final pricing.

D. Award will be made on the total sum of ELINS 0001 through 0053, which must be the same total amount stated in Section B Supplies or Services and Prices/cost. In the event there is a discrepancy between the Section B ELINS pricing and Section B CLIN price, the Section B ELINS will be held to be the intended offer, and the Section B CLIN will be adjusted accordingly.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

SECTION: C - DESCRIPTION/SPECS

Refer to specifications and drawing attachements provided.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .