This is Amendment 0003 to solicitation N4008525B2500 for an IR DEMO Project at Camp Lejeune, issued by NAVFACSYSCOM Mid-Atlantic on February 25, 2025. The amendment includes maps and responses to 26 contractor questions about the demolition project which involves 53 structures.
Key clarifications provided include: no UXO is expected during foundation excavation; construction phasing is not required; contractors must provide their own equipment and job trailers; the contractor is responsible for verifying cold/dark status of structures and disposing of any remaining items inside; NCDEQ stormwater permitting is not applicable; no air sampling or blood testing is required; and contractors must have OSHA hazard waste certification. The government intends to fully fund the total project rather than partial funding for select structures. Several responses refer contractors to sheet G-002 for specific requirements regarding demolition, environmental notes, and recycling requirements. Some questions about hazardous waste permits are still pending input from the Designer of Record.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend 0007.pdf | ||
| Amend 0006.pdf | ||
| MCIEAST-MCB 11350.1B Amend 0006.pdf | ||
| Amend 0005.pdf | ||
| Building locations.pdf | ||
| Amend 0004.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001.pdf | ||
| 252500SOW and Specification.pdf | ||
| 252500Asbestos Survey.pdf | ||
| 252500Lead SurveyReport.pdf | ||
| 252500Drawings.pdf | ||
| SOLN4008525B2500.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR6087820
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation # N-40085-25-B-2500 IR DEMO Project FY24 This amendment should be acknow ledge w hen your proposal is submitted. Failure to acknow ledge may consitute grounds for rejection of proposal.
Reason for Amendment 0003: Maps Attached and for RFI Responses
1. CONTRACT ID CODE PAGE OF PAGES
1 6
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-Feb-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008525B2500
X 9B. DATED (SEE ITEM 11)
14-Feb-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-Feb-2025
CODE
NAVFACSYSCOM MID-ATLANTIC
ROICC CAMP LEJEUNE
1107A BIRCH STREET
CAMP LEJEUNE NC 28547-2521
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008525B2500
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been added by full text:
AMENDMENT 0003
Question 1:
Does the govt expect to encounter UXO's during any excavation of foundations?
Answer1:
No. Refer to sheet G-002, “Special Environmental Notes”, note #5.
Question 2 Question: Please clarify if a phased proposed project schedule is required with the proposal response.
Answer 2 This project does not require construction phasing.
Question 3 Does the site have a preferred order in which the structures are to be removed?
Answer 3 No. Refer to sheet G-002, “General Demolition Notes”, note #4.
Question 4 Will the contractor be provided an existing structure to operate from, they can set up workstations?
Answer 4 The contractor is responsible for providing their own equipment and job trailers.
Question 5:
Will the contractor need to provide a trailer for the govt?
Answer 5 The contractor is responsible for providing their own equipment and job trailers.
Question 6 Will the contractor be responsible for verifying cold and dark status of the structures?
Answer 6 Yes. Refer to sheet G-002, “General Demolition Notes”, note #6.
Question 7 Will the contractor be responsible for providing a SWPPP for this project? If so, can the contractor anticipate approval from the state, prior to 60 days after award?
Answer 7 NCDEQ Stormwater permitting is not applicable to this project. Refer to sheet CG502.
Question 8 Are there any as-builts of the site for the structures or underground utility designs?
Answer 8 All available information is provided in the contract documents.
Question 9 Can the Superintendent carry a dual role on this project?
Answer 9 The superintendent can have a dual role as the Project Manager or the Safety Officer with their role.
Question 10 Does the site anticipate contaminants in the soil during excavation that will require special handing?
Answer 10 Refer to sheet G-002, “General Demolition Notes”, notes #13 & 14.
Question 11:
Is the Prime contractor required to have the same lics / certifications as the ACM abatement contractor they bring on-site?
Answer11 The Prime or their Subcontractor on site is required to have the license/certification as stated in the solicitation meeting all state, federal, and local requirements.
Question 12 Does the site anticipate needing traffic re-routed during the demolition of the structures?
Answer 12 Refer to sheet G-002, “General Demolition Notes”, note #4.
Question 13:
Will these structures be empty prior to demo? If not does the contractor need to price relocation of items or increased disposal qty beyond structure sizes?
Answer 13 The contractor will be responsible for disposal of any items remaining inside the structures.
Refer to sheet G-002, “General Demolition Notes”, note #15.
Question 14 Are any of the structures in this proposal located in the exclusion zone (ez) or contaminated reduction zone (CRZ)?
Answer 14 No.
Question 15 Will the contractor need to establish a Decon area for labor / equipment?
Answer 15:
No.
Question 16 Will all labor need to have HAZWOPER training prior to starting work?
Answer 16 Contractors are required to have OSHA hazard waste certification as stated in the solicitation.
Question 17 Can the govt verify that the designated laydown areas are close enough to utilities on-site and will not require temp setup?
Answer 17 Yes.
Question 18:
Does the govt anticipate needing to submit a permit to the State and EPS for Haz waste disposal?
If so, what is the expected approval times?
Answer 18 waiting on input from the Designer of Record (DOR).
Question 19
Does the govt anticipate needing to submit a permit to the State and EPS for Haz waste transport? If so, what is the expected approval times?
Answer 19 waiting on input from the Designer of Record (DOR).
Question 20 What are the recycling requirements for this project?
Answer 20 Refer to sheet G-002, “General Demolition Notes”, note #19.
Question 21 Is the contractor responsible for removing universal waste from the structures (ballast, lights, etc...), if so, will the site provide containers?
Answer 21 Refer to sheet G-002, “General Demolition Notes”, note #19.
Question 22 Is air sampling required during the lifecycle of the project?
Answer 22 No. Refer to sheet G-002, “Special Environmental Notes”, note #6.
Question 23 Will blood testing be required before and after the remediation of lead materials?
Answer 23 No.
Question 24 Please verify the noted deadlines referenced in the RFP are in Eastern Standard Time (local time to NC).
Answer 24 Yes, North Carolina is under the Eastern Standard Time.
Question 25 Does the "funding availability" outlined in the solicitation include all 53 structures or no award?
Or does the govt anticipate awarding even with partial funding, to pick from specific structures (ELIN) they want done?
Answer 25
It is the intent of the Government to funds the total project.
Question 26 If funding is available for this project, when does the govt anticipate award?
Answer 26 Funding will be issued upon issuance of the award/a fully funded contract.
(End of Summary of Changes)